High Line 10th Avenue Square: separate framing, salvaged decking and planted areas

Track salvaged decking from removal through reinstallation separately from framing and planted-area work. The two agency records describe related work at the same location, but they do not establish a single contract.

Guide2 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Two records at 10th Avenue Square
  2. Assign the interfaces before carrying the price
  3. Hold point before decking removal

Track salvaged decking from removal through reinstallation separately from framing and planted-area work. The two agency records describe related work at the same location, but they do not establish a single contract.

Two records at 10th Avenue Square

One agency record describes replacing Sunken Overlook framing and reinstalling salvaged decking. A second agency record describes reconstructing structural wood framing, tree pits and irrigation at 10th Avenue Square. The NYC Capital Projects Dashboard May2026 agency record: P-3HLSNKN lists the phase as Pre-Design in its May 2026 reporting period. Its agency data date is 2026-06-24. This is a source-dated narrative, not evidence of a live tender, an award or observed physical progress.

Assign the interfaces before carrying the price

InterfaceScope or questionEstimator review
Overlook framingRemoval and replacementDefine limits and temporary support in the design.
Salvaged deckingRemoval, storage and reinstallationIdentify tagging, protection and responsibility for unsuitable pieces.
Tree pitsReconstructionCoordinate protection and access with the landscape scope.
IrrigationReconstructionIdentify isolation, tie-ins, testing and restoration.

The table is estimator analysis, not an owner scope assignment. Compare the issued drawings and specifications with each bidder’s qualifications. Record the drawing revision and the package that accepts each connection, restoration and test.

Hold point before decking removal

Illustrative estimator analysis: inventory each area of decking against its intended destination, record condition and agree who decides whether a piece can be reused. Assign protected storage and the cost treatment for damaged or unsuitable material. Separately show tree-pit and irrigation tie-ins; do not assume a salvage contractor owns landscape reinstatement.

Both records are pre-design descriptions. Obtain the eventual drawings, salvage criteria and procurement boundaries before combining or allocating the work.

For the next review, use the trade scope generation and logistics estimate review to carry the selected assumptions into trade scope.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.