How to write an electrical scope of work subs can price on the same basis

Write an electrical bid scope that fixes the pricing basis for power, lighting, controls, utility work and temporary service, with a reusable package outline.

Guide11 min read

Published

Tower crane above steel reinforcement

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Establish the document basis before writing inclusions
  2. Write system commitments, not equipment inventories
  3. Distribution and mechanical equipment power
  4. Lighting and lighting controls
  5. Site electrical, utility service and emergency power
  6. Resolve interfaces with a responsibility attachment
  7. Define the pricing rule when the drawing count is not the obligation
  8. Illustrative pricing review: equal drawings, unequal commitment
  9. Price temporary power as an operating period
  10. Reuse this electrical scope outline
  11. A. General and document basis
  12. B. System inclusions
  13. C. Testing and closeout
  14. D. Exclusions and work by others
  15. E. Clarifications and unresolved basis
  16. F. Alternates and allowances
  17. G. Unit prices
  18. H. Bidder acknowledgment and buyout reconciliation
  19. Keep the electrical scope connected to its sources

An electrical bid package should tell every subcontractor which systems to carry, where each responsibility starts and stops, and what constitutes completed work. A list of specification sections is the reference basis, not the finished scope.

For a GC estimator soliciting a ground-up commercial building at near-complete CDs, the strongest scope fixes the base pricing assumptions before asking for a lump sum. It names the fixture package, mechanical power connections, controls boundaries, site electrical endpoints, utility responsibilities and temporary-power operating period. It also tells bidders how to identify deviations without silently changing the base.

The objective is not identical prices. It is prices for the same commitment. Two capable electrical subcontractors can disagree on labor and procurement while still pricing the same work.

This guide addresses a GC-issued electrical bid scope and its proposed subcontract exhibit. It is not a delegated electrical design specification. On DD-stage GMP or design-build work, add an explicit design-responsibility and allowance basis rather than treating this outline as evidence that the design is complete.

Establish the document basis before writing inclusions

Create a short document register at the front of the package. Identify the drawing issue, specification issue, addenda and written clarifications bidders must price. List actual sheet and section identifiers, not a generic instruction to review all documents.

Use these document groups as the review map:

  • Electrical drawings: one-line diagrams, distribution plans, panel schedules, equipment connections, lighting and control plans, fixture schedules, site electrical plans, grounding details and demolition sheets where applicable.
  • Electrical specifications: the project's applicable common-work, raceway, conductor, grounding, distribution-equipment, lighting, controls, emergency-power, testing and study sections.
  • Related design documents: mechanical equipment schedules and control diagrams; civil utility and trench details; structural pads, pole foundations and support details; architectural reflected ceiling plans and mounting details.
  • Other package requirements: applicable temporary facilities, coordination, commissioning, submittal and closeout sections; utility service documents; owner-furnished equipment information; alternates and allowances.

A useful primary-source example is the federal guide-specification set. UFGS 26 51 00, Interior Lighting, references distribution work in 26 20 00, exterior lighting in 26 56 00 and commissioning in 01 91 00.15. UFGS 26 56 00 in turn references underground or overhead distribution sections outside Division 26. These references show why a lighting section alone does not describe the entire installation. Sources: interior lighting, paragraph 1.2; exterior lighting, paragraph 1.2.

These are editable military guide specifications, not universal requirements for commercial construction. The versions checked for this guide were 26 20 00 dated May 2025 with Change 2, February 2026; 26 51 00 dated May 2020 with Change 2, November 2021; 26 56 00 dated August 2021; and 01 50 00 dated August 2026. Use the actual issued project sections and applicable code basis, not those dates as a substitute for the contract documents.

For the broader document-to-package method, use the construction scope generation guide. The electrical-specific task here is to convert that document basis into inspectable responsibility statements.

Write system commitments, not equipment inventories

Organize inclusions around systems a reviewer can follow from source to load. For each system, specify the work, endpoints, furnishing responsibility, installation responsibility and required completion deliverables.

