Build a custom AI earthwork takeoff app in Piper
Build an earthwork balance and haul tracker around reviewed quantities, material eligibility, bank-to-compacted conversions and grading revision checks.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 10 min
- Published
On this page
- Define the material movements before the dashboard
- Specify the inputs that make a balance defensible
- Write conversion rules that cannot reverse themselves
- Work through a balance before building it
- Choose the data connection, not a prettier spreadsheet
- Give Piper an actual earthwork tool request
- Test the revision workflow before trusting the new balance
- Standardize the rules, not yesterday's ground conditions
For a GC estimator pricing a commercial site package at DD or bid stage, the first custom earthwork app worth building is a material balance and haul tracker, not a single cut-minus-fill calculator. It should answer which excavated material can serve which fill requirement, on what volume basis, and what must leave or enter the site.
Build that logic before asking Piper to build the tool. Piper supports plain-language construction app building on the same project documents and takeoff quantities used by the team. The proposed tool below starts with reviewed measurements and volume inputs. It does not assume a native surface-model engine or promise that contours alone produce a reliable cut/fill calculation.
The governing rule is simple: no net balance without a material assignment, a conversion basis and a review status. A grading change can alter all three without changing the app's formulas.
Define the material movements before the dashboard
Start with the decisions the sitework package needs to support:
- Is approved site material sufficient for each specified fill use?
- How much unsuitable material requires removal, separate from reusable surplus?
- What imported material is required, in compacted placement volume and delivered loose volume?
- Which quantities or assumptions need review before the GC carries the haul number?
Earthwork volumes change between the undisturbed bank state, the excavated loose state and the placed compacted state. FHWA's earthwork design guidance explicitly distinguishes these states and calls for project-specific geotechnical information when assigning shrink and swell factors. Its roadway guidance is a technical reference here, not a measurement or payment rule for every commercial site contract.
Use BCY for bank cubic yards, LCY for loose cubic yards and CCY for compacted cubic yards throughout the proposed tool. Never leave the state hidden behind a column labeled only “CY.”
Material suitability is a separate decision from conversion. WSDOT's Soil Cut Design guidance, Chapter 10 describes testing to determine whether excavated soil can be reused, including organic-content and compaction testing. A factor tells you how volume changes. It does not establish that the soil is acceptable beneath a slab.
For this app, define source lots and destination requirements separately. A source lot might be reusable common excavation in the west pad. A destination might be structural fill beneath the building. Link the two only after the team confirms eligibility under the project's geotechnical recommendations and specifications.
Do not apply this simplified tracker as a substitute for engineered slope design, a survey surface comparison or contract payment measurement. Where the source volume calculation belongs in a specialist workflow, keep that calculation there and bring its reviewed results and basis into the balance.
Specify the inputs that make a balance defensible
Write the input specification as if another estimator will take over tomorrow. Recommended fields are:
Area and ownership. Give each pad, parking zone, road segment or utility corridor a stable identifier. Record its extent, phase and scope owner. Do not use the parcel boundary as the default stripping boundary. Define the stripping area and exclusions from the actual package.
Volume basis. Record the volume method, existing-grade reference, proposed excavation reference and source revision. If a reviewed quantity came from a grid, retain its calculation basis. If it came from cross sections, retain the sections and spacing. FHWA describes average-end-area volume calculation as using adjacent section areas and their separation, and notes that the method is approximate. The tracker should preserve the method, not treat quantities from different methods as interchangeable observations.
Vertical reference. For the proposed app, define subgrade as finish elevation less the applicable pavement or slab assembly thickness. Keep finish elevation, assembly depth and resulting subgrade as separate inputs. If an incoming volume already terminates at subgrade, do not deduct that assembly again.
Material classification and eligibility. Distinguish reusable excavation, unsuitable removal, topsoil held for reuse and surplus approved material. Give each fill demand its required material class. Do not route every source to every destination just because both use cubic yards.
Supplemental excavation and replacement. Record geotechnical over-excavation, replacement fill and trench-related quantities separately, with an overlap treatment. WSDOT's August 2026 Earthwork Construction Manual addresses excavation below subgrade and replacement of soft or unsuitable material. Those provisions apply to WSDOT work, but they illustrate why a grading surface alone is not the complete excavation basis.
Factors and haul assumptions. Store each material's conversion multiplier, input state, output state, source page and review status. Keep effective truck load, destination, route assumption and quote basis separate from the soil factors.
For broader item naming and formula organization, use earthwork takeoff setup and structure tips. The custom app's job is to enforce the relationships between those inputs, not to repeat the measurement process.
Write conversion rules that cannot reverse themselves
Prefer explicit multipliers to a single ambiguous “shrink/swell percent” field:
- Compacted supply = approved reusable BCY × bank-to-compacted multiplier.
- Loose export = export BCY × bank-to-loose multiplier.
- Required import BCY = unmet CCY demand ÷ import bank-to-compacted multiplier.
- Delivered import LCY = required import BCY × import bank-to-loose multiplier.
These are proposed calculation rules. Confirm the source convention before entering a multiplier.
The convention matters. The Wisconsin-sponsored weight-volume research report distinguishes bank-to-loose expansion from compacted-to-bank expansion in its reporting. It is research on Wisconsin materials, not a national specification or a default factor library.
A bank-to-compacted reduction and a compacted-to-bank increase do not use the same denominator. Illustrative convention check: if 100 BCY becomes 90 CCY, the bank-to-compacted multiplier is 0.90. Converting back requires dividing by 0.90, not adding 10 percent. The reverse increase is approximately 11.1 percent.
The practical consequence is larger than a mislabeled heading. An app that reads “10 percent” from a report and assumes the wrong direction can produce a plausible import quantity with the wrong purchasing basis. Require the tool to display a test conversion beside every factor: “100 input yards becomes X output yards.” Have the reviewer confirm that sentence against the source.
WSDOT's geotechnical guidance also notes that factors depend on soil type, in-place density, fill construction and compactive effort. Therefore, request factors by material, not one global site factor. If the report supplies none, retain an estimator-approved assumption or an unresolved input. Do not manufacture a geotechnical value.
Work through a balance before building it
The following is a synthetic acceptance fixture, not a project result or a recommended soil factor. It is deliberately simple so the team can verify the proposed app by hand.
Assume the reviewed quantity inputs are:
- Total excavation: 10,000 BCY.
- Approved reusable excavation: 8,000 BCY.
- Unsuitable material assigned to export: 2,000 BCY.
- Compatible fill demand: 9,000 CCY.
- Reusable material bank-to-compacted multiplier: 0.90.
- Unsuitable export bank-to-loose multiplier: 1.25.
- Imported material bank-to-compacted multiplier: 0.90.
- Imported material bank-to-loose multiplier: 1.20.
- Effective load for each illustrative haul stream: 20 LCY per trip.
Approved site supply is 8,000 × 0.90 = 7,200 CCY. The compatible fill shortfall is 9,000 − 7,200 = 1,800 CCY.
That requires 1,800 ÷ 0.90 = 2,000 BCY of imported source material, or 2,000 × 1.20 = 2,400 LCY delivered. At the illustrative effective load, import requires 120 trips.
Separately, unsuitable export is 2,000 × 1.25 = 2,500 LCY, or 125 trips at the illustrative load.
The total-cut comparison suggests surplus because 10,000 exceeds 9,000. The material-compatible balance requires both import and export. That is the decision this tool must preserve: an unsuitable outbound stream cannot cancel a structural-fill purchase.
For the proposed truck calculation, divide each loose haul stream by its reviewed effective load and round trips upward. Treat that load as an input established for the actual vehicle, material and route. FHWA's truck size and weight resources cover federal standards and state enforcement; a body-volume assumption does not resolve applicable weight limits.
Trip count is not a haul price. Keep loading, travel, queuing, return time and disposal or supply charges in the pricing basis. FHWA's earthwork guidance describes haul cost in relation to equipment rates and actual movement time. This tracker should support the estimate, not imply that dividing by truck capacity prices the operation.
Choose the data connection, not a prettier spreadsheet
A well-maintained spreadsheet can implement all of this arithmetic. The distinction is how the quantities, source pages and decisions stay connected when the package changes.
| Review concern | Spreadsheet maintained beside the project | Tool built on Piper project data |
|---|---|---|
| Quantity inputs | Team enters or links reviewed quantities and maintains their revision references | Built tool can read project takeoff quantities alongside drawings, specs and addenda |
| Calculation rules | Team maintains formulas, factor definitions and validation checks | Team describes rules in plain language and reviews the resulting workspace file |
| Source evidence | Team maintains page references and links with the workbook | Numbers link back to source pages within the shared project context |
| Change response | Team establishes a process to identify affected inputs and update the workbook | Team can request a workflow automation that runs when project information changes |
| Reuse | Team distributes and maintains a controlled workbook template | Tested tools can be added to company project templates |
| Release judgment | Estimator confirms eligibility, factors and the carry | Estimator confirms eligibility, factors and the carry |
These Piper capabilities are described on Build with Piper. The balance and haul behavior is a tool specification to build and test, not a claim that an earthwork-specific app is supplied out of the box.
For a fixed, fully reviewed quantity set, a separate workbook may be sufficient. On a DD package with grading revisions, pavement-section changes and unresolved geotechnical recommendations, prioritize a tool whose outputs retain the connections needed to reopen the right decisions.
The custom takeoff app guide covers the cross-trade building pattern. Here, the distinctive requirement is preserving material compatibility and volume state through every calculation.
Give Piper an actual earthwork tool request
Piper lets teams describe what they need in plain language, then review and change the result like any other workspace file. What is built reads the same project context, including drawings, specifications, revisions, addenda and takeoff quantities. No coding is needed.
