Build a custom AI electrical takeoff app in Piper
Build an electrical takeoff summary that separates measured feeders from branch allowances, preserves circuit assumptions, and sends revisions back for review.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 11 min
- Published
On this page
- Define four outputs before adding a cost total
- Give each electrical row a basis, not just a unit
- Calculate feeders from configuration plus route
- Make branch allowances replaceable, not cumulative
- Test changes that leave the headline count unchanged
- Build the summary on the project, then test the requested behavior
- Example request a team could type
- Request an addendum-driven review, not an unreviewed carry
- Questions before making the summary a company standard
For a GC estimator reviewing a commercial office package at DD or pricing a GMP, the first custom electrical tool should be a basis-controlled summary, not a calculator that turns every device into feet of wire.
Start with devices and fixtures by type, panels and gear, feeder route lengths, and a separately identified branch allowance per eligible device. Make the tool show which quantities are measured, which are derived from a documented configuration, and which are estimating assumptions. A total with those distinctions is useful. A total that hides them is not ready to carry.
You can build that summary in Piper by describing it in plain language. But define the electrical rules before asking for the app. The design below is a proposed tool specification and acceptance exercise, not a report of a completed implementation or tested performance.
Define four outputs before adding a cost total
Keep four outputs separate even if they eventually feed one estimate:
- Equipment and device counts: fixtures by schedule type, receptacles by type, lighting controls, panels, disconnects and gear.
- Feeder quantities: physical route LF, raceway LF by size and material, and conductor LF by size and function.
- Branch allowances: quantity derived from eligible devices and an estimator-approved basis, with measured branch work shown separately.
- Open decisions: missing routes, conflicting schedule information, unassigned controls and unresolved trade boundaries.
Do not make blank and zero interchangeable. A reviewed zero means the team has established that no quantity belongs in that row. A blank route means the feeder cannot yet produce a supported length. An allowance is neither of those: it is a positive carry with a stated assumption.
The distinction matters because the electrical information has different jobs. The current UFGS 26 20 00 Interior Distribution System, May 2025 with Change 2 dated February 2026, asks designers to show equipment locations, single-line diagrams, elevations, limiting dimensions and equipment ratings on drawings. Read that as a useful model for separating configuration from location, not permission to scale a schematic feeder line.
For lighting, UFGS 26 51 00 Interior Lighting, May 2020 with Change 2 dated November 2021, calls for a luminaire schedule with voltage, driver, dimming and mounting information, along with accessories and room control strategies. That supports a second rule: a fixture count is not a complete lighting package definition.
These are federal guide specifications, not universal commercial-project requirements. Their current public versions were checked on November 24, 2026. Use the project's issued drawings, edited specifications and addenda to populate the tool. Do not import unselected guide-spec options as contractual scope.
Give each electrical row a basis, not just a unit
The proposed summary should retain enough information to explain a changed number without rebuilding the estimate.
For a device or fixture, request its type, location or zone, count, schedule reference, source drawing, revision, new or existing treatment, branch-allowance eligibility and review status. Keep integrated accessories separate from field-installed companion items so the team can decide what the fixture price already includes.
For a feeder, request an identifier, from/to equipment, configuration source, route source, measured horizontal length, vertical additions, number of raceways, raceway specification, conductor configuration, and separately stated tails or slack. Leave conductor sizes and protective-device selections to the project's design basis and qualified review. This summary is not an electrical design approval tool.
For a branch allowance, request:
- The eligible device family and zone.
- The length basis per device, with units.
- Whether it includes drops, local interconnections, homeruns or connection tails.
- Wiring method and material basis.
- Conductor assumptions, if conductor quantities are being derived.
- Which measured rows replace which portions of the allowance.
- The estimator responsible for accepting the basis.
For a control system, use the room or control zone as a second grouping alongside fixture type. A schedule type tells you what the fixture is; it does not, by itself, settle what controls the room needs.
Use the same discipline for site lighting. UFGS 26 56 00 Exterior Lighting, August 2021, separately addresses luminaires, poles, brackets, foundations and grounding. Its drawing notes call for luminaire and accessory locations plus the control strategy. A sensible summary therefore needs support identifiers, not a rule that assigns one foundation to every light head.
For general takeoff item structure rather than app logic, use the companion electrical takeoff setup guide.
Calculate feeders from configuration plus route
A useful feeder calculator joins two records: the circuit configuration and the route measurement. Neither record alone is enough.
For underground distribution, UFGS 33 71 02, February 2026 with Change 1 dated May 2026, calls for duct and cable locations and conductor numbers and sizes on drawings. Section 3.10 describes a parallel arrangement containing phases A, B and C plus a neutral in each conduit. This is a source-specific arrangement, not a default for every feeder.
Illustrative feeder example, not a design recommendation: assume the issued configuration shows two parallel raceways, each containing three phase conductors and a neutral of the same scheduled size, plus one separately scheduled equipment grounding conductor. The accepted route consists of 120 LF horizontal and 18 LF vertical. The estimator allows another 6 LF of conductor per run for termination tails, but not another 6 LF of raceway.
The calculation should preserve all three bases:
- Route length: 120 + 18 = 138 LF.
- Raceway quantity: 138 × 2 = 276 LF of the scheduled raceway.
- Phase and neutral conductor quantity: (138 + 6) × 2 × 4 = 1,152 conductor LF of the scheduled size.
- Equipment grounding conductor quantity: (138 + 6) × 2 × 1 = 288 conductor LF of its separately scheduled size.
A single field named “feeder LF” cannot communicate those quantities. If 138 LF becomes the raceway total, the second raceway disappears. If 144 LF becomes the route basis for everything, conductor tails become extra raceway. If all five conductors roll into one size, the grounding conductor loses its material basis.
The acceptance test is not simply whether multiplication works. Remove the configuration source and require the output to show an unresolved configuration, not silently retain the last multiplier. Then change two raceways to three and check that the route remains 138 LF while the dependent material quantities change.
For underground runs through structures, add a separate cable-path adjustment where applicable. UFGS 33 71 02 Section 3.9 directs cables around structure walls rather than along the shortest path between penetrations. Read together with duct locations, that means duct route length and cable length may need different additions. The app should request that basis rather than force both into the same LF field.
Make branch allowances replaceable, not cumulative
Where branch routing is not drawn, ask the tool to calculate an explicit allowance. Do not ask it to present an inferred route as a measurement.
Competent estimators can reasonably choose different bases. On a repetitive office floor, a device-based allowance may serve a DD comparison. Where panel locations, circuit groups and routing constraints are sufficiently developed, a route-based quantity may be the better carry. What should decide the method is whether the available documents and reviewed assumptions support the route, not whether the tool can draw one.
Illustrative branch example: assume 80 receptacles are eligible for an allowance of 22 LF per device. Define that allowance as local interconnection and drops only. Homeruns are excluded from the allowance and measured separately at 360 LF.
- Local branch allowance: 80 × 22 = 1,760 LF.
- Separate measured homeruns: 360 LF.
- Combined estimating basis: 2,120 LF of raceway, subject to the assumed wiring method.
Now assume revised drawings establish 510 LF of local branch work serving 20 of those same receptacles. The tool should replace the allowance for those 20 devices:
- Remaining allowance: (80 − 20) × 22 = 1,320 LF.
- Measured local work: 510 LF.
- Measured homeruns: 360 LF.
- Revised total: 1,320 + 510 + 360 = 2,190 LF.
The increase is 70 LF, because 510 LF replaces 440 LF. Simply adding the new measurement to the original carry produces 2,630 LF, overstating the revised basis by 440 LF.
That is why each measured branch row needs a coverage relationship to the allowance it replaces. Do not merely subtract “measured LF” from “allowance LF”; they may describe different extents. Match the served devices and included work first.
If the 22 LF factor already included homeruns, adding 360 LF would be another overlap. Keep that inclusion statement visible beside the formula. Do not derive wire LF until the conductor basis is separately accepted.
Test changes that leave the headline count unchanged
The hardest acceptance test is a revision that changes scope without changing fixture count.
Suppose an illustrative room still contains 24 fixtures after an addendum. The revised schedule changes their dimming basis, while the revised control narrative calls for a different room-control arrangement. A summary grouped only by fixture count reports “no change.” A summary linked to schedule attributes and room controls should send the affected package back for review.
This check combines the interior-lighting guide's schedule requirements with its separate accessory and control-strategy requirements. The practical consequence is not necessarily another fixture. It may be different drivers, control equipment, wiring or testing scope. The app should identify affected rows and unanswered questions, not invent the replacement assembly.
Apply the same pattern to supports. Illustrative site-lighting acceptance case: 18 light heads consist of 12 heads on six twin-head poles and six building-mounted heads. The proposed summary should return 18 heads, six poles and six building-mounted locations. A foundation quantity of 18 fails even though the fixture count is correct. Foundation type and trade ownership still need their own evidence and review.
Use this proposed review register for both cases:
- Trigger: identify the changed drawing, schedule row, specification clause or addendum instruction.
- Dependency: identify the fixture, feeder, branch factor, control zone or support record that relies on it.
- Treatment: classify the change as quantity, configuration, scope, assumption or unresolved information.
- Decision: record the estimator's correction, clarification, carry or exclusion.
- Release: retain the reviewed basis before treating the affected subtotal as ready to carry.
An electrical total also needs coverage beyond the summary. Use electrical bid exclusions to review for package qualifications and MEP interface ownership for connections and handoffs the quantities alone do not assign.
Build the summary on the project, then test the requested behavior
Piper's construction app builder lets teams describe tools and changes in plain language, without coding. The result is reviewed like any other workspace file. Apps can read takeoff quantities, drawings, specifications, revisions, addenda, scopes, bids and decisions from the same project, without exports or copy and paste.
