I-35 Capital Express South: separate elevated lanes, creek bridges and bypass scope
Review I-35 Capital Express South across elevated lanes, at-grade sections and creek bridges, distinguishing new structure, widening and bypass connections.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
Use separate estimate lines for elevated work, at-grade transitions, the bypass and each creek crossing. A single corridor quantity can hide different structural and staging interfaces.
The dated project record
TxDOT describes the SH 71 to SH 45 SE project as adding two HOV lanes in each direction, including elevated and at-grade sections and a southbound bypass of Stassney Lane and William Cannon Drive. It identifies reconstruction at South Boggy and Onion creeks and widening at Slaughter Creek. Construction began in November 2022, with late 2028 forecast for completion; Fluor is listed as contractor. The source is TxDOT CapExSouth. Check the current owner record before relying on any date or project status.
Distinguish reconstructed bridges from widening
The following is an estimating review, not a statement that the owner assigned these tasks to a particular contractor. Use the current drawings, specifications and contract documents to settle the actual boundaries.
| Scope or location | Review and assignment question |
|---|---|
| Elevated lanes | Identify foundations, superstructure, access and transitions to at-grade work in the issued limits. |
| Stassney and William Cannon bypass | Trace the bypass connection to adjoining roadway and traffic stages; identify who carries each tie-in. |
| South Boggy and Onion creeks | Review reconstruction limits and temporary access separately for each crossing. |
| Slaughter Creek | Distinguish widening from complete reconstruction; reconcile existing-structure interfaces and approach work. |
Track the elevated-to-at-grade sequence
For example, a bridge proposal may cover a structure while its roadway counterpart assumes the approach is included. Mark the physical end point and stage on both scopes before accepting either assumption.
Keep the South Boggy Creek and Onion Creek reconstruction rows separate from Slaughter Creek widening. A scope based on full replacement can misstate the retained-structure and approach assumptions at a widening; the issued design must define the actual extent.
Evidence needed for this package
Obtain the elevated-lane and at-grade transition details, each creek crossing's retained-work limits and the bypass staging around Stassney Lane and William Cannon Drive. Exclude an expired one-night closure from today's access basis.
For the broader method, see the logistics estimate review. Use the project-specific register above to bring the general boundary review back to the actual work.
Related reading
Construction logistics plans: turn access and storage assumptions into priced scope
A site logistics drawing is useful when its assumptions reach the estimate. Review access, storage, deliveries, handling and repeated moves before pricing.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.