Homecrest Cloudburst project: porous streets and underground storage interfaces
Separate Homecrest street capture, candidate storage sites and restoration before turning a neighborhood flood concept into an estimate.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
The Homecrest Cloudburst announcement supports a planning estimate for street capture and possible underground storage, not a takeoff of fixed tank sites. The preconstruction decision is whether the available design identifies a complete path from porous pavement through a connection to storage and restoration. If it does not, keep the missing quantities and site decisions visible.
On April 30, 2026, the city announced $95 million in DEP funding for a project targeting a 350-acre Homecrest area including Kings Highway, Coney Island Avenue and avenues P, R, S, T, U and V. Planned methods include porous street pavement and underground storage on public land. Traffic triangles, courts, schoolyards and parking lots were being evaluated. The funding announcement is not a construction award, and those categories are not a list of final tank locations.
Convert site selection into an estimating register
Use the following as a decision register, not a list of confirmed work. Price only the alternatives supported by the current assignment and disclose the basis.
| Decision | Evidence to request | Estimate affected |
|---|---|---|
| Street capture | Drainage map, pavement limits, sections and subsurface investigation | Removal, porous surface, base, excavation and traffic arrangements |
| Storage site selection | Selected public parcel, footprint, access and existing utilities | Excavation, storage structure, protection and site constraints |
| Capture-to-storage connection | Pipe alignment, invert elevations, crossings and connection details | Pipe, structures, utility conflicts and tie-in work |
| Surface restoration | Existing-use survey and proposed finished surface for the selected parcel | Pavement, landscape or recreation reinstatement and maintenance |
| Operating handoff | Access points, inspection and maintenance responsibilities in issued documents | Access features, testing and turnover documentation |
If the selected site moves from a traffic triangle to a schoolyard, do not merely swap the surface area in the estimate. Revisit the connecting alignment, construction access, protection and restoration limits. No location or sequence is assumed here. The plumbing underground scope boundary provides a useful method for assigning connections where two drawing disciplines meet.
Reconcile estimates when the design matures
Request the current design and drainage boundary, site-selection record, utility investigations, sections and procurement documents. Compare the street and storage scopes line by line, including temporary work and reinstatement. A design assumption can be carried as a named alternative, but should not be presented as an agency-selected solution.
The city's announcement includes an estimate of annual stormwater managed, which is a forecast rather than measured post-construction performance. It does not establish a start date or contract quantities. Use the NYC public bid review checklist to distinguish a public funding announcement from documents that actually govern a bid.
The Brownsville South hub review works from a different evidence stage: its April 2026 presentation names three potential public sites and a planned design submission. Homecrest's announced neighborhood and site categories should remain provisional until its own current design selects locations. Neither project supplies quantities for the other.
Related reading
The five-foot line: plumbing and site utilities
Review plumbing and site-utility endpoints, connections, excavation and fees against actual project requirements before assigning scope or carrying a price.

NYC public construction bid review: connect the requirement to the number
A NYC public-bid review should trace owner requirements into scope, quotes, schedule and the final number. A practical review map for small GC precon teams.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.