Build a custom earthwork scope and gap register in Piper
Build an earthwork register that connects soil assumptions, trade boundaries, bidder answers and addendum impacts, with estimator review before scope is issued.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 10 min
- Published
On this page
- Hold three answers for every earthwork requirement
- The minimum useful record
- Use earthwork boundaries as the tool's structure
- Test the register with a material change that moves two quantities
- Give dewatering two closure paths, not one checkbox
- Compare maintenance work, not spreadsheet capability
- Ask Piper for the review behavior in plain language
- Trigger a review when an addendum arrives
- Review the built file before making it the company template
On a ground-up commercial project at bid CDs or a CMAR earthwork package at DD, build the register around what must be decided before the scope is issued, not around a longer list of excavation tasks. Each material requirement needs its source, location, assigned package, quantity basis, bidder response and unresolved pricing treatment connected.
Piper's Build with Piper workflow lets teams describe a register or automation in plain language, build it on the same project information used elsewhere in the workspace, and review the result like any other file. The useful part is not replacing a scope-sheet format. It is keeping a geotechnical assumption connected to the grading scope, the utility boundary and the number carried when an addendum changes that assumption.
This guide specifies a tool and a review exercise. It is not a report of a completed build or a claim that Piper resolves soil conditions automatically. Use a narrower quantity-checking tool if ownership, scope and pricing basis are already settled.
Hold three answers for every earthwork requirement
A single “included” field is insufficient. The register should distinguish:
- Requirement: What work do the current project documents call for?
- Assignment: Which package will furnish, execute, protect or verify it?
- Pricing treatment: Where is the cost carried, and on what basis?
A geotechnical report can recommend undercutting a building pad without establishing whether the earthwork bidder included it. An earthwork scope can assign undercutting without establishing whether disposal and replacement fill are in the same price. A bidder can acknowledge the addendum while leaving its earlier unsuitable-soil exclusion intact.
These are proposed checks, not findings about a particular project. Their value is that one affirmative answer cannot close all three questions.
The active August 2023 UFGS 31 00 00 Earthwork guide specification, with references aligned to July 2026, distinguishes structural fill, utility bedding, satisfactory material, unsatisfactory material and unstable material. It also separates excavation, subgrade preparation, backfill and testing. It requires editing for project-specific conditions; its bracketed choices are not universal requirements.
Use those distinctions to design the register, then populate it from the issued documents for the actual job. Do not substitute the guide specification for the project's geotechnical report or contract. For the scope-writing decision itself, use the earthwork scope-of-work guide.
The minimum useful record
Ask for one record per distinct location and obligation, with these connected fields:
- Identity and location: Stable item identifier, building pad or site zone, and affected work.
- Evidence: Document title, page or detail, revision and source link. Separate an explicit requirement from an estimator assumption.
- Boundary: Proposed responsible package, adjoining package and the handoff condition.
- Quantity basis: Bank, loose or compacted volume; material class; conversion assumption and its source.
- Commercial basis: Lump sum, unit price or allowance; included operations; disposal destination or haul assumption when relevant.
- Open question: Exact clarification needed, responsible reviewer and required decision before issue or carry.
- Bidder response: Proposal reference, qualification or exclusion, clarification response and whether pricing was revised.
- Change treatment: What changed, which earlier decision may be stale, and what the estimator accepted or reopened.
These are requested fields, not existing Piper interface labels.
Split a row when it contains different owners or different closure conditions. “Utility trench excavation and final grading” may require separate records even when one bidder prices both. Otherwise, accepting the trench price can accidentally close the paving handoff.
Use earthwork boundaries as the tool's structure
A useful starting structure follows interfaces rather than specification headings: building pad, pavement subgrade, landscape soil zone, utility corridors, temporary drainage, and import/export.
For each interface, define the condition that ends one package's work and starts another's. In a pavement area, ask for the delivered elevation, compaction basis, tolerance, protection period and treatment of damage after the handoff. In a landscape area, distinguish stripping and stockpiling from placing the specified planting soil. In a utility corridor, separate excavation, bedding, backfill, testing and restoration.
This is estimating advice. No universal trade assignment follows from the word “earthwork.” The UFGS guide itself addresses trench excavation, bedding and initial backfill separately from final backfill, including different final-backfill applications beneath pavement and in turfed areas. That organization supports a boundary check, not a conclusion about which subcontractor must carry it.
Competent estimators can disagree about assigning all trench excavation to the utility contractor. On a small site, one earthwork operation may offer a practical excavation sequence. On a phased site, the utility contractor may need direct control of its trench production. Decide from access, sequence, equipment responsibility and the actual proposals, not the company's last scope sheet.
The tool should retain the rejected assignment and the reason for the accepted one. At buyout, “earthwork owns excavation” is less useful than “earthwork owns this corridor's excavation through the stated handoff; utilities own bedding, pipe-zone backfill and subsequent restoration.” The example is illustrative scope language and still needs project review.
For the broader interface search, refer to earthwork scope gaps rather than adding every possible exclusion to this custom tool.
Test the register with a material change that moves two quantities
Illustrative review fixture, not a project result: A commercial building pad requires 4,000 compacted cubic yards of fill. The initial plan identifies 5,000 bank cubic yards of cut as available for reuse. For this test only, assume each bank cubic yard of acceptable cut yields 0.80 compacted cubic yard.
The starting balance is:
5,000 BCY × 0.80 = 4,000 CCY available.
Now introduce a synthetic addendum and geotechnical clarification: 1,000 BCY within the planned excavation is unsuitable for structural fill, and a further 600 BCY of undercut below the previous design surface must be removed and replaced. Assume that additional undercut creates a 600 CCY replacement requirement measured to the same excavation geometry.
The revised calculation is:
- Reusable cut: 5,000 − 1,000 = 4,000 BCY.
- Compacted fill available: 4,000 × 0.80 = 3,200 CCY.
- Compacted fill required: 4,000 + 600 = 4,600 CCY.
- Imported fill shortfall: 4,600 − 3,200 = 1,400 CCY.
- Unsuitable material to dispose of: 1,000 + 600 = 1,600 BCY.
Assume, illustratively, $38 per CCY for imported fill delivered, placed and compacted, and $18 per BCY for unsuitable excavation, loading, haul and disposal. Assume neither cost is already covered, and no deduction is due from the base price for this fixture.
1,400 × $38 + 1,600 × $18 = $53,200 + $28,800 = $82,000 incremental exposure.
The failure is not simply forgetting unsuitable-soil removal. A removal-only check would show $28,800 while missing $53,200 of fill cost. The revised material classification reduces the supply, while the deeper excavation increases the demand. The register must connect both effects to the same change.
The December 2023 WisDOT-sponsored weight-volume research report distinguishes bank, loose and compacted states and explains that conversion conventions vary among agencies and sources. It is research, not a specification or regulation. Its material factors are not defaults for this commercial-project fixture. The 0.80 yield above is deliberately synthetic.
Specify the conversion direction in words and in the formula. “20% shrink” alone leaves too much room for interpretation. Also keep payment units separate from production units: do not apply a compacted-yard fill rate to a bank-yard disposal quantity.
Ask the tool to flag these four affected decisions for review:
- Does the revised source actually establish both the unsuitable zone and the additional undercut?
- Who owns removal, disposal and replacement, including any change to the utility boundary?
- Does the proposal's unit price include every operation used in the test calculation?
- Does the estimate already carry any of these costs, requiring a deduction or reallocation?
That is a more demanding acceptance test than asking whether the tool found the words “unsuitable material.”
Give dewatering two closure paths, not one checkbox
A second test should combine a safety obligation with a discharge obligation.
OSHA 29 CFR 1926.651(h) prohibits employee work in excavations with accumulating water unless adequate precautions are taken. Where water-removal equipment controls accumulation, a competent person must monitor the equipment and operations.
Separately, for projects covered by EPA's modified 2022 Construction General Permit, Part 2.4 requires dewatering discharge controls, and Part 4.3.2 requires inspection during discharge once each day discharge occurs. EPA's current permit page lists the modified 2022 permit and identifies the 2027 permit as proposed. Confirm the project's actual permitting authority and coverage; state, tribal and local requirements can differ.
The estimator's inference is important: a pump inclusion does not establish discharge-treatment coverage, and a discharge inspection does not establish excavation-safety monitoring. They have different purposes and may have different responsible parties.
In the proposed register, separate pump operation, safety monitoring, treatment equipment, discharge inspection and reporting. Link them to one dewatering issue, but close them independently. Do not treat assigning work to a subcontractor as transferring an operator's regulatory obligations.
Run a synthetic proposal through the check: “Dewatering included; environmental compliance by others.” The useful output is an unresolved boundary, not an automatic add-back. The reviewer must establish the discharge route, applicable permit, treatment responsibility and pricing treatment before deciding the carry.
Compare maintenance work, not spreadsheet capability
A spreadsheet can hold source links, formulas, revision history and decision notes. The decision is how much separate maintenance the team wants to own as those connections change.
| Review concern | Spreadsheet scope sheet | Custom tool on Piper project data |
|---|---|---|
| Evidence connection | Team maintains page links and revision references in the sheet | Built work reads the project's documents and source-traced information |
| Trade boundary | Team records assignments and follows up across package sheets | Request connected boundary records and open questions on shared project data |
| Quantity assumption | Formulas can retain units and conversion direction if deliberately structured | Request the same explicit unit checks using quantities and decisions the project already holds |
| Addendum review | Team finds affected rows and records what was reopened | An automation can review an arriving addendum against affected scope; estimator reviews the consequences |
| Bidder clarification | Team links proposal revisions and answers to the relevant rows | Request clarification records connected to scopes, bids and decisions |
| Reuse | Template is useful when old job assumptions are cleared | Add a tested tool to company templates, keeping project-specific answers subject to review |
The Piper column describes a build specification supported by its shared-data and automation capabilities, not a claim that this particular register is supplied out of the box. The spreadsheet remains a sound choice when a team has a bounded package and a disciplined way to maintain its references.
Ask Piper for the review behavior in plain language
Use a request like this as a starting point:
Build an earthwork scope and gap register for this project. Use the current drawings, specifications, addenda, geotechnical information, trade scopes, takeoff quantities, subcontractor proposals and recorded decisions available in the workspace. Separate requirements from estimator assumptions. For each material item, retain its source page and revision, location, proposed package owner, adjoining package, quantity and volume state, pricing treatment, open question, bidder clarification and reviewer decision. Organize the work around the building pad, pavement subgrade, landscape zones, utility corridors, drainage and import/export. Flag unsupported assumptions and conflicting assignments for review. Ask me where the structure or responsibility is unclear.
This requests a register, not a licensed geotechnical determination. Piper's public app-building description supports plain-language creation and changes, registers, trackers, workbooks and workflow automations. Built work reads the same project information as Piper, including drawings, specifications, revisions, takeoff quantities, scopes, bids and decisions. The result remains in the workspace with the same permissions and history.
Use Scope Generation for drafting trade-specific requirements and surfacing uncertain ownership with source references. The custom register adds your company's desired review structure around that work; it should not become a second, disconnected scope basis.
For the broader build pattern, see building a custom scope tool in Piper. For preparing the underlying draft, use the earthwork AI scope-generation sequence.
Trigger a review when an addendum arrives
A separate plain-language request should define the event and the boundary of the automation:
When an addendum arrives, review it against the earthwork scope and gap register. Surface affected requirements and potentially stale assumptions, boundary assignments, bidder clarifications and pricing treatments. Explain the source of each proposed impact. Prepare the affected items for estimator review; do not treat the addendum's arrival or acknowledgment as approval of a revised scope or carry.
Piper's approved app-building workflow includes automations that run when something changes, specifically reviewing an addendum against the scopes it affects. One step can hand off to the next. That supports initiating the review, not settling the consequential decisions.
Test the automation request with the material-change fixture above. A useful review should identify the earlier reuse assumption, the extra replacement demand, the affected proposal and the estimator decision that needs reopening. Also test an unrelated architectural addendum. The goal is justified attention, not reopening the entire earthwork package after every incoming document.
A change can affect the estimate without changing the earthwork scope's wording. For example, a clarified yield assumption can change an import allowance while the assigned work stays the same. Keep that distinction visible. The broader drawing-revision cascade explains why revision review must follow downstream commitments.
Review the built file before making it the company template
Review the result like any other workspace file. Start with a known source, a known exclusion and a known revision, then inspect whether the requested connections are present. This is a proposed acceptance exercise, not evidence of completed testing.
Require the reviewer to answer:
- Can each material requirement be traced to the correct page and revision?
- Are missing units or conversion assumptions left unresolved rather than guessed?
- Can assignment be accepted while pricing treatment remains open?
- Does a bidder's revised response address the specific issue, rather than merely acknowledge the addendum?
- Does the material-change fixture retain both supply and demand effects without counting existing costs again?
- Does the dewatering fixture preserve both safety and discharge responsibilities?
Ask Piper to change the tool where the requested behavior is missing or unclear. Only then add what works to company templates, a capability described in Build with Piper.
Reuse the structure, questions and closure logic. Do not reuse the last project's soil yield, disposal assumption, permit basis or accepted trade assignment as if it were a company standard. The register earns its place when it preserves why the scope changed and what still needs a person to decide.
FAQ
Can I build this earthwork register without coding?
Yes. Build with Piper lets teams describe registers, trackers and automations in plain language and ask for changes the same way. Review the result like any other workspace file. The earthwork fields and checks in this guide are a proposed build specification, not named interface features.
Will Piper decide whether excavated material can be reused?
Do not use the custom register to make that technical determination. Ask it to connect the project's material requirements, geotechnical information, quantities and bidder assumptions, then surface conflicts for review. Acceptance must follow the actual project requirements and the responsible technical review, not an inferred soil classification.
What should happen when an earthwork addendum arrives?
Trigger review of affected scope items and potentially stale decisions, not automatic acceptance of revised scope or cost. Keep the changed source connected to the assignment, bidder clarification and pricing treatment. Acknowledging receipt does not establish that a proposal now covers removal, disposal and replacement fill.
What belongs in the reusable company template?
Keep the field structure, source requirements, boundary questions, explicit unit conventions and reviewer closure checks. Clear project-specific values and accepted answers before reuse. Piper supports adding tested built work to company templates, but the next project's material suitability, permit basis and package assignments still need review.
Related reading
What Changed? How Drawing Revisions Cascade Through Scope, Bids, and the Estimate
A drawing revision is not only a sheet delta. Trace what it does to trade scopes, live bids, and the estimate before bid day locks the number.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.