The underlying takeoff workflow supports manual, assisted and agentic measurement from PDF drawings in one editable takeoff file. Assisted tools propose boundaries, traces or similar-symbol candidates for the user to inspect and correct. Agentic takeoff starts with a measurement task and produces editable measurements grouped into items for review. Neither workflow removes review of scale, revision, geometry and coverage.
The custom summary should consume reviewed quantities and preserve their basis, not hide measurement review inside its formulas. For the product measurement sequence, see electrical takeoff in Piper; for reusable app design across trades, see the custom takeoff app guide.
| Decision | Spreadsheet maintained beside the project | Tool built on Piper project data |
|---|---|---|
| Quantity inputs | Team maintains copied quantities and their revision references | Reads takeoff quantities from the same project |
| Electrical formulas | Team defines and reviews feeder multipliers and branch factors | Team requests the same rules in plain language and reviews the result |
| Source basis | Team maintains source links and assumption records | Numbers link back to source pages; derived rules still need an explicit basis |
| Addendum treatment | Team identifies affected rows and updates the workbook | Team can request an automation triggered by an addendum, with review of affected rows |
| Reuse | Copy the workbook and reset project-specific assumptions | Add the tested tool to company project templates and reset project-specific assumptions |
A well-maintained spreadsheet can perform the arithmetic and retain source references. The reason to build on the project is to keep quantities, document changes and estimating decisions connected as the basis evolves.
Example request a team could type
Build an electrical takeoff summary for this project's current pricing package. Read the takeoff quantities, electrical drawings, fixture and panel schedules, one-line diagrams, specifications and addenda. Group devices and fixtures by type and zone, and list panels and gear separately. For each feeder, keep configuration evidence separate from route evidence. Show route LF, raceway LF by size and material, conductor LF by size and function, and separate vertical, tail and cable-path additions. Do not scale schematic one-line lengths. Create a branch allowance per eligible device using factors I supply, with an inclusion statement for drops, local runs and homeruns. Match measured branch work to the devices and scope it replaces so it is not added twice. Keep lighting controls by room or zone and site-lighting supports separate from light heads. Show missing information as an open question, not zero. Include source references, assumptions and estimator review status. Ask me where a rule or input is unclear.
This is a specification to review with Piper, not a promise that every requested rule arrives correctly on the first attempt. Piper's published workflow says it asks where requests are unclear and lets teams request changes to what they build.
Request an addendum-driven review, not an unreviewed carry
Piper supports workflow automations that run when something changes, including an addendum arriving, and one step can hand off to the next. A suitable follow-up request is:
When an electrical addendum arrives, review it against this summary's quantity sources and rule assumptions. Produce a change register for affected fixtures, controls, feeders and branch allowances. Distinguish a document change from a reviewed quantity change. Keep unresolved routes and configurations visible, and require estimator review before I use revised subtotals in the carry.
Test that request with the feeder multiplier change, branch replacement and count-neutral lighting revision above. Review the formulas, source references, treatment of missing inputs and proposed change register as workspace files. Correct the tool in plain language where the result does not follow the requested basis.
Once that behavior is useful, add it to company templates. Piper keeps built tools in the workspace with the same permissions and history as the rest of the project. Carry forward the field structure, review rules and acceptance examples, but require each new project to establish its own wiring methods, feeder configurations, branch factors and scope boundaries.
Questions before making the summary a company standard
FAQ
Can the tool calculate branch circuit lengths when routing is not drawn?
It can calculate a requested estimating allowance using team-supplied factors, but that output should remain labeled as an assumption. Define eligible devices and whether the factor includes drops, local runs and homeruns. Replace only the portion of the allowance covered by later reviewed measurements.
Should feeder LF come from the one-line diagram?
Use the one-line for the documented circuit configuration, not as a scaled physical route unless the drawing expressly provides that basis. Require a separate route source and vertical additions. Keep raceway quantity, conductor quantity and termination allowances in distinct fields so one length does not silently stand for all three.
What should happen when an addendum changes controls but not fixture counts?
The requested automation should identify affected schedule attributes, control zones and assumptions for review even if the fixture total stays unchanged. Test that behavior before relying on the tool. The estimator then decides what changes in the scope, quantity basis or carry rather than accepting “no count change” as “no cost change.”
Does building the summary remove takeoff review?
No. Piper's manual, assisted and agentic takeoff measurements remain reviewable and editable, and the estimator still checks source sheets, scale, geometry, revision and coverage. The custom summary adds another review obligation: confirm that formulas, inclusion rules and replacement relationships correctly interpret those quantities before carrying the result.
Related reading
Common Electrical Bid Exclusions GCs Should Review
Review electrical exclusions, temporary power, equipment interfaces, testing and closeout against the actual package requirements before choosing the carry.

MEP coordination in preconstruction: assign the interfaces before comparing trade prices
MEP coordination can reveal responsibilities beyond one trade’s drawings. Review supports, openings, controls, access, testing and complete package coverage.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.