Build a custom structural steel bid leveling tool in Piper
Build a steel leveling tool that separates detailing, connection design, erection and shared scope, then tests revised bids without automating the carry.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 10 min
- Published
On this page
- Define the steel package before defining the calculation
- Build rows around obligations, not just material categories
- Detailing does not close the connection-design row
- Deck needs its own basis even when the steel bidder includes it
- Compute the package number and the project contribution separately
- Worked example: the apparent low bidder changes after coverage review
- Make the exclusion library ask better questions
- Test a revised quote against the plugs it replaces
- Build and review the tool on Piper's project information
A custom steel leveling tool should answer two questions separately: what does each bidder carry, and what must the GC carry to complete the same package? Do not start by asking it to rank steel prices per ton. Start by defining the boundaries between fabrication, erection, connection design and work assigned elsewhere.
For a GC estimator pricing a ground-up commercial building at bid-stage CDs, the useful output is a source-backed comparison with unresolved decisions visible. It should distinguish a subcontractor's offer from the GC's leveling adjustments and from shared project costs. Otherwise, a complete-looking total can hide an embed-setting gap or charge crane access twice.
Piper lets teams describe and build tools in plain language on the project information already in its workspace. The construction rules below are a proposed tool specification and acceptance test, not a report of a completed build. Your team still reviews the result and decides the carry.
Define the steel package before defining the calculation
This playbook is for building structural steel packages. It is not a bridge payment-item model or an engineering check of connection adequacy. On schematic or DD pricing, identify unresolved design assumptions explicitly rather than treating the comparison as a fixed-scope buyout. See pricing design intent when drawings are incomplete for that separate decision.
Record the project-specific governing basis first: issued drawings, structural notes, specifications, addenda, trade scope and pricing milestone. Include the specified editions of referenced standards. A current standard is not permission to silently replace the edition in the contract.
The current AISC standards page identifies ANSI/AISC 303-22 and describes the Code of Standard Practice as a contracting framework whose trade practices apply unless the contract documents contain contrary provisions. That makes the project documents essential, not optional, inputs to the tool. AISC's current Code page supports the framework; it does not settle every package assignment.
For a concrete model of document structure, the current public UFGS 05 12 00 file is the August 2018 guide specification, Change 2 dated May 2021, with references coordinated to October 2026. It separately addresses fabrication drawings, delegated connection design, coatings and field quality control. It also instructs specifiers to edit its options for the actual project. Use it here as an official example, not a requirement on every commercial building. UFGS 05 12 00
The tool should compare a bid against the issued package, not use a standard scope library as proof that the bidder owes everything in that library. For the general leveling process, use the construction bid leveling guide.
Build rows around obligations, not just material categories
Keep a member-quantity summary, but make the leveling rows describe deliverables and boundaries. A proposed steel register should include these groups:
- Fabrication and detailing: member supply, shop fabrication, fabrication drawings, connection details and required submittals.
- Connection design: whether delegated design is required, the stated design basis, sealed calculations where required, and the bidder's qualification concerning design inputs.
- Erection: erection labor, field bolts and welds, hoisting, temporary bracing, sequence assumptions and mobilizations.
- Adjacent packages: joists, deck, miscellaneous metals, shear studs and opening supports, with the actual furnish/install split.
- Concrete interfaces: embeds, anchor rods, templates, setting or surveying responsibilities, and grout supply and placement.
- Finish and verification: shop coating, field touch-up, galvanizing repair, fireproofing interfaces, contractor quality control, and separately assigned inspection or testing.
These are review rows, not universal assignments. For each, show the required work, source page, responsible package, bidder's statement, coverage status, price treatment and open question. Preserve the original proposal wording beside any normalized interpretation.
Use distinct coverage statuses such as included, excluded, qualified, silent and unresolved. Silence should not become a zero-cost inclusion. An exclusion should not become an automatic plug.
Detailing does not close the connection-design row
UFGS 05 12 00 paragraph 1.5.2 calls for fabrication drawings containing connection details. Its separate, optional paragraph 1.5.3 calls for delegated connection design using indicated connection loads and signed, sealed design calculations. Read together, those provisions give the tool a useful check: a statement that shop drawings are included does not by itself resolve a separate delegated-design obligation. UFGS paragraphs 1.5.2 and 1.5.3
Suppose the issued specification retains delegated design, the structural notes supply connection loads, and a proposal says “detailing included; engineering by others.” The proposed tool should connect those three records and draft a clarification about design coverage. It should not infer that the detailing price includes engineering or attempt to approve the connection design.
The decision changed is commercial: obtain a compliant design add price, assign the service elsewhere with a price, or leave a documented unresolved exposure for the chief estimator. Do not hide it inside the tonnage row.
Deck needs its own basis even when the steel bidder includes it
The Steel Deck Institute identifies ANSI/SDI COSP 2023 as its current Code of Standard Practice for Steel Deck, replacing COSP17. It covers the trade practices for design, sale, purchase, manufacture and installation absent contrary instructions. SDI's current Code page
Use that separate deck basis to create a document check, not to dictate which subcontractor receives the work. If the steel quote includes deck, reconcile that inclusion with the separately solicited deck package before adding either price. Ask about the defined deck assembly and its interface items, not only square footage.
The tool's ownership field matters here: “covered in another package” is different from “excluded and uncovered.” Both can appear as exclusions in the steel proposal; only the second requires a new coverage decision.
Compute the package number and the project contribution separately
Specify two calculations:
Comparable package total = raw proposal + uncovered-scope adjustments + approved basis adjustments − confirmed credits.
Project contribution = comparable package total + assigned costs carried outside that subcontract.
These are proposed estimating rules, not a standard-mandated formula. The second number prevents costs deliberately kept in general requirements or another package from disappearing. It also prevents those same costs being added twice.
Every adjustment needs an item identifier, scope description, pricing basis, source, owner and reviewer treatment. Distinguish:
- A bidder-confirmed add price from a GC estimate.
- A price for a fixed obligation from an allowance for unresolved extent.
- A cost unique to one bidder's approach from a shared project cost.
- A scope omission from a changed pricing basis.
A price-per-ton diagnostic can be useful after that work. Define whether the denominator includes only main members or also connection material and other steel. Do not multiply a whole-package rate by a member-weight change unless the bidder confirms that basis: detailing, mobilization and engineering may not move with that weight.
Worked example: the apparent low bidder changes after coverage review
Illustrative only. A commercial building has a GC-approved comparison basis of 180 short tons of structural members. Deck is separately covered; embed setting and grout placement are already carried in the concrete package. Assume both bidders have otherwise accepted the same fabrication and erection scope.
Bid A is $810,000 and excludes connection engineering, crane rental and field primer repair. Bid B is $865,000 and expressly includes those three items. Both include detailing. Their initial whole-package diagnostics are $810,000 ÷ 180 = $4,500 per ton and $865,000 ÷ 180 = $4,805.56 per ton. Those ratios are not material-only rates.
For this example, the retained project specification requires delegated connection design and primer repair. The GC obtains or approves these illustrative adjustments for A:
- Connection engineering: $14,000.
- Crane rental for the quoted erection plan: $32,000.
- Field primer repair: $12,000.
A's comparable package becomes $810,000 + $14,000 + $32,000 + $12,000 = $868,000. B remains $865,000. A's apparent $55,000 advantage becomes a $3,000 disadvantage. That is a coverage result, not a finding that either bidder is generally cheaper.
There is also $18,000 of crane access-area preparation carried in the GC's site budget for either option. Project contributions are therefore $886,000 for A and $883,000 for B. Do not add that $18,000 to the steel subcontract price if it remains in the site budget.
Why keep crane rental and access preparation separate? OSHA 29 CFR 1926.752(c) requires the controlling contractor to ensure adequate site access and a firm, graded, drained area for material storage and safe equipment operation. That requirement does not establish who supplied the crane in a particular quote. OSHA's current steel-erection provision
Combining the proposal's crane exclusion with the site-access requirement changes the estimating check: close equipment coverage and site readiness independently. Buying the crane does not close the access-area row.
Make the exclusion library ask better questions
An exclusion library should store the check prompted by the phrase, not a default dollar amount.
For “engineering by others,” ask whether the issued package requires delegated connection design and which party will provide it. For “embeds by others,” split furnish from set and verify the concrete package's corresponding inclusion. For “painting excluded,” identify which coating operation is actually excluded.
The painting distinction is particularly important. UFGS 05 12 00 paragraph 3.5 requires repair of shop primer damaged by handling, transporting, cutting, welding or bolting; paragraph 3.5.1 addresses field priming under stated exposure conditions. A generic painting exclusion could concern finish coats, primer repair or both. The tool should preserve that ambiguity until clarified. UFGS paragraphs 3.5 and 3.5.1
Likewise, “special inspections excluded” should trigger a check of the actual verification obligations and assignments. Do not use it to delete contractor quality-control work without reviewing the specification. The UFGS example separately specifies field testing and inspection services in paragraph 3.7; a project may have different retained requirements and separate owner arrangements.
Competent estimators may disagree about whether to retain an unclear item as a steel addback or carry it elsewhere. The deciding evidence should be a priced, workable assignment, including access and sequencing, not which location makes the steel comparison look lower. Keep that judgment visible. The exclusions and qualifications review guide covers the broader review method.
Test a revised quote against the plugs it replaces
Continue the illustrative example. Bid A sends Revision 2 for $850,000, now including crane rental and field primer repair but still excluding connection engineering.
The correct revised comparison is $850,000 + $14,000 = $864,000. With unchanged site preparation, its project contribution is $882,000. A is now $1,000 below B on the assumed common basis.
If the tool replaces the base price but retains every old plug, it calculates $850,000 + $14,000 + $32,000 + $12,000 = $908,000. The $44,000 error comes from stale adjustments, not arithmetic.
