East Village CLMC1105: separate jack-and-bore, duct bank and owner conductor work
Review East Village CLMC1105 across jack-and-bore, carrier ducts and manholes, keeping groundwater assumptions and Austin Energy's conductor handoff separate.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
Price the bore assembly and its transitions separately from the owner’s later conductor installation. The 36-inch dimension describes the casing bore, not each carrier; groundwater in the summary is a site description, not a priced dewatering allowance.
The dated project record
The City listing for IFB 6100 CLMC1105, checked November 17, 2026, showed a December 3, 2026, 2 p.m. deadline. It describes approximately 342 feet of 36-inch jack-and-bore with twelve five-inch carrier pipes grouted within the casing, 386 feet of twelve-duct open-cut bank, 79 feet of two-duct open-cut bank and two 12-by-12-foot manholes. Austin Energy will install conductors at project completion. The source is Official IFB6100CLMC1105. Check the current owner record before relying on any date or project status.
Follow the casing-to-duct-bank transitions
The following is an estimating review, not a statement that the owner assigned these tasks to a particular contractor. Use the current drawings, specifications and contract documents to settle the actual boundaries.
| Scope or location | Review and assignment question |
|---|---|
| Bore and casing | Trace launch and receiving limits, casing installation, access and restoration to the issued details. |
| Carriers and grout | Assign twelve carriers, spacers if required by the documents, grouting and the transition into the manholes. |
| Open-cut banks and manholes | Separate the twelve-duct and two-duct runs; identify excavation, structure connections, backfill and surface restoration. |
| Owner conductors | Record Austin Energy’s later conductor installation and confirm acceptance, access and handoff requirements. |
Separate construction acceptance from conductor work
A bore quote and duct-bank quote may both stop at a manhole wall. Ask who connects and seals the carriers, completes the bank and restores the work area. Separately obtain the groundwater requirements and each bidder’s dewatering basis; do not insert an allowance unsupported by the documents.
Make a handoff line for the completed raceway before Austin Energy installs conductors. Confirm whether its acceptance requires a particular cleaning, verification or access condition; the listing names the owner-installed work but does not state those detailed obligations.
Evidence needed for this package
Request bore and manhole connection details, groundwater requirements, duct-bank sections and Austin Energy's acceptance and conductor-installation sequence. Preserve the separate twelve-duct and two-duct runs and verify the crossing dimensions from the issued drawings.
For the broader method, see the underground piping scope review. Use the project-specific register above to bring the general boundary review back to the actual work.
Related reading
The five-foot line: plumbing and site utilities
Review plumbing and site-utility endpoints, connections, excavation and fees against actual project requirements before assigning scope or carrying a price.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow