North Hawk and Orange Street: reconcile court and stormwater scope

Reconcile the porous court, subsurface storage, sewer and outlet controls described in Albany’s capital plan.

Guide2 min read

Published

Tower crane above steel reinforcement

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Connect the court surface to the drainage system
  2. Close the funding and design questions separately

At North Hawk and Orange Street, a court price and a storm-sewer price do not by themselves demonstrate complete coverage. The estimating decision is where the porous playing surface, storage below it, retaining edges and controlled outlet meet, and which proposal carries each transition.

The Albany Water capital plan, printed sections 3-6 and 3-8 (physical PDF pages 60 and 62), describes a project at 127 Orange Street combining a separated Orange Street storm sewer, bioretention, regraded porous basketball court, subsurface stormwater management, retaining walls and seating. An actuated outlet valve uses real-time controls. The December 2025 plan anticipated construction beginning in 2026 but said the Water Board awaited an executed grant. That planning statement does not establish that a grant was subsequently executed, construction began, or a bid is open.

Connect the court surface to the drainage system

The source describes the intended system, not the limits of individual trade contracts. The following is estimating analysis: use it to test proposed package splits once a current issued set exists.

BoundaryCheck against the issued revisionsQuestion for the carry
Court elevations and storageGrading, section and storage details at the same revisionWho owns subgrade preparation and the transition from porous surface to the system below?
Storage and sewerConnection location, invert and any separation limitsDoes either civil proposal carry the complete connection and reinstatement?
Walls, seating and landscapeEdge details, finished grades and adjacent bioretentionWho carries excavation, foundations and finish where the court meets a wall or seat?
Outlet valve and controlsValve location, power, control sequence and testing requirementsWho supplies, installs, wires, programs and demonstrates each part if required?
Bioretention and courtOverflows, edge grades and planting limitsAre surface grading and drainage paths included consistently by both bidders?

An illustrative mismatch: a court contractor prices the playing surface to the top of prepared base, while the civil contractor excludes final grading beneath the court. A low total may conceal the missing preparation. Request a defined elevation and a written interface before accepting either price as complete. Conversely, do not double-carry the same connection because both trades reference it without stating who performs it.

Close the funding and design questions separately

Before committing an estimate, request the latest solicitation and addenda, grant and authorization status, civil and landscape sheets, control narrative, and any owner-defined work limits. Compare section cuts to the grading plan, then record the revision and proposed responsible bidder for every unresolved edge. Ask for a clarification where documents leave the outlet control, power or acceptance boundary unclear. These are questions for the current package, not requirements established by the capital plan.

The Albany project-stage guide helps separate capital planning from bid evidence. Use the bid coverage guide to compare the actual responses once a package is issued.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.