How to do AI bid leveling for site utility bids, step by step
Level storm, sanitary and water bids with AI using source-backed scope rows, depth and payment checks, reviewed adjustments and a defensible carry decision.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 11 min
- Published
On this page
- 1. Define utility rows that survive different proposal formats
- Make the building handoff explicit
- 2. Establish the document baseline and proposal lineage
- 3. Delegate extraction, not scope ownership
- An example instruction for site utility bids
- 4. Normalize depth and payment content before calculating plugs
- Worked example: the low base survives, but the carry changes
- 5. Review the interfaces that a complete-looking matrix can miss
- Connection permission is not connection scope
- Testing can require work after installation is finished
- Dewatering and unsuitable replacement are related, not identical
- 6. Separate the comparable position from the commitment
- Keep utility requirements and carry decisions connected
For a GC estimator leveling storm, sanitary and water proposals on a commercial hard-bid project, start by defining the required work by segment, connection and acceptance condition. Then use AI to extract proposal terms and map them to that basis. Do not ask it to choose the most complete bid from the proposals alone.
The useful output is a two-sided evidence record: where the project requires the work, and where the bidder includes, excludes or qualifies it. A price adjustment comes afterward. A sewer length can be correct while its depth basis is wrong; a tap can be excluded while connection labor remains included; testing can be priced without the return visit needed to perform it.
This process assumes a defined solicitation package and accessible proposal documents. At DD or an early GMP, retain unresolved design assumptions as assumptions rather than turning them into missing-scope verdicts. For the underlying leveling process, use the construction bid leveling guide.
1. Define utility rows that survive different proposal formats
Build a small project-basis register before loading bids. Each row needs a system, physical limit, requirement source, quantity basis and intended package owner. Give it an ID that will stay the same when the number changes.
Use rows such as:
- SAN-01: sanitary main from MH-1 to MH-2, with pipe size, material, profile reference and priced depth definition.
- SAN-02: connection at the existing manhole, including opening, connector, benching and inspection obligations where specified.
- STM-01: storm drain from inlet I-3 to I-4, including the selected joint and bedding requirements.
- WAT-01: domestic water from the utility connection to the stated building handoff.
- FIR-01: fire service from its connection to its separate handoff, with acceptance requirements identified.
- RST-01: trench restoration by surface type and drawing limits.
- TMP-01: specified temporary support, dewatering or bypass work, with responsibility still open where the documents do not settle it.
Split a run when its material, depth pricing, installation method or restoration basis changes. Do not split every fitting into a cost row merely because AI extracted it separately. The question is whether that fitting is already part of the quoted assembly.
The official documents used here are the active UFGS guides for water distribution, August 2024, sanitary sewerage, May 2018, stormwater utilities, November 2021 and earthwork, August 2023, checked November 24, 2026. These are editable military construction guide specifications, not universal commercial-project requirements. Use the issued project specifications and applicable utility-owner requirements for the actual bid.
Make the building handoff explicit
UFGS 33 11 00, paragraph 3.2.1.1.1, terminates its water-line work approximately five feet from the building unless otherwise indicated. Its opening guidance also distinguishes this exterior work from piping typically covered by Division 22 near the building. That is a document convention, not evidence that two subcontractors priced matching endpoints.
Require a physical handoff description in both proposals: location, elevation where relevant, termination fitting, cap or plug, and who makes the final connection. The plumbing and site utility boundary guide addresses that interface in detail.
Recommended decision rule: a boundary row is closed only when the project limit and both adjoining package commitments agree. A drawing note alone closes neither subcontractor's coverage.
2. Establish the document baseline and proposal lineage
Collect the civil plans and profiles, utility details, applicable specification sections, issued scope sheet, geotechnical information, utility-owner correspondence included in the solicitation, addenda and prebid answers. Include earthwork and restoration documents where they affect the utility package.
For each proposal, record the original filename, date, attachments, stated drawing or addendum basis and subsequent written clarifications. Identify whether a revision replaces the whole proposal or changes only named items. If that is unclear, ask the bidder rather than allowing AI to combine favorable terms from different versions.
Keep two statuses separate:
- Receipt status: the bidder acknowledged the addendum.
- Pricing status: the bidder confirmed which changed work its price includes.
For example, an illustrative revision may acknowledge Addendum 2 yet retain a sanitary depth limit copied from the original proposal. The acknowledgment does not resolve the old limit. The relevant review is the revised profile against that surviving qualification, not the addendum box alone.
Use the drawing revision cascade guide for tracing upstream changes into affected commitments.
Checkpoint: every bid has one identified current commercial position, with unresolved revision conflicts visible. Do not proceed with an unidentified mixture of base quotes and amendments.
3. Delegate extraction, not scope ownership
Ask AI for structured extraction before asking for a leveled number. Preserve the bidder's actual wording beside any normalized description.
Extract base price, inclusions, exclusions, qualifications, alternates, allowances, unit prices, quantity assumptions, depth bands, connection limits and addenda acknowledgments. Require filename and page references, plus the relevant passage. For a spreadsheet, require sheet and cell references instead.
Use these coverage states: explicit inclusion, explicit exclusion, qualified inclusion, not addressed, conflicting evidence and not applicable. Treat “not addressed” as an open question. It is not permission to enter zero, and it is not automatically proof of exclusion.
| Review task | Delegate to AI | Estimator decides | Evidence to require |
|---|---|---|---|
| Proposal extraction | Structure price and commercial terms | Whether extraction matches the original | Proposal passage with file and page or cell |
| Scope mapping | Suggest matching project rows | Whether physical limits and assemblies match | Requirement source plus proposal source |
| Depth normalization | Identify bands and extend approved quantities | Depth datum and rate applicability | Current profile, quantity basis and quoted rate terms |
| Connection review | Separate tap, fees, labor and support terms | Who carries each part of the connection | Project detail, issued owner requirement and bidder commitment |
| Gap review | Flag exclusions, silence and contradictions | Clarification, adjustment or carry elsewhere | Both sides of the scope difference |
| Revised quote review | Identify changed and surviving terms | Which revision governs | Original, revision and written clarification |
| Carry preparation | Assemble reviewed adjustments and open items | Final number and accepted exposure | Adjustment basis, reviewer treatment and current bid |
This is a delegation plan, not a claim that every AI tool can perform every task reliably. Test the output against the documents you supplied. The tool-neutral AI bid leveling workflow covers the broader review controls.
An example instruction for site utility bids
Use an instruction like this after the estimator has approved the row register:
Compare the supplied storm, sanitary and water proposals against the approved utility row register and current document index. Preserve each bidder's price and wording. For every row, return the project requirement source, proposal source, coverage state, quantity and unit, depth definition, physical endpoints, included assembly components and open questions. Extract alternates, allowances and unit prices separately from the base bid. Separate utility-owner fees and tap work from contractor connection labor, excavation, support and restoration. Do not assume five feet from the building is the agreed package boundary. Do not treat silence or addendum acknowledgment as inclusion. Flag contradictions between plans, profiles, specifications, scope sheets and proposals without resolving document precedence yourself. Show formulas only where quantities and rate applicability are supported. Do not invent rates or adjustments. Return unresolved scope and unreadable sources for estimator review, not a bidder recommendation.
The essential control is the separate requirement and proposal source. One citation to a civil detail cannot establish what a subcontractor priced.
4. Normalize depth and payment content before calculating plugs
A site utility comparison needs more than common units. It needs common rate content.
For each unit-priced row, establish the measurement endpoints, depth datum, included excavation and backfill, appurtenances, testing and restoration. Where a proposal gives a depth limit without a definition, clarify whether it refers to cover, invert depth or excavation depth. Do not select the cheapest interpretation.
The UFGS guides illustrate why this matters. Water paragraph 1.1.2 includes pipes, joints, specials and fittings in the line rate, while hydrants, valves and valve boxes have separate each-item payment. Testing and necessary incidentals are included in payment. Stormwater paragraph 1.1 discusses whether excavation is part of completed-work items or separately paid, and paragraph 1.1.3 provides structure pricing with additional depth payment. Those arrangements apply only when retained in the project's payment basis. They cannot be imposed on a subcontractor's differently structured quote.
Recommended check sequence: read the quoted rate, then its inclusion clause, then the project measurement basis, then the profile or detail. Only after all four agree should AI extend the row.
Worked example: the low base survives, but the carry changes
The following numbers and documents are illustrative, not market rates or a customer result.
Assume a hard-bid commercial project with 600 LF of sanitary main. The estimator verifies the current profile and the bidders confirm that depth means finished grade to invert. The approved comparison quantities are 400 LF up to eight feet and 200 LF over eight feet through twelve feet.
Bidder A quotes a $420,000 base including all 600 LF at the shallow rate, with an incremental $45/LF surcharge for the deeper band. Its base excludes pavement patching, sanitary CCTV and connection standby. Bidder B quotes $452,000 and explicitly includes those items and both depth bands. Both bids otherwise carry the same required package.
The reviewed adjustment record for A is:
- Deeper sanitary segment: 200 LF × $45/LF incremental surcharge = $9,000.
- Pavement restoration: 300 LF × six-foot specified restoration width = 1,800 SF; 1,800 SF × an estimator-approved illustrative $8/SF quote = $14,400.
- Specified sanitary CCTV: separate illustrative quote of $4,500.
- Connection standby: illustrative agreed allowance of $2,000.
A's comparable position is $420,000 + $9,000 + $14,400 + $4,500 + $2,000 = $449,900. It remains $2,100 below B, not $32,000 below B.
The material decision is not the addition. It is whether the $45 rate is incremental or a replacement rate, whether patching belongs in this package, and whether A has committed to the reviewed work. If restoration is carried in the paving package, retain it in the comparison as project cost attributable to A's exclusion but do not book it again in the utility award.
Now assume an illustrative late profile revision moves another 100 LF into the deeper band without changing total pipe length. A's evaluated position increases by 100 × $45 = $4,500, reaching $454,400. B would be $2,400 lower only if B confirms its $452,000 price covers the revised profile. An unchanged total length does not preserve the comparison.
For exclusions beyond this example, use the subcontractor exclusions and qualifications review.
5. Review the interfaces that a complete-looking matrix can miss
Run three targeted reviews after mapping. These are checks on the comparison basis, not another request to summarize the bids.
Connection permission is not connection scope
UFGS water paragraphs 3.1.1 and 3.1.2 distinguish making connections in the Contracting Officer's presence from permission to operate existing valves. Sanitary paragraph 3.3.3.2 provides a post-connection inspection before burial where that provision is retained.
Read the applicable connection requirements together with the bidder's tap and fee exclusions. A utility owner performing the tap does not, by itself, settle who excavates, exposes the main, waits for inspection, provides temporary support or restores the surface.
Recommended treatment: break the interface into owner work, contractor preparation, connection execution and acceptance support. Leave any unsupported assignment open. Do not add a generic “tap plug” that hides four unresolved responsibilities.
Testing can require work after installation is finished
UFGS stormwater paragraph 3.9.1.2, where selected, requires flexible-pipe deflection testing no sooner than 30 days after final backfill and compaction testing, and after work imposing loads over or adjacent to the pipeline, including paving. Water paragraph 3.1.3 separately directs trench earthwork to Section 31 00 00.
Together, these provisions expose a package-sequencing question: the utility subcontractor may finish installation before another package finishes the overlying work that permits final testing. “Testing included” does not tell the GC whether the bid includes remobilization, access coordination and the required cleaning before that later test.
Require confirmation of the test sequence and return visit, not just a testing checkmark. Do not assume sanitary and storm acceptance methods are interchangeable; the sanitary guide separately identifies leakage, deflection and inspection provisions.
Dewatering and unsuitable replacement are related, not identical
UFGS earthwork paragraph 1.2.12 says satisfactory material can become unstable through ineffective drainage or dewatering. Stormwater paragraph 1.1.8, where used, bundles removal, disposal and replacement into the payment for backfill replacing unstable material.
An exclusion for dewatering beside an allowance for unsuitable replacement therefore needs more review than two independent plugs. Ask what each price assumes about keeping the trench stable, what triggers replacement, and whether removal and disposal are included. Otherwise the comparison can accept an allowance whose quantity basis depends on an unpriced operation.
That is a basis conflict, not proof that the bidder's means and methods are defective. Resolve it with the bidder and the project team before choosing the adjustment.
6. Separate the comparable position from the commitment
Issue clarifications by row ID. Ask one question with a physical limit and requirement reference, then request confirmation of inclusion, added price or revised qualification. Record the answer as a new source.
Before carry, classify every adjustment as one of four treatments:
- Accepted bidder revision, incorporated in the current proposal.
- Estimator adjustment, with a supported quantity and price basis but no bidder commitment yet.
- Work carried in another package, with that package's coverage identified.
- Unresolved exposure, with an owner and next action.
Competent estimators may differ over carrying A's adjusted position or B's confirmed package in the example. The deciding facts should be the remaining qualifications, documented price commitments and ability to close the interface before award, not a preference for the largest number or the most polished matrix.
Keep the raw bid, comparable position and intended award amount visible separately. Reopen affected rows when a profile, restoration detail or connection requirement changes. A reviewed row is not permanently closed merely because its earlier arithmetic was correct.
Keep utility requirements and carry decisions connected
The workflow needs one current project basis connecting profiles, specifications, proposals, revisions, clarifications and adjustments. Otherwise the row that changes depth and the bid that still carries the old band can look independently complete.
In its Bid Leveling workflow, Piper compares subcontractor proposals against intended scope and relevant project information, extracts commercial terms, and surfaces source-backed gaps, exclusions and qualifications. Revised bids, addenda and clarification responses remain connected to the leveling workflow. The estimator reviews adjustments and decides the carry.
The useful standard remains the same with or without Piper: another estimator should be able to open a row, inspect both sources, understand the adjustment and distinguish a priced commitment from an unresolved assumption.
FAQ
Can AI level site utility bids without a GC takeoff?
It can help extract and map proposal terms, but the GC still needs a defensible quantity basis for quantity-dependent adjustments. Use verified project quantities or reviewed takeoff where appropriate. Do not let AI average bidder quantities to manufacture the reference length, restoration area or depth-band allocation.
Should silence about testing be treated as an exclusion?
No. Mark it not addressed and seek confirmation against the specific project test and acceptance requirements. A bidder may include testing within an assembly price, but silence does not establish that commitment. Separate the test itself from cleaning, inspection support and any required return visit.
How should utility-company fees and taps be handled?
Separate fees, owner-performed tap work and contractor connection support into distinct rows. Use the issued utility-owner requirements and proposal commitments to assign them. An exclusion for fees does not establish an exclusion for excavation or connection labor, and owner-performed work does not automatically cover restoration.
What should happen when a revised profile changes depth but not length?
Recheck the affected depth bands and each bidder's current pricing basis. Preserve the unchanged length, calculate only supported incremental adjustments, and obtain confirmation from any lump-sum bidder before assuming its price covers the revision. Reopen related structure or temporary-work rows if their basis also changes.
Utility bid leveling depends on connecting each drawing or specification requirement to the bidder's coverage and the final carry, especially when revisions change the pricing basis. The software comparison for creating trade scopes from drawings and specifications compares scope and bid-package assembly with a requirement-to-carry workflow, including how Piper connects source-linked trade scopes to proposal exclusions using drawings, specifications, addenda and company standards.
Related reading
The five-foot line: plumbing and site utilities
Review plumbing and site-utility endpoints, connections, excavation and fees against actual project requirements before assigning scope or carrying a price.

Construction bid leveling: a practical guide for GCs
How to level subcontractor bids across design-bid-build, CM-at-risk, design-build, and progressive design-build, and why the same spreadsheet does not work for all of them.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.