The proposed revision rule is therefore item-based: every changed coverage statement reopens the corresponding adjustment for review. Preserve the previous proposal and decision basis, identify superseded adjustments, and show the proposed new comparison before anyone adopts it.
An addendum acknowledgment needs a separate check. Record acknowledgment, affected scope rows and evidence that the revised price addresses those rows. Acknowledgment alone should not mark an old engineering qualification resolved.
For each clarification, retain the question, bidder, affected row, response source, pricing consequence, unresolved issue and reviewer disposition. Ask a closed commercial question where possible: “Does Revision 2 include the specified field primer repair, and does it replace the prior exclusion?”
Build and review the tool on Piper's project information
The Build with Piper workflow supports plain-language requests for registers, trackers, workbooks and change-triggered automations. What teams build reads the same project information as Piper: drawings, specifications, revisions and addenda, takeoff quantities, scopes, bids and decisions. Results live in the workspace with its permissions and history and are reviewed like other workspace files.
The distinction is not that a spreadsheet cannot retain sources or history. It is who maintains the connections when a bid or project requirement changes.
| Review concern | Spreadsheet maintained on the side | Tool built on Piper project data |
|---|---|---|
| Source basis | Team maintains document references and current copies | Reads the project documents and sources already in Piper |
| Steel scope rows | Team enters and maintains coverage interpretations | Request trade-specific rows and source-backed checks for review |
| Revised proposal | Team reconciles the new quote with old adjustments | Request a change-triggered comparison and adjustment review |
| Unclear responsibility | Reviewer records and resolves the ambiguity | Piper asks where the build request is unclear; estimator resolves scope judgment |
| Carry approval | Estimator decides | Estimator decides |
Use this example request as a starting specification, then inspect what is actually built:
Build a structural steel bid-leveling register for this project using the issued trade scope, subcontractor proposals, drawings, specifications, addenda and takeoff quantities. Separate fabrication and detailing, delegated connection design, erection and hoisting, deck and joists, miscellaneous metals, embeds furnished versus set, grout, coatings and verification obligations. Show the source requirement and original bidder wording for each row. Keep included, excluded, qualified, silent and unresolved coverage separate. Show raw price, reviewer-approved adjustments, comparable package total and separately assigned project costs. Keep every adjustment connected to its scope item, pricing basis and reviewer treatment. Do not infer missing prices or approve a carry. Ask me about unclear rules.
Then describe an automation:
When a new or revised steel proposal arrives, check it against the current package and prepare an updated comparison. Identify changed inclusions, exclusions, qualifications and addendum acknowledgments. For revised bids, identify old adjustments whose basis may have changed and prepare those items for review. Keep open clarifications visible. Do not approve the revised carry.
Piper's Bid Leveling workflow extracts proposal terms, checks bids against intended scope and surfaces source-backed gaps and qualifications. The steel-specific calculation and review rules above are what you ask the custom build to implement, then verify; they are not assumed preconfigured behavior.
Test the result with the illustrative bid pair and revision before adding it to company templates. Check that it produces $868,000, then $864,000 for A, leaves shared site costs outside the subcontract price, and does not mistake detailing for design coverage. Ask Piper to change anything that fails. The general custom bid-leveling tool guide covers the cross-trade build specification.
Add the verified structure to company templates, not the project's prices or settled assignments. Re-establish the governing basis on each new job. A reusable steel tool should preserve the questions that protect the carry, not reuse last project's answers.
FAQ
Can the tool level steel proposals with different tonnages?
It can support the comparison, but first establish what each quantity includes. Use member weight as a diagnostic, not an automatic whole-package adjustment basis. Ask the bidder to reconcile quantity differences and confirm whether a proposed unit rate includes fabrication, erection, connection material and fixed services.
Should every steel exclusion receive a plug?
No. First determine whether the item is required, whether it is already priced elsewhere, and what the bidder actually excluded. A confirmed assignment to another package needs a coverage record. An uncovered obligation needs clarification or a reviewed adjustment. Ambiguous language needs an open question, not an invented price.
What should happen when a revised steel bid arrives?
Prepare a new comparison and reopen adjustments tied to changed coverage. Retain the previous basis so the reviewer can explain the movement. A revised base price should not inherit old plugs without checking whether the revised proposal now includes the work those plugs represented.
Does building this tool require coding or let Piper choose the subcontractor?
Neither. Teams describe and change tools in plain language, then review the result like other workspace files. Piper can extract proposal terms and support scope comparison, but consequential assumptions, adjustment approval and the final carry remain decisions for the estimating team.
Related reading
How to review subcontractor exclusions and qualifications
Subcontractor bids bury risk in exclusions and qualifications. Identify them, classify impact, normalize the comparison, and lock decisions into the subcontract scope letter before award.

Construction bid leveling: a practical guide for GCs
How to level subcontractor bids across design-bid-build, CM-at-risk, design-build, and progressive design-build, and why the same spreadsheet does not work for all of them.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.