Distribution and mechanical equipment power

Spell out service equipment, transformers, switchboards, panelboards, feeders, branch circuits, raceways, conductors, grounding, identification and required supports. Identify demolition, reconnection and service-continuity obligations separately on renovation work.

For mechanical equipment, use an equipment-tag attachment. Include the supply source, voltage and phase shown, feeder or circuit basis, disconnect arrangement, starter or VFD furnishing party, power termination point and controls assignment. Mark unavailable information as an open clarification rather than filling it with an unsupported assumption.

The distinction between power and controls deserves precise language. UFGS 26 20 00 paragraph 3.1.19 includes power wiring and connections to motors and equipment, while excluding automatic control wiring and devices within control circuitry unless otherwise noted or specified; those are assigned to the section specifying the associated equipment. That is a specific guide-specification allocation, not a rule that all controls belong outside electrical. Source: equipment connections.

Recommended decision rule: reconcile the equipment schedule, electrical connection detail and controls diagram before writing the boundary. If a VFD is factory supplied with the unit, say who installs the assembly and where the electrical feeder terminates. If it is field supplied, name who furnishes it, mounts it, supplies its power and connects its control wiring. Do not allow the phrase “mechanical equipment by others” to replace those decisions.

Lighting and lighting controls

Name the base fixture schedule and required options. State who furnishes fixtures, drivers, emergency components, mounting accessories and controls. Require substitutions to be offered separately unless the solicitation expressly permits another basis.

Describe the controls installation through completion: devices, power packs, control cabling, gateways where specified, programming, sequences, verification, commissioning support, training and handover. UFGS 26 51 00 treats lighting controls as part of its lighting scope and lists control diagrams, sequences, compatibility certificates, verification tests and training deliverables. Source: paragraphs 1.4, 3.2 and 3.3.

The important interaction: a mechanical automatic-controls exclusion and a lighting-controls inclusion can coexist. A blanket “controls wiring excluded” sentence cannot communicate that distinction. Name the system being excluded, then affirm the lighting-control work retained in the electrical base.

Site electrical, utility service and emergency power

For site work, define the complete run and then allocate its parts: excavation, bedding, raceways or ductbank, backfill, testing, pull boxes, conductors, foundations, poles, grounding and surface restoration. State endpoints using a detail, location or equipment identifier.

For utility work, identify the service document relied on and separate utility-furnished work from contractor-installed infrastructure. Assign application coordination, fees or deposits, metering provisions, inspections and connection attendance as the actual project requires. If the utility basis is not available, issue a common allowance or explicit assumption for bidders to price; do not ask each bidder to invent its own service arrangement.

For a generator package, use the same component-level allocation. Address generator and transfer-equipment furnishing, setting, pads, feeders, control connections, fuel-system interfaces, startup, test support and closeout. This is a recommended scope-writing check, not a claim that every listed item belongs to electrical on every project.

Resolve interfaces with a responsibility attachment

Use a responsibility schedule alongside the prose scope. The schedule below is a writing template, not a default trade allocation.

InterfaceElectrical commitment to stateComplementary commitment to confirm
Mechanical equipmentFeeder, disconnect, starter or VFD work, and termination endpoint by equipment tagEquipment furnishing, factory wiring, automatic controls and startup party
Low voltage and fire alarmRetained pathways, boxes, sleeves, power feeds or other specifically assigned workCable, devices, head-end equipment, programming, testing and acceptance party
Site lightingPole and fixture furnishing, anchor hardware, raceways, conductors and grounding assigned to electricalFoundation construction, trenching, backfill and restoration assigned to named packages
Utility serviceContractor-side service infrastructure, coordination and connection attendanceUtility work, fees, deposits, meter and service-availability basis
Emergency powerEquipment, power connections, assigned controls and test supportSetting, pads, fuel system and other named interfaces
Temporary powerInstallation, distribution, maintenance, relocations and removal included in the priceConsumption charges, special loads and extensions beyond the stated duration

Write “by others” only when you can name the other party or package and describe the complementary work. An unpriced assignment is still an open decision.

Pole foundations illustrate why this attachment matters. UFGS 26 56 00 paragraph 2.6.7 addresses anchor bolts but references cast-in-place concrete and underground electrical distribution for concrete requirements. Its pole-drawing provisions also require structural and dimensional information. Source: paragraphs 1.5.1.2 and 2.6.7.

Recommended check sequence: pair the electrical pole detail with the foundation detail, then assign anchor-bolt furnishing, template delivery, bolt setting, conduit stub-ups and grounding before assigning the concrete package. Excluding “pole bases” does not answer who supplies the hardware that must be coordinated before the base is poured.

Competent estimators may choose different allocations. An electrical subcontractor may carry complete foundations on one project; a site-concrete package may carry them on another. Decide using procurement responsibility, field capability and who can control the approved pole information before placement, not the section number alone.

Use the MEP interface review for the wider coordination process and the electrical scope gaps guide for missing-coverage investigations.

Define the pricing rule when the drawing count is not the obligation

A scope can give bidders the same drawing set and still leave them pricing different quantities.

UFGS 26 51 00 paragraph 3.1.5.2 treats the indicated occupancy/vacancy sensor quantity as a minimum and requires additional units for full coverage. It also requires coordination of sensor testing with the commissioning specification. Source: sensor installation provisions.

If your issued project specification uses that language, “include all sensors shown” is an incomplete pricing instruction. The scope must preserve the coverage obligation and say what layout and verification work the bidder must carry. If the documents instead prescribe a fixed installation, do not add an unpriced performance obligation yourself.

Illustrative pricing review: equal drawings, unequal commitment

Assume an office package has 18 sensors shown. Its hypothetical issued specification requires full coverage, and a coordinated preliminary layout supports six additional sensors. All quantities and prices below are illustrative, not market rates or measured project results.

  • Bidder A offers $210,000, carrying only the 18 shown sensors and excluding programming and verification.
  • Bidder B offers $216,500, carrying 24 sensors, programming and the specified verification.
  • For this illustration, a written clarification from A prices six installed sensors at $450 each, programming at $2,200, and verification at $1,800.

A's revised comparable price is:

$210,000 + (6 × $450) + $2,200 + $1,800 = $216,700.

The apparent $6,500 advantage becomes a $200 disadvantage on this defined basis. That does not automatically determine award; it establishes that the original prices represented different commitments.

The scope-writing fix is not “add six sensors” without further review. It is to identify whether the contract basis is a fixed count or coverage, require the bidder's layout basis where appropriate, and include the required programming and verification. A device unit price can price a quantity change, but it does not necessarily cover system-level programming or test attendance.

This is a failure mechanism to check before solicitation, not an empirical finding about electrical bids. For proposal language already received, use the existing electrical exclusions review.

Price temporary power as an operating period

Temporary power needs a separate inclusion, even when the electrical subcontractor also installs the permanent service.

UFGS 01 50 00 distinguishes provision of temporary utilities, payment for utility services, and meters and temporary connections. Its temporary-utilities paragraph requires utilities needed for construction, while subsequent provisions address the available supply and charging arrangements. Source: paragraphs 3.2.1 through 3.2.3.

For a commercial bid package, translate the actual logistics and contract requirements into a common operating basis:

  • Supply point and assumed service availability.
  • Supported loads, distribution areas and temporary lighting extent.
  • Installation and inspection responsibilities.
  • Maintenance and planned relocations.
  • Start and end triggers, including removal.
  • Consumption charges and equipment-rental responsibility.
  • Treatment of special loads and extensions beyond the base period.

Judgment call: a lump sum is defensible when the temporary layout and operating period are sufficiently defined. If permanent energization remains uncertain, ask for a stated base period and separately defined extension pricing. Do not let bidders independently assume when temporary power ends.

Read temporary-power requirements against permanent-service milestones. The useful distinction is between an electrical installation that is finished and a temporary system that must remain in operation. Specify the release trigger rather than assuming those dates coincide.

Reuse this electrical scope outline

The following is an editable drafting outline. Replace prompts with project-specific language, remove inapplicable work and resolve material blanks before issue.

A. General and document basis

Identify project, package, drawing and specification issues, addenda and incorporated clarifications. State the base bid basis, work areas, phases, access assumptions and applicable project requirements. Identify design duties only where expressly assigned.

B. System inclusions

Describe service and distribution; feeders and branch circuits; grounding and identification; lighting and controls; equipment power; site electrical; emergency power; and demolition or reconnection where present. Attach equipment tags and defined endpoints. Include required supports, penetrations and associated work according to the responsibility attachment.

C. Testing and closeout

List the actual required studies, field tests, settings, labeling, reports, commissioning participation, manufacturer attendance, training, record drawings, manuals, spares and warranties. Name deliverables and required participants rather than using “testing complete” as the entire scope.

D. Exclusions and work by others

List approved exclusions with the covering package, limits and retained electrical work. Separate mechanical automatic controls from lighting controls. Resolve low-voltage, fire-alarm, utility, excavation, pole-foundation and fuel-system assignments by component.

E. Clarifications and unresolved basis

Record each unresolved requirement with its source, common pricing assumption, confirmation owner and decision trigger. Tell bidders to identify deviations separately. Do not present a GC pricing assumption as a design-team resolution.

F. Alternates and allowances

Identify each alternate by number and define the complete add or deduct scope. For fixture substitutions, request affected drivers, controls, mounting, emergency components, submittals and verification work as part of the proposed change. State whether allowance amounts are included in base, what they cover and how related installation is treated.

G. Unit prices

Specify unit, assembly contents, installation conditions and included labor, material, equipment and markup. Distinguish a complete new device installation from a device-only supply price. State how quantity changes will be authorized and measured under the proposed agreement.

H. Bidder acknowledgment and buyout reconciliation

Require acknowledgment of the document register and scope attachment. Capture exclusions, qualifications and alternate bases separately from the requested base. Before subcontract execution, reconcile accepted revisions into the proposed exhibit and confirm agreement language with the responsible contract reviewer.

A final release test is simple: select one rooftop unit, one lighting-control zone and one site pole. Can a reviewer trace each from document requirement through package ownership to completed work? If not, the scope is not ready merely because every heading is filled in.

Keep the electrical scope connected to its sources

The maintainable record is the requirement, source, assigned package, pricing basis and unresolved decision together. That matters when a revised equipment schedule changes a disconnect, a lighting revision changes the controls layout, or a utility clarification changes the service boundary.

Piper's Scope Generation workflow uses drawings, specifications, addenda and company knowledge to prepare trade-specific scopes from one evolving understanding of the project. It organizes requirements by package, retains source references and surfaces unclear trade boundaries for review. Company scope structures and standard language can become part of the draft.

For electrical work, the estimator still decides the allocation and pricing basis. Piper drafts and checks; it does not turn an unresolved controls boundary or utility assumption into an approved commitment.

FAQ

Is referencing Division 26 enough for an electrical scope of work?

No. Use the actual sections as references, then define systems, endpoints, interfaces and completion obligations. The federal guide-specification examples connect lighting to distribution, commissioning and site work in other sections. Your issued project documents determine which related requirements must be assigned in the electrical package.

Should mechanical controls wiring be included in electrical?

Follow the project's equipment and controls requirements, then state the assignment explicitly. Reconcile the mechanical schedule, electrical connection detail and controls diagram by equipment tag. Do not confuse a mechanical automatic-controls exclusion with lighting controls, which need their own furnishing, wiring, programming and verification basis.

How should the scope handle temporary power?

Define the supply, loads, distribution, maintenance, relocations, operating period and removal trigger. Assign consumption charges separately. When permanent-service availability is uncertain, use a stated base period and defined extension pricing rather than allowing each bidder to assume a different end date.

Can this outline become the subcontract scope exhibit?

Yes, as a drafting starting point, after accepted clarifications and commercial decisions are reconciled into it. Confirm the proposed agreement's treatment of the exhibit and conflicting documents with the responsible contract reviewer. The bid scope alone does not establish that every bidder qualification has been resolved or accepted.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.