Creekwalk Phase 3: separate trail sections, bridge scope and funding assumptions
Separate two trail sections and reconcile conflicting schedule and bridge funding statements before forming a Creekwalk Phase 3 estimate.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 2 min
- Published
On this page
For a preconstruction team tracking Creekwalk Phase 3, the immediate decision is whether a future package covers the northern trail conversion, the southern creekside route, bridge replacement, or a defined combination. The city's planning page does not resolve that decision today. Keep bridge count, funding, right-of-way and dates as open items until current issued documents settle them.
The city project page, checked November 17, 2026, describes the three-mile extension from West Colvin Street to Dorwin Avenue as in design. It identifies a preferred route and two sections. Its dates and bridge descriptions are planning statements, not proof of an open bid or completed construction.
Two sections imply different work
Section 3.1 runs from Colvin Street to Ballantyne Road. The city describes narrowing the existing parkway surface in the northern portion and expanded or new sidewalks along the next portion, with crossing improvements. That suggests an estimating review should separate removal and conversion of existing pavement from sidewalk and crossing work, subject to the eventual plans.
Section 3.2 runs from Ballantyne Road to Dorwin Avenue along the creek channel. The planned route includes connections to the Van Duyn and Clary/Chaffee pedestrian bridges, a route under Seneca Turnpike, and improvements at Dorwin Avenue. Those features create different questions about creekside access, bridge interfaces and working limits. Their presence on a planning map does not establish quantities or procurement boundaries.
Keep the discrepancies visible
| Decision | City page evidence | Estimator treatment |
|---|---|---|
| Section 3.1 date | Narrative estimates 2027; detailed timeline shows summer 2028 to summer 2029 | Retain both as forecasts and request an updated schedule before pricing time-dependent assumptions |
| Bridge count and funding | Goals and detailed timeline mention two replacements; section narrative estimates enough funding for one and seeks funding for the second | Price only the issued scope; record alternate bridge treatment and funding as unresolved |
| Section 3.2 funding | The timeline identifies future funding work and a later construction phase | Do not treat the full southern route or both bridges as an already funded issued package |
| Right-of-way and approvals | The page describes property needs and future design and funding approvals | Obtain current acquisition status and access constraints before relying on a work sequence |
The apparent inconsistencies may reflect updates made at different times. The page does not identify which statement controls. A pursuit team should attach the conflicting passages to its assumptions register and request clarification, rather than selecting the earlier date or counting both bridges as funded work.
Turn the planning record into an estimate basis
Start separate registers for 3.1 and 3.2. For each, record the latest drawing revision, limits, surface treatment, access and restoration assumptions. For the bridges, identify whether a future package requires replacement, connections to a retained bridge, or a separately authorized alternate. A bridge omitted from the base package can still affect adjacent path limits and access.
For right-of-way, ask whether the land needed for each access and work area has been acquired and when it will be available. Confirm funding agreements and approvals from the current project record; a planned milestone is not a completed approval. If the documents leave a potential scope unresolved, use the project's commercial rules to determine an appropriate qualification or allowance and name the information that releases it. The general distinction is covered in contingency and allowance review.
Related reading
Construction contingency vs. allowance: name the uncertainty before carrying it
Allowances and contingency address different estimating questions. A GC review for separating undefined selections, identified risks and missing trade coverage.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.