Hirsch Center records renovation: price the fourth-floor move with the fit-out
Separate fourth-floor fit-out, evidence and records relocation, and ongoing operations at the Hirsch Center.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
At the Hirsch Center, treat the fourth-floor fit-out and the move as connected but separately assigned scopes. The estimator needs to know who makes the destination ready, who moves owner material and who accepts the space before existing operations change location.
The May 2026 DDC agency record describes renovating portions of the fourth floor to move evidence storage and operations from the cellar and consolidate them with records. It also names offices, storage, new restrooms and a pantry. Agency data dated June 23, 2026 lists construction procurement; that is not proof of a current invitation or move.
Make the move a separate responsibility line
This is an estimator's interface register. It does not describe actual security procedures or a documented move sequence.
| Work | Boundary question | Information to obtain |
|---|---|---|
| Fourth-floor construction | Who provides partitions, finishes and building-system changes? | Issued plans and room schedule |
| Storage and offices | Who supplies and installs storage equipment and furniture? | Owner-furnished equipment and fit-out schedule |
| Restrooms and pantry | Who carries plumbing, ventilation, electrical and finishes? | Coordinated MEP and architectural drawings |
| Relocation | Who packs, transports and accepts owner materials? | Owner-approved move responsibility matrix |
| Continued operations | What access and service interruptions are permitted? | Owner-approved phasing and operational constraints |
Do not infer the contents, handling method or security arrangements from the phrase evidence storage. The owner should define those requirements through the appropriate project channels. The construction estimate can still identify the existence of a relocation interface and the need for an agreed responsibility and schedule.
Set a destination-ready gate
In an illustrative phasing plan, complete and test the destination's building systems and finishes, install agreed storage and equipment, obtain owner acceptance and only then schedule the move. The actual sequence and acceptance criteria must come from the owner and issued documents. Identify any temporary space and double handling only if supported by the plan or an explicit estimating assumption.
Before bid leveling, reconcile the move, utility shutdowns, protection and final cleaning with the fit-out bids. An exclusion for owner moves does not answer who prepares the route or corrects destination deficiencies.
For the broader package review, use the trade scope generation and the phasing estimate review.
Related reading
Construction scope generation: a practical guide for GCs
How general contractors turn drawings, specifications, addenda, and company standards into trade scopes a subcontractor can price, an estimator can trace, and a senior reviewer can challenge.

Construction phasing: price the handoffs as well as the work periods
A construction phase is more than an activity label. Review pricing setup, temporary work, turnover, remobilization and the sequence behind the estimate.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.