Use a request like this, adapting area names and review responsibilities to the job:
Build an earthwork balance and haul tracker for this project. Start with our reviewed takeoff quantities and reviewed cut/fill volume calculations. Organize source lots and fill destinations by area, phase and material class. Read the drawings, specifications, geotechnical report if present, and addenda for the basis behind each input. >Keep bank, loose and compacted cubic yards separate. Store every conversion as an input-to-output multiplier with its source and review status. Show a test conversion of 100 input yards for each multiplier. Ask me where a factor, material eligibility or source basis is unclear. >Allocate only approved reusable material to compatible fill demands. Show unsuitable export separately from reusable surplus. Calculate unmet compacted fill demand, required imported bank volume, delivered loose import volume, loose export volume and estimated trips using reviewed effective loads. Do not offset incompatible streams. >Include stripping, over-excavation, replacement fill and trench quantities with explicit overlap treatment. Identify whether each grading volume uses finish grade or subgrade. Keep unknown quantities unresolved rather than treating them as zero. >Build a dashboard and an assumption register with source references. When a revised grading sheet or addendum arrives, run a review workflow for affected areas and assumptions. Recalculate from updated reviewed inputs, show what changed, and keep the resulting balance pending estimator review before it becomes our carry.
This request separates the calculator from its evidence. Piper asks where a request is unclear instead of guessing, but the team still needs to inspect how the built result handles unknowns and incompatible materials.
For measurement inputs, Piper Takeoff supports manual, assisted and agentic PDF takeoff in one editable file. Assisted tools propose candidates that the estimator accepts or corrects; agentic takeoff starts from a measurement task and produces editable measurements for review. The earthwork takeoff walkthrough in Piper covers that separate workflow.
Test the revision workflow before trusting the new balance
Ask for a change-triggered workflow, not an unchecked replacement of the accepted number. Piper supports automations that run when something changes, with one step handing off to the next. The following is the desired earthwork review behavior to validate in the built tool.
When a grading revision or addendum arrives, request an affected-input register. It should identify the relevant area, changed source, quantity or assumption needing review, and downstream outputs requiring recalculation. Keep the previously accepted balance available for comparison.
Then use deliberate acceptance tests:
- Quantity change. Change the fixture's reviewed fill demand. Confirm that the app updates the compatible shortfall without turning unsuitable export into supply.
- Factor change. Change only the bank-to-loose import multiplier. Delivered loose volume and trips should change; compacted demand should not.
- Eligibility change. Withdraw approval from a source lot. The app should stop allocating that lot and expose the resulting unmet demand.
- Missing basis. Remove a required factor. Affected outputs should remain unresolved, not silently calculate with zero or a default.
- Overlap change. Mark a supplemental excavation quantity as already included in the base volume. Confirm that excavation and replacement are treated separately and neither is added twice.
These tests check dependencies, not just arithmetic. For a real revised pad, review the changed area and section basis before accepting a recalculation. The drawing revision cascade explains why the changed quantity must also reopen affected scope and bid assumptions.
Standardize the rules, not yesterday's ground conditions
Once the team has tested the file, add what works to company project templates. Piper supports reusing built tools in those templates, with the same workspace permissions and history as the rest of the project.
Carry forward the field definitions, conversion-direction checks, material allocation rules and acceptance fixture. Do not carry forward a prior project's shrink factor, disposal destination, truck load or geotechnical removal depth as an approved value for the next site.
The completed app should leave a precon manager with an inspectable material movement plan: where each source can go, what its volume becomes, which requirements remain unmet and which changed assumptions prevent release. That is more useful than a polished net-CY total.
FAQ
Can this app calculate earthwork directly from contours?
This proposed app starts from reviewed volume inputs; it does not assume native surface-model calculation. Record the method and source basis behind each quantity. Use the appropriate volume-calculation workflow before bringing its results into the balance, then review how the app allocates and converts those volumes.
What if the geotechnical report gives no shrink or swell factor?
Keep the factor unresolved or enter a clearly labeled, estimator-approved assumption with its basis. Do not have the app invent a project-specific value. Request clarification where the missing factor changes the import, export or haul decision, and distinguish that uncertainty from the measured geometry.
Should import and export be netted into one haul quantity?
Not when the material streams are incompatible. Keep unsuitable export, reusable surplus and required import separate. Compare usable site supply with compatible fill demand in a common volume state, then convert each outbound and inbound stream independently for its haul calculation.
Does a revised sheet mean the new balance is ready to carry?
No. It should trigger review of affected quantities and assumptions. Validate the built workflow's change handling, review the updated inputs and compare the resulting balance with the accepted version. The estimator still decides which quantity and pricing basis belong in the carry.
Related reading
What Changed? How Drawing Revisions Cascade Through Scope, Bids, and the Estimate
A drawing revision is not only a sheet delta. Trace what it does to trade scopes, live bids, and the estimate before bid day locks the number.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow