Build a custom site utility scope and gap register in Piper
Build a site utility register that connects pipe limits, trench scope, testing, bidder answers and addendum impacts without treating a draft as an approved carry.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 10 min
- Published
On this page
- Start with utility segments, not one row per system
- Give each record a requirement, an assignment and a resolution
- Requirement and location
- Responsibility and interfaces
- Pricing basis and bidder evidence
- Open question and decision treatment
- Make testing records follow acceptance boundaries
- Compare the work required to maintain the scope
- Ask Piper to build the register in plain language
- Test an addendum that changes the price without changing pipe length
- Approve the record logic before saving the company template
A useful site utility scope tool must connect three things: the physical segment, the responsibility assigned to it, and the evidence behind that assignment. A list of storm, sanitary and water inclusions is not enough. The register should show what happens when a connection moves, a trench gets deeper or a bidder excludes restoration.
For a GC estimator preparing a hard-bid warehouse package, or a preconstruction manager closing a commercial GMP, build the register around those decisions before asking Piper to build the tool. Build with Piper lets teams describe registers and workflow automations in plain language on the same project information Piper reads. The result still needs review like any other workspace file.
The objective is not an automatically approved scope. It is a reviewable connection between the current documents, the package sent to bidders and the number the team intends to carry.
Start with utility segments, not one row per system
Use a segment identifier that means something in the field: sanitary from MH-1 to MH-2, domestic water from the main tap to the building handoff, or storm from inlet DI-3 to the outfall. Those identifiers are illustrative, not actual project references.
Keep separate records for activities that do not share the pipe's boundary. A tap, inspection, abandonment or paving repair may need its own assignment even when it relates to one segment.
The five-foot line is a good example. UFGS 33 11 00, Water Utility Distribution Piping, places its water-line termination approximately five feet from the building unless otherwise indicated. It also directs earthwork to Section 31 00 00. Neither provision alone establishes which subcontractor must excavate that final stretch or complete the connecting joint. These are guide specifications, not universal commercial subcontract boundaries. See the actual water specification, paragraphs 3.1.3 and 3.2.1.1.1.
That interaction changes the register design. Store pipe installation limits and trench limits separately. A single “site contractor to five feet” field can leave the final trench unassigned even when both pipe packages look complete. For the underlying boundary question, use the plumbing and site utility handoff guide.
This article uses four current, active UFGS examples to test the register's logic: water distribution dated August 2024, sanitary sewerage dated May 2018, stormwater utilities dated November 2021 and earthwork dated August 2023. WBDG's active specification catalog is for military construction. Use these examples as a review method, not as requirements for a private commercial job. Your issued specifications, drawings, utility-owner conditions and contract payment basis control the actual package.
The full site utility scope-writing guide addresses package language; here the question is how to hold the evidence and decisions behind that language.
Give each record a requirement, an assignment and a resolution
Do not use “included” as a substitute for all three. A workable register needs the following record structure. These are proposed fields to request, not Piper menu names or a prebuilt screen.
Requirement and location
Hold the system, segment endpoints, pipe size and material, relevant structure identifiers, and drawing or detail reference. Include the profile and depth basis where they affect pricing. Separate domestic water and fire service when they have different requirements.
Attach the source page, specification paragraph and revision or addendum reference to the requirement. A source citation should explain why the work is required, not merely point to a civil sheet containing the same pipe.
Responsibility and interfaces
Record who furnishes, installs, excavates, backfills, restores, tests and coordinates acceptance. Use separate entries where ownership differs. For service connections, also record who performs the tap, who authorizes valve operation and who pays any documented fees.
Authority is not the same as labor scope. The water guide requires connections in the Contracting Officer's presence and restricts operation of existing valves unless expressly directed. Those clauses do not say that the observer performs the connection. A record reading only “connection by authority” would obscure that distinction. See UFGS 33 11 00, paragraphs 3.1.1 and 3.1.2.
Make the tool hold both performing party and authorizing or witnessing party. If the project documents do not identify the performing party, leave an open question rather than assigning the work from the authority's name.
Pricing basis and bidder evidence
Keep the quantity and unit, depth-band definition, included incidental work, exclusions and pricing source. Link the bidder's clarification to the exact scope item it resolves. Distinguish an estimator's proposed assignment from a bidder's written acceptance.
A particularly useful distinction is quantity for pricing versus quantity for payment. The stormwater guide provides pipe measurement without deductions for manhole diameter and also provides separate structure payment, including a depth adjustment above a specified threshold. That is not necessarily the subcontractor's fabrication or installation quantity. See UFGS 33 40 00, paragraphs 1.1.1 and 1.1.3.
If the prime payment basis includes a length convention that the sub quote does not use, the register should expose the difference. It should not silently convert both quantities into one “correct” length.
Open question and decision treatment
Hold the question, the party expected to answer, the affected package and estimate line, and the current treatment. Useful distinctions are unresolved, proposed assignment, accepted assignment and reopened after change.
For each material unresolved item, identify whether the team needs a bidder clarification, a design answer, an allowance or a defined carry assumption. Record who approves that treatment. These are recommended review states, not product defaults.
Make testing records follow acceptance boundaries
A utility scope register should not close testing merely because a bidder wrote “testing included.” Ask what system is tested, where the test boundary ends, who witnesses it and what work must remain exposed.
The sanitary guide's optional inspection provisions illustrate why. Paragraph 3.3.3.2 provides for inspection after connection and before burial, with field-support personnel performing the inspection and selected contractor testing obligations. The applicability depends on the edited project specification. See UFGS 33 30 00, inspection provisions.
Read that alongside the earthwork guide's requirements to verify existing utility location and elevation and protect utilities during construction. See UFGS 31 00 00, paragraph 3.1.1.
The combined review rule: an uncertain existing connection elevation is not resolved by assigning the pipe installer. It also affects the verification task, connection inspection and backfill handoff. Give those activities linked records with named responsibilities. Otherwise a complete-looking installation scope can carry neither the verification cost nor the work needed to preserve access for inspection.
Competent estimators may choose different package arrangements. One may keep excavation through testing and backfill under the utility subcontractor. Another may use a sitework contractor for excavation and restoration. Choose based on the actual work sequence, each bidder's coverage and who can control the exposed connection until acceptance. The register should preserve that choice, not enforce a company default against contrary project requirements.
For other boundary checks, use the site utility scope-gap guide rather than adding an unrelated checklist to this tool.
Compare the work required to maintain the scope
A spreadsheet can hold sources, revision history and decisions. The useful comparison is how those connections are maintained, not whether spreadsheets are capable of storing them.
| Review need | Spreadsheet scope sheet | Custom tool on Piper project data |
|---|---|---|
| Source behind a requirement | Team adds and maintains page references or links | Built register reads the same project documents and source tracing as Piper |
| Changed drawing or addendum | Team identifies affected rows and revisits related decisions | Requested workflow can review an arriving addendum against affected scopes |
| Bidder clarification | Team connects the answer to scope rows and pricing treatment | Requested register can hold the answer alongside scope, bids and decisions |
| Company reuse | Copy the structure and clear project-specific content | Add the tested register and workflow to company templates |
| Approval responsibility | Team approves assignments and carry assumptions | Team reviews the built file and approves consequential decisions |
Piper's public app-builder description supports registers, trackers, forms, workbooks and workflows that run when information changes. It also states that these tools read the same drawings, specifications, revisions, quantities, scopes, bids and decisions as Piper. The proposed field structure here is a design request, not a claim that this exact site utility tool has already been built or tested.
Ask Piper to build the register in plain language
Supply the current project information and the company's existing scope structure. Include civil plans and profiles, utility details, relevant specifications, issued addenda, bidder proposals and clarification responses. Include utility-owner requirements only when they are available and applicable. A missing tap agreement must remain missing evidence, not become a default assignment.
Use a request like this:
Build a site utility scope and gap register for this project using our scope structure. Organize storm, sanitary, domestic water and fire-service work by identifiable segments and connections. For each item, hold the requirement, source page and revision, physical endpoints, pipe and trench responsibility, restoration responsibility, testing and acceptance boundary, pricing basis, bidder clarification and open decision. Keep proposed assignments distinct from accepted assignments. Where sources conflict or responsibility is unclear, hold the question for our review rather than guessing. Connect affected scope items to the related bid and carry decision where that information exists. Ask me where this request is unclear.
Then inspect the result like any other workspace file. Build with Piper supports describing and changing tools without coding, while the built work stays in the workspace with the same permissions and history. Do not assume the requested structure is correct because it was produced successfully.
The distinction from ordinary Scope Generation is the ongoing register. Scope Generation organizes project requirements into trade scopes and surfaces uncertain boundaries for estimator review. The custom tool defines how your team holds those assignments, outstanding questions and later changes together. For the cross-trade tool design, see building a custom scope tool.
Test an addendum that changes the price without changing pipe length
Use a controlled example before relying on the register in bid week.
Illustrative test fixture: a warehouse storm segment is 200 linear feet. A bidder's agreed shallow-trench rate is $140 per foot, with structures and final paving excluded. An addendum lowers the downstream invert so 60 feet fall into an agreed deeper band at $185 per foot. It also changes one structure from 8 feet to 10 feet deep and expands paving restoration from 500 to 700 square feet.
Assume, for this fixture only, a confirmed structure adjustment of $900 per added depth foot and restoration at $12 per square foot. The rates, thresholds and documents are synthetic, not market benchmarks or actual quotes.
The original segment carry is:
- Pipe and trench: 200 × $140 = $28,000.
- Structure: illustrative base price of $6,000.
- Restoration: 500 × $12 = $6,000.
- Total: $40,000.
The revised basis is:
- Pipe and trench: 140 × $140 + 60 × $185 = $30,700.
- Structure: $6,000 + 2 × $900 = $7,800.
- Restoration: 700 × $12 = $8,400.
- Total: $46,900, an increase of $6,900.
The pipe length did not change. A register designed to reopen only quantity differences would miss the entire adjustment. The failure is not arithmetic. It is treating length as the sole connection between a drawing revision and the estimate.
The stormwater guide's separate structure-depth payment basis and the earthwork guide's trench, dewatering and utility-verification provisions show why a profile change deserves a broader review than a length check. They do not establish the fixture's rates or dictate the commercial subcontract terms.
Ask for the change workflow this way:
When an addendum arrives, review it against the scope items it affects. Prepare an impact review showing the changed source, affected segment or connection, previous assignment, proposed scope change, related bidder clarification and pricing question. Include profile and depth changes even when plan length is unchanged. Keep prior accepted decisions visible and bring affected decisions back for review. Do not treat the impact review as approval to issue scope or change the carry.
Piper's app-builder facts support workflows triggered by an arriving addendum and steps that hand work to the next step. This is a requested review workflow, not a completed demonstration of the fixture. For the broader dependency logic, see how drawing revisions cascade through scope, bids and the estimate.
Approve the record logic before saving the company template
Review the tool against the fixture in two passes.
First, check evidence and boundaries. Can you inspect the source behind each requirement? Are the pipe, trench and paving limits distinct? Does an inspection authority remain separate from the performing contractor? Does missing evidence stay an open question?
Second, check decision history. Does the addendum review preserve the original accepted basis? Does it identify the deeper band, structure adjustment and restoration change? Does it retain the bidder's answer rather than replacing it with an inferred acceptance?
If the deeper-band rate is not agreed, the correct output is an open pricing question. If the structure quote already includes the added depth, the correct output is no additional carry for that item. A tool that always adds a plug would be as unreliable as one that never reopens the price.
Only then ask Piper to change the tool where needed and add what works to company templates. Reuse the structure, responsibility distinctions and review workflow. Do not reuse a five-foot boundary, tap assignment or testing assumption as an approved fact on the next project.
The reusable asset is the way the team connects requirements to commitments. The project-specific answer still belongs to the estimator and preconstruction team.
FAQ
Do we need code to build this register in Piper?
No. Teams describe the tool and requested changes in plain language, then review the result like any other workspace file. Registers, trackers, forms, workbooks and change-triggered workflows are supported categories. The field names and review states in this guide are proposed requirements, not predefined interface labels.
Should the register assume all site utility work ends five feet from the building?
No. Store the actual documented handoff for each system and distinguish pipe limits from trench, testing and restoration limits. The cited water guide uses an approximate five-foot termination unless otherwise indicated, but it does not establish a universal subcontract boundary for storm, sanitary and water work.
What should happen when an addendum arrives?
Request an impact review of affected scope items and decisions, not an automatically approved replacement scope. Review endpoint, profile, material, testing and restoration changes alongside quantity changes. Preserve the prior accepted basis so the estimator can decide what needs clarification, reassignment or a different carry.
When is the tool ready to become a company template?
After the team checks its source links, boundary assignments, open-question treatment and change review against a controlled example. Save the structure and workflow that worked, not the project's specific assumptions. Piper supports company templates, but the team must still review the next project's assignments and pricing basis.
Related reading
The five-foot line: plumbing and site utilities
Review plumbing and site-utility endpoints, connections, excavation and fees against actual project requirements before assigning scope or carrying a price.

What Changed? How Drawing Revisions Cascade Through Scope, Bids, and the Estimate
A drawing revision is not only a sheet delta. Trace what it does to trade scopes, live bids, and the estimate before bid day locks the number.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.