EPC and EPCM bids: identify the contracting role before comparing the price

Map contracting parties, procurement authority and completion interfaces before comparing EPC and EPCM prices on an industrial project.

Guide3 min read

Published

Tower crane against an overcast sky

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Map the agreements and authority first
  2. Trace the equipment interfaces through acceptance
  3. Surface information and site gaps before fixing a carry
  4. Hand off the contract basis with the number

A price labeled EPC is not automatically comparable with one labeled EPCM. Before an industrial GC or CM levels either offer, map what each party is being paid to deliver, who signs the supply and construction contracts, who can issue instructions, and what evidence establishes completion. Use the actual agreement and scope, not the acronym, to determine the allocation.

The labels are useful starting points. In its public introduction to the historical 1999 Silver Book, FIDIC describes an EPC/turnkey example in which one entity undertakes engineering, procurement and construction to deliver a facility ready for operation. IChemE's catalog describes its 2023 Blue Book as a form for engineering, procurement and construction management services for process plants, including design, procurement, construction supervision and commissioning. These publisher examples are not a rule for every agreement. Neither label proves a particular guarantee or allocation of all risks.

Map the agreements and authority first

For every material package, identify the contracting parties and the party responsible for design, purchasing, installation and direction. A party managing procurement may have a different role from the party signing a purchase order or accepting its commercial risk. Review the draft agreement, scope, authority schedule and commercial qualifications together. Ask who can approve substitutions, changes and vendor instructions, and whose acceptance is needed.

The following fictional process-equipment package is a review tool, not a description of either publisher's form.

InterfaceOffer A: integrated packageOffer B: management servicesQuestion before leveling
Equipment purchaseOffer includes purchase subject to vendor termsFee describes procurement support; purchase party unclearWho signs the order and bears price and delivery changes?
DesignEquipment design included; utility design boundary unclearEngineering services listed; deliverable boundaries unclearWho produces and approves each interface drawing?
InstallationMechanical installation included; electrical connection excludedConstruction supervision described; installer contract unclearWho contracts and prices the excluded connections?
Tests and acceptanceVendor test included; site performance test qualifiedCommissioning assistance listed; acceptance responsibility unclearWhich test, criteria, witness and records are promised?
ChangesProposal reserves vendor changesAuthority to instruct vendors not statedWho approves cost and schedule changes?

The offers may both be useful, but their totals buy different things. Carry missing installation, owner purchases or separate professional services explicitly when developing a comparable estimate. Do not add a speculative amount and present it as the bidder's commitment; show the assumption and owner of the unresolved scope.

Trace the equipment interfaces through acceptance

Use the equipment list, process and utility documents, vendor scope and draft agreement to identify the boundaries: foundations and anchors, unloading, piping tie-ins, power, controls, utilities, startup consumables and operator training where applicable. For each interface, record the supplying party, receiving party, source revision, price treatment and outstanding clarification. A vendor's equipment price can be complete for supply while the overall system still lacks installation or utilities.

Likewise, distinguish factory testing, site testing, commissioning assistance and final acceptance. Record the promised deliverable and evidence, not just the word “commissioning.” Ask who supplies test procedures, instruments, operators and feedstock, and which party can accept the result. Whether those items apply depends on the project documents.

Surface information and site gaps before fixing a carry

FIDIC's 2017 Silver Book publisher overview identifies circumstances in which its form is unsuitable, including insufficient tender information and certain underground or uninspectable work without special provisions. It also describes Particular Conditions as part of the contract. That warning is a useful prompt to examine the actual information and agreement, not a substitute for reading the applicable terms.

For a brownfield package, list unknown existing utilities, access restrictions, investigation results and available shutdown windows. Assign an RFI or investigation owner and set a decision date. If a question cannot be closed before bid, state its effect on scope, schedule and the estimate basis; obtain the authorized team's decision on any qualification or contingency.

Hand off the contract basis with the number

A useful handoff includes the role map, issued document list, exclusions, equipment and construction interfaces, acceptance evidence, open RFIs and the commercial decision owner. Identify the industrial estimate interfaces and compare the delivery context, but return to the specific agreement to settle the allocation. Reopen the map when a purchase party, vendor scope or acceptance test changes.

FAQ

Does EPC mean the contractor accepts every project risk?

No. The agreement and its conditions allocate responsibilities and risks. An EPC label alone does not establish a universal transfer or performance guarantee.

Can an EPCM fee be compared directly to an EPC price?

Only after reconciling the work and obligations included in each number. Separate services, owner purchases, construction contracts and remaining interfaces in the comparison.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow