Flushing Creek CSO disinfection: reconcile three site functions before pricing
Reconcile Flushing Creek disinfection procurement with the planning report’s three physical site interfaces before pricing.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
The City Record Online listing, checked November 17, 2026, identifies DEP solicitation CSO-FC-DF, EPIN 82627B0019, and lists a December 16, 2026 due date with documents in PASSPort RFx38460. Verify the live listing and addenda before relying on that date. The issued package was inaccessible for this review, so neither the full scope nor an unamended deadline can be confirmed here.
The February 2, 2026 City Planning Commission report describes two proposed new sites and retrofit work inside the existing Flushing Bay CSO retention facility. That planning boundary is a valuable scope map, but does not prove that every element is included in this particular issued contract.
Build a physical site and function register
| Location | Planning context | Estimator's question |
|---|---|---|
| Avery Avenue | One of the new disinfection facility sites | What site work, process equipment, utilities and access are in the issued package? |
| 32nd Avenue and College Point Boulevard triangle | The other new facility site | What are the property limits, delivery route and street interfaces? |
| Existing Flushing Bay CSO retention facility | Retrofit inside an operating facility | Which shutdowns, protection, tie-ins and restoration are assigned? |
| Connections between sites | Planning describes disinfection and dechlorination functions for TI-010 and TI-011 | Which pipe, power, controls and test boundaries appear in this contract? |
The report uses inconsistent chlorination labels in its narrative. Avoid resolving that discrepancy by assumption: use the physical site descriptions and ask DEP to reconcile the process drawings, equipment schedules and bid documents. Do not infer chemical equipment quantities or pipeline routes from the planning report.
Trace one connection through access and testing
For each connection shown in the issued set, identify where the new pipe or cable starts and ends, who exposes the existing service, who makes the tie-in and who tests and restores the work. At the existing facility, obtain the actual operating constraints and identify the party responsible for arranging any isolation or access. At the triangle, distinguish work inside the site from any street occupation that the contract requires. An unassigned transition can leave two complete-looking proposals with no funded connection.
Use the underground scope boundary review to level the pipe interface. The St Albans cloudburst project involves a different storage chain, not the same disinfection scope.
Reconcile the issued package before a commitment
Request the PASSPort drawings, specifications, addenda, site access and operational restrictions, bid form and clarification responses. Compare the issued site limits and process diagram to the planning locations, then document exclusions and priced alternatives. If the package cannot be obtained, treat the planning report as context only, not as a basis for a firm construction commitment.
Related reading
The five-foot line: plumbing and site utilities
Review plumbing and site-utility endpoints, connections, excavation and fees against actual project requirements before assigning scope or carrying a price.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow