I-35 University segment: review crossings, Airport Boulevard and pedestrian work
Review I-35 University segment scope by named crossing, including Airport Boulevard and Capital Plaza, before assigning temporary access and utility responsibilities.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
TxDOT anticipates construction of the I-35 Capital Express Central University segment from 2027 to 2033, weather permitting, and lists its contractor as TBD. The overview names five reconstructed crossings, the Airport Boulevard intersection and a Capital Plaza pedestrian bridge. TxDOT University segment Source status checked November 17, 2026. Make the crossing, rather than the trade, the first unit of review. Each crossing has a different combination of traffic, utilities, pedestrian access and temporary works that must be assigned in the issued staging plan.
Build a register for the five named crossings
The following register is estimating analysis, not a statement of the owner’s contract assignments. The owner overview establishes the project context; the current drawings, specifications and package documents determine what a bidder must carry.
| Interface | Review boundary | Decision to resolve |
|---|---|---|
| Manor and Dean Keeton | Crossing reconstruction | What access and utility continuity must each stage retain? |
| 32nd and 38½ streets | Crossing reconstruction | Who carries temporary crossings, relocation and final restoration? |
| Wilshire Boulevard | Crossing reconstruction | Where do bridge, roadway and utility limits meet? |
| Airport Boulevard | Intersection reconstruction | Which package controls signal changes and traffic transitions? |
| Capital Plaza | Pedestrian-only bridge | Who carries approaches, temporary pedestrian routes and handback? |
TxDOT’s contractor field says TBD; that is a status on its overview, not proof that a trade solicitation is open. TxDOT University segment
Make the crossing the unit of scope review
For each location, place issued plan sheets, stage dates, maintained movements, utility owners and bid exclusions in the same row. Ask a targeted RFI where a temporary sidewalk or signal is shown but no package takes installation and maintenance. Confirm every assumption against the current documents before setting a carry.
The University description identifies Manor Road, Dean Keeton Street, 32nd Street, 38½ Street and Wilshire Boulevard, plus the Airport Boulevard intersection and Capital Plaza pedestrian bridge. Keep a separate row for each location: grouping the work as 'crossings' hides which roadway movement, utility connection or accessible route a particular stage must preserve.
Documents to request before committing
Obtain the individual crossing plans and stage diagrams, intersection signal transitions, utility-owner requirements and Capital Plaza approach details. Keep this segment distinct from Downtown upper-deck removal and lowered-mainlane work unless issued documents expressly connect the responsibilities. A contractor field of TBD does not establish an open solicitation.
The logistics estimate review provides a broader method for documenting these boundaries and carrying unresolved assumptions through bid review.
Related reading
Construction logistics plans: turn access and storage assumptions into priced scope
A site logistics drawing is useful when its assumptions reach the estimate. Review access, storage, deliveries, handling and repeated moves before pricing.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.