Earthwork bids: reconcile excavation, soil reuse and disposal before carrying a price

Level earthwork proposals by quantity basis, material disposition and responsibility for testing, import, disposal and temporary work.

Guide2 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Separate quantity states and material decisions
  2. Worked comparison: a missing destination
  3. Close the interfaces before leveling

A comparable earthwork bid identifies what is excavated, what may be reused, where rejected material goes and who supplies replacement fill. Freeze the survey, design surfaces, geotechnical information and proposal qualifications before comparing prices. A single excavation quantity is not proof of a balanced site.

The UFGS earthwork guide treats subsurface information, stockpiles, suitable material, borrow, dewatering and shoring as distinct subjects. It is an example guide, not automatically the issued project specification. The actual report, contract and project requirements govern the bid basis and allocation of risk.

Separate quantity states and material decisions

Label excavation measured in place as bank volume, hauled material as loose volume, and installed fill as compacted volume. They are different measurement states. Do not convert them with a universal swell or shrink factor; obtain project-specific assumptions and confirm the unit used in each proposal. Identify who determines suitability, who orders testing, and who may authorize a change if conditions differ.

Worked comparison: a missing destination

Assume a fictional site has an estimated 1,000 bank cubic yards of excavation. The design team has not yet confirmed how much is suitable for reuse. Proposal A includes excavation and stockpiling but excludes off-site disposal and imported replacement. Proposal B includes excavation and disposal of a stated 300 loose cubic yards, but excludes import. Neither is a complete like-for-like price, and 300 loose cubic yards cannot simply be subtracted from 1,000 bank cubic yards.

Disposition or interfaceProposal AProposal BDecision before carry
Excavate1,000 bank cubic yardsSame stated bank basisVerify survey and limits
Reuse and stockpileStockpile included; suitability openReuse qualification openIdentify tests and placement requirements
Unsuitable materialDisposal excluded300 loose cubic yards includedAlign conversion, destination and excess unit price
ReplacementImport excludedImport excludedObtain quantity basis and supply/placement price

Request each bidder's aligned base and separately priced alternatives for rejected material, haul, tipping and imported fill. Retain the uncertainty rather than silently treating either proposal as complete. Identify an authorized disposal destination and any necessary approvals through the responsible parties; this review does not determine environmental permissions.

Close the interfaces before leveling

Stockpile location and protection, weather damage, testing, dewatering, shoring and utility protection all have cost and schedule consequences. Assign each to a trade or GC carry, describe the condition or duration assumed, and distinguish initial tests from retests. Do not design temporary works from a bid table. Record the site condition, notice and authorization process required by the contract when unexpected material is encountered.

The underground plumbing boundary addresses the trade interface; the logistics review addresses access and stockpile constraints. Both should use the same scope and drawing revision as the earthwork comparison.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.