Build a custom earthwork bid leveling tool in Piper
Build an earthwork leveling tool around material balance, volume states, exclusions and revisions, with source-backed adjustments and estimator-owned carry.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 11 min
- Published
On this page
- Define the material movement before designing the comparison
- Make volume state part of the unit, not a comment
- Work the comparison through removal, replacement and water
- Build an exclusion library that follows consequences
- Separate proposed plugs from approved adjustments
- Keep the tool on the project, not beside it
- Give Piper a request the team can test
- Questions before making the earthwork tool a company template
For a GC estimator leveling a warehouse site package at bid-stage CDs, the custom tool should answer one question: what would each proposal cost on the same earthwork basis, and what remains unresolved? A sorted list of totals is not enough. The comparison needs a material balance, explicit volume states, linked removal and replacement scope, and a record of which proposal revision supports each adjustment.
Piper lets teams describe a tool in plain language and build it on the same project documents, quantities, scopes and bids used by its other workflows. Its Build with Piper documentation describes registers, workbooks and change-triggered automations, with the result reviewed like any workspace file. The estimator still approves the assumptions and carry.
Start by defining the earthwork rules below. Then ask Piper to build around them. The custom tool is valuable when it preserves the basis behind the number, not merely your preferred bid-tab layout.
Define the material movement before designing the comparison
This guide applies to GC comparison of earthwork subcontractor proposals. It is not a replacement for an owner's bid schedule, contractual measurement rules, geotechnical design or excavation safety planning. On an early GMP, label unresolved design assumptions rather than making the tool produce a false fixed scope. The distinction is developed in estimating design intent from incomplete drawings.
A useful reference for the row structure is UFGS 31 00 00, Earthwork, August 2023, the active guide edition checked for this article. It separately addresses structural fill, utility bedding, drainage and dewatering, subgrade preparation, finishing and testing. It also directs the specifier to tailor the guide to the project. Those categories are review prompts, not automatic assignments to the earthwork subcontractor.
For the warehouse package, request these groups of rows:
- Surface preparation: clearing, stripping depth, topsoil stockpile, disposal and later respreading. Separate these quantities from structural cut and fill.
- Bulk grading: cut by material classification, approved reuse, stockpile handling, import and export. Identify the excavation and placement limits.
- Building pad: structural fill, scheduled over-excavation, proof rolling, moisture conditioning and compaction. Keep defined excavation separate from an allowance for field-directed unsuitable removal.
- Trade interfaces: utility trench excavation and backfill, pavement subgrade, landscape finish grading and topsoil. Record the handoff surface or elevation, not just a trade name.
- Temporary and support work: drainage, dewatering, discharge treatment, erosion-control installation and maintenance, surveying/layout, testing and permits where applicable.
Every row should contain a project requirement and source, proposed trade owner, bidder inclusion or exclusion, quantity and unit, measurement basis, price treatment, clarification and reviewer disposition.
A row called “fine grading included” should remain unresolved until the estimator knows whether it means pavement subgrade, aggregate base trimming or landscape finish grading. These are different handoffs. Request a boundary stated as a surface and acceptance condition, then check the adjacent proposal for matching coverage.
For general leveling mechanics, use the construction bid leveling guide. The custom earthwork tool should concentrate on the material movements and interfaces that change this package's comparison.
Make volume state part of the unit, not a comment
Treat “CY” without a defined state as an open clarification. Use bank cubic yards (BCY), loose cubic yards (LCY) and compacted cubic yards (CCY) as distinct units in the requested register.
The December 2023 WisDOT-sponsored weight-volume research report distinguishes bank, loose and compacted states and notes that factor terminology and calculation procedures vary among sources. It is research on Wisconsin materials, not a standard or a source of universal factors. Its useful implication here is that a field labeled “shrink factor” is incomplete without a conversion direction and formula.
Specify these normalization rules:
- Preserve the bidder's original unit and quantity beside the comparison basis.
- Store the conversion as an explicit relationship, such as “1 BCY yields 0.80 CCY,” with its source and approval status.
- Convert quantities into the rate's stated unit before extending that rate.
- Do not turn a lump-sum proposal into a quantity-adjustable contract merely because the tool can calculate an implied unit cost.
- Keep material balance, haul quantity and payment quantity separate. A delivery-ticket quantity need not be the project's compacted placement quantity.
For a reusable material yielding `r` CCY per BCY, the comparison calculation is:
Required bank volume = required compacted volume ÷ r.
For that material stream, proposed import is the required bank volume less approved reusable bank volume, subject to a minimum of zero. This is a planning relationship, not a contractual payment rule. Keep unsuitable soil, topsoil and material that fails the specified fill criteria out of approved reuse.
The source interaction matters: the grading drawings establish geometric demand, while the project fill criteria establish which excavated materials can satisfy it. A cut/fill balance that ignores material eligibility can report a balanced site while the price still needs both disposal and import.
Work the comparison through removal, replacement and water
Illustrative example only. The quantities, prices and conversion relationship below are synthetic acceptance-test inputs, not benchmarks, customer results or a geotechnical recommendation.
Assume the estimator approves this comparison basis:
- Scheduled fill demand is 6,000 CCY, excluding the additional replacement described below.
- Approved reusable excavation is 5,000 BCY, excluding unsuitable material.
- The illustrative yield is 0.80 CCY per BCY for both approved reuse and the proposed import material.
- A separate comparison allowance covers 800 BCY of unsuitable removal and disposal, plus 600 CCY of replacement fill.
- Both proposals' other scope is assumed comparable after review.
The scheduled fill requires 6,000 ÷ 0.80 = 7,500 BCY. Deducting 5,000 BCY of approved reuse leaves 2,500 BCY of scheduled import.
Bid A is $280,000. It includes 1,500 BCY of scheduled import, a $15,000 removal/disposal allowance representing 500 BCY at $30 per BCY, and pumping. It excludes replacement for the unsuitable allowance and discharge treatment and inspection scope. Its clarified import rate is $24 per BCY, covering the specified material, delivery, placement and compaction.
Bid B is $330,000. For this test, assume its written clarification confirms all 2,500 BCY of scheduled import, the 800 BCY removal/disposal allowance, 600 CCY replacement and the same defined water-control package.
| Comparison item | Bid A | Bid B |
|---|---|---|
| Raw proposal | $280,000 | $330,000 |
| Scheduled import shortfall | 1,000 BCY × $24 = $24,000 addback | Included |
| Removal/disposal allowance increase | 300 BCY × $30 = $9,000 addback | Included |
| Replacement fill outside scheduled demand | 600 CCY ÷ 0.80 × $24 = $18,000 addback | Included |
| Discharge treatment and inspection scope | $9,000 illustrative reviewed plug | Included by clarification |
| Evaluated comparison | $340,000 | $330,000 |
Bid A's adjustments total $60,000: $24,000 + $9,000 + $18,000 + $9,000. Its raw $50,000 advantage becomes a $10,000 higher evaluated position.
The useful lesson is not the addition. It is the dependency: increasing an unsuitable removal allowance can create replacement demand outside the scheduled grading balance. A removal-only row cannot reveal that exposure. Conversely, adding replacement again when the fill model already includes it would overstate Bid A.
Require the tool to identify whether replacement is already inside the takeoff demand before drafting the adjustment. Also require the clarified $24 rate to have the same scope for the replacement material; if it does not, the $18,000 extension remains unresolved. A unit-price label alone does not establish that scope match.
Neither evaluated total is an automatic carry. On a hard bid, the chief estimator must decide whether the clarification and plug evidence are adequate to commit. On a developing GMP, the team may preserve the uncertain quantity as a separately identified allowance. The software should show that judgment, not hide it inside a normalized total.
Build an exclusion library that follows consequences
Use the library to suggest checks, not default addbacks. Each entry should connect the proposal wording to a current project requirement, affected quantities, adjacent trade and possible price treatment. The broader method belongs in reviewing subcontractor exclusions and qualifications.
For this tool, ask for these earthwork entries:
- Rock excluded: compare the bidder's classification with the project's definition and bidding basis. Do not price every difficult excavation as rock. UFGS 31 00 00 distinguishes hard/unyielding material from rock; the issued project definition must control the review.
- Unsuitable soil excluded or allowance-limited: connect removal, disposal, replacement source, replacement placement and quantity measurement. Keep documented scheduled over-excavation separate from uncertain field-directed work.
- Dewatering excluded or “pumping included”: split excavation water control from treatment, discharge routing, inspection and operating duration.
- Testing excluded: identify who performs acceptance testing and who carries contractor testing or retesting if required. Do not infer an assignment from the word “testing.”
- Erosion-control maintenance excluded: identify maintenance through the defined handoff, including who owns later repairs and removal under the issued scope.
- Surveying/layout or permits excluded: link the exclusion to the responsibility assignment before adding cost. A covered GC obligation is not a missing earthwork subcontract item.
The water entry deserves a compound check. OSHA 29 CFR 1926.651(h) requires adequate precautions against accumulated water and competent-person monitoring when water-removal equipment controls accumulation. For sites covered by EPA's 2022 Construction General Permit as modified in 2025, Part 4.3.2 requires dewatering inspection once per discharge day, and Part 4.6.3 requires the associated report within 24 hours.
These requirements serve different purposes. Pumping coverage does not, by itself, prove discharge inspection coverage. UFGS also connects drainage measures to preventing soil instability and defines material that can become unstable through ineffective drainage or dewatering. Read together, these sources justify three linked review questions: who controls the excavation water, who carries applicable discharge obligations, and how is water-related material deterioration treated in the proposal?
That is a scope check, not a finding that every pumping bid is defective. The contract, permit and subcontract assignments decide the actual obligation. EPA's CGP applies where EPA is the permitting authority; state requirements can differ. As checked November 24, 2026, EPA still describes the 2027 replacement permit as proposed. Store the applicable issued permit basis, not a universal EPA rule.
Separate proposed plugs from approved adjustments
Request distinct fields for raw bid, draft adjustment, reviewer-approved adjustment and unresolved exposure. Those are different states of the decision.
For every proposed plug, require:
- The requirement not covered and the proposal evidence supporting that conclusion.
- Quantity, material state, rate scope and source of the amount.
- A check against existing allowances and coverage in other packages.
- Clarification status, responsible reviewer and final treatment.
In the example, the $9,000 water plug is a reviewed illustrative estimate, not a value extracted from Bid A. Its record should say so. The $9,000 removal adjustment is different: it extends a clarified proposal rate against the additional comparison quantity.
A competent estimator may prefer a priced clarification over a GC plug for uncertain groundwater duration. Another may carry a documented GC allowance when the earthwork subcontractor excludes that risk. What should decide it is the water basis, duration, assignment and available pricing evidence, not which treatment makes the low bidder remain low.
Keep the tool on the project, not beside it
A spreadsheet can retain formulas, history and source links. The distinction is the work required to keep those connections current, not the presence of cells.
| Review need | Spreadsheet on the side | Custom tool on project data |
|---|---|---|
| Proposal basis | Team enters values and maintains links to proposal revisions | Built work reads the same project bids and sources as Piper |
| Volume conversion | Team maintains formulas and approved factor references | Request explicit unit relationships and review the built calculations |
| New bid or addendum | Team reconciles imported values and affected comments | Change-triggered automation can prepare the next review |
| Adjustment authority | Team controls approvals through its chosen process | Request draft and approved treatments; estimator retains the decision |
| Company reuse | Copy the structure and reset job-specific assumptions | Add tested work to company templates, then establish each project's basis |
The last column combines Piper's documented building capabilities with the design requirements recommended here. It is not a claim that a finished earthwork application already ships with all these rules.
Give Piper a request the team can test
Use this as an example plain-language request, then review and change the result:
Build an earthwork bid leveling register for this warehouse site package using our trade breakdown. Read the proposals, issued scope, grading drawings, specifications, geotechnical information provided in the workspace, addenda and takeoff quantities. Keep raw proposal amounts and bidder units visible beside the comparison basis. Organize rows for surface preparation, bulk grading, building pad, import/export, unsuitable removal and replacement, utility interfaces, finish-grade handoffs, water controls, erosion-control maintenance, testing, layout and applicable permits. >Show bank, loose and compacted quantities separately. Ask for clarification when a unit, conversion relationship, material eligibility or responsibility is unclear. Use only reviewer-approved conversion relationships for proposed extensions. Check whether replacement fill is already included in scheduled demand before proposing an addback. >Include an exclusion register and clarification log linked to the requirement and proposal sources. Each clarification should identify the affected row, question, recipient, response, price effect and reviewer treatment. Separate proposed plugs, approved adjustments and unresolved exposures. Show raw and evaluated positions without approving a carry. >When a new or revised earthwork bid arrives, prepare the comparison against current project scope, identify changed proposal terms, and list earlier clarifications and adjustments that need review. Keep their prior basis available rather than treating silence in the new quote as confirmation. Leave consequential assumptions and the final carry for our estimator.
Piper's Bid Leveling workflow supports extracting proposal terms, comparing bids against intended scope and surfacing gaps with sources. Build with Piper supports automations triggered by a new bid or addendum, with one step handing off to the next. The request defines how your team wants that work organized; it does not prove every requested behavior until the built result is inspected.
Review it like any workspace file. Test the synthetic example above, then change Bid A's clarification to include replacement and verify that the proposed $18,000 addback is removed only from the affected comparison. Next, provide a revised bid that changes the import rate but leaves the old water clarification uncertain. The desired result is a changed extension and an open water-review item, not wholesale approval of the revised total.
Also test an addendum that changes pad limits while leaving a prior proposal untouched. The tool should prepare review of the affected quantity basis rather than assume the quote absorbed the change. The wider dependency is explained in how drawing revisions cascade through scope, bids and the estimate.
Once the team accepts the structure and checks, add the working tool to company templates. Carry forward row definitions, conversion conventions and review rules. Reset project quantities, factors, permit applicability, material assumptions and trade assignments. The reusable asset is the company's decision method, not the last site's soil balance.
Questions before making the earthwork tool a company template
FAQ
Does building the tool require coding?
No. Piper's Build with Piper documentation says teams describe what they need in plain language and Piper builds and changes it. Review the result like any other workspace file. The work here is defining the earthwork quantities, boundaries and approval rules clearly enough to test.
Can the tool compare unit-price and lump-sum earthwork bids?
Request a common comparison basis while preserving each proposal's original pricing terms. Convert quantities into the clarified rate unit and distinguish proposed adjustments from contractual entitlements. A calculated implied unit cost does not turn a lump-sum quote into a quantity-adjustable agreement.
What should happen when a revised proposal arrives?
Request a fresh comparison against current scope and a list of prior clarifications and adjustments needing review. Piper supports change-triggered automations, but the team must inspect the built behavior. Silence in a revised quote should not be treated as acceptance of an earlier clarification.
Does Piper choose the earthwork subcontractor or carry number?
No. Piper extracts, checks and supports the comparison; consequential assumptions and the final carry remain estimator decisions. The custom tool should preserve that boundary by separating proposed adjustments, approved treatments and unresolved exposure instead of converting a calculated total into an approved commitment.
Related reading
What Changed? How Drawing Revisions Cascade Through Scope, Bids, and the Estimate
A drawing revision is not only a sheet delta. Trace what it does to trade scopes, live bids, and the estimate before bid day locks the number.

Construction bid leveling: a practical guide for GCs
How to level subcontractor bids across design-bid-build, CM-at-risk, design-build, and progressive design-build, and why the same spreadsheet does not work for all of them.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow