Pennsylvania Separations Act: writing scopes for multiple-prime public work
Write Pennsylvania public-building scopes around prime-contract boundaries, verified exceptions and the handoffs that change who carries openings and coordination.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 10 min
- Published
On this page
- Confirm the owner's statute before building four packages
- Treat energy exceptions as boundaries, not blanket permission
- Separate who coordinates from who performs the interface
- Write openings as a chain of obligations
- Worked review: the cheaper opening method may belong to another prime
- Resolve the boundary through the bid documents, not a private scope rewrite
- Keep the prime boundary connected to the changing project
For a GC estimator bidding the general-construction prime on a Pennsylvania public-building renovation, the first scope decision is not which MEP subcontractors to solicit. It is which contracts the public owner will award and which interfaces remain in your contract.
On a covered multiple-prime solicitation, write the general-construction scope around obligations to other primes, not around MEP work you assume you will buy out. Section 1 of the Separations Act requires separate specifications, bids and awards for the named plumbing, heating, ventilating and electrical branches. It does not provide a complete allocation of every opening, sleeve, control connection or temporary service. Act of May 1, 1913, P.L.155, No.104, §1, commonly cited as 53 P.S. §1003.
That distinction changes the estimate. A scope gap may require an owner-issued clarification across contracts, not a private adjustment between the GC and its subs.
Confirm the owner's statute before building four packages
The operative Act 104 text covers erection, construction and alteration of a public building when the entire cost of the work exceeds $4,000. It directs the specification preparer to separate the named branches and the contracting authority to award each to its lowest responsible bidder. The official compilation identifies the section's December 22, 1981 amendment. Act 104, §1.
Do not turn that sentence into “every Pennsylvania public project requires four primes.” The building limitation, owner-specific statutes and authorized exceptions matter. The following are verified provisions, checked November 24, 2026, rather than an exhaustive exemption opinion for every public entity.
For DGS construction, use the DGS-specific rule. Section 322(6) permits the Department of General Services to dispense with Act 104 below $25,000 total construction cost and expressly subjects projects at or above $25,000 to it. Section 322(2) also subjects DGS design/build contracts to the Act to the extent provided in paragraph (6). Changing the delivery-method label is therefore not itself an exemption. 62 Pa.C.S. §322(2), (6).
For a borough, do not assume the original Act controls. The Act's compiler notes identify its repeal insofar as it relates to boroughs. The current Borough Code uses permissive language: above its applicable contracting amount, separate specifications may be prepared at council's request, and separate bids may be received if those specifications have been proposed. That is a materially different starting point from Act 104's mandatory language. Act 104, compiler notes; 8 Pa.C.S. §1405.
For school districts, read the Public School Code too. Section 751(a.2) has its own separate-contract language and an annually adjusted base threshold under section 120. Do not substitute either the Act's $4,000 figure or the DGS $25,000 figure for the school district's applicable procurement basis. Public School Code, §751(a.2).
The practical gate is a short procurement-basis record:
- Legal identity of the owner, not just the facility name.
- Governing statute and applicable threshold provision.
- Separate-prime or single-contract arrangement stated in the solicitation.
- Any claimed exception, its authority and the work it actually covers.
- Incorporated general conditions, supplementary conditions and current addenda.
If those entries disagree, ask the owner through the prescribed prebid process before rebuilding the scope. An estimator should not resolve a procurement-law conflict by silently changing package ownership.
Treat energy exceptions as boundaries, not blanket permission
Two energy-related provisions can change the contracting arrangement, but neither is shorthand for “renovations are exempt.”
The Guaranteed Energy Savings Act authorizes a governmental unit to enter into a qualifying contract notwithstanding contrary law. Section 3753(g) permits a single guaranteed energy savings contract with each responsible provider selected under that subchapter. The same section contains proposal, report, guarantee and other conditions. Installing efficient equipment alone does not establish that those contracting procedures apply. 62 Pa.C.S. §3753(a), (d), (e), (g).
The Solar for Schools Act is more explicit. An approved grant recipient may use Separations Act or Guaranteed Energy Savings Act procedures. If it elects the latter for an approved solar energy project, section 3(f)(1) exempts that approved project from Separations Act contracting requirements. The official compilation includes the 2025 repeal of the administrative-fee subsection; the project-delivery language remains in section 3(f). Act 68 of 2024, §3(f)(1), (l).
Estimating judgment: if a campus program includes an energy contract and a separately bid building renovation, mark the boundary between them as a scope interface. Do not extend the energy procurement basis to the rest of the campus work without the owner's documented authority.
For example, identify whether a new electrical feeder, roof restoration or shutdown support belongs inside the approved energy project or in the adjacent renovation contract. A legally permitted single energy contract can still meet a separately awarded construction prime at the same physical connection. The exception may reduce the number of contracts within one package without eliminating the handoff outside it.
Separate who coordinates from who performs the interface
For a confirmed multiple-prime job, use two layers of scope:
- Execution scope: the work your prime and its subcontractors must furnish, install, test or restore.
- Interface scope: information, access, sequencing and coordination your prime must provide to or receive from another prime.
Do not price the second layer as if it automatically includes the first.
DGS provides a useful contract-specific example. Its publicly posted 2020 General Conditions say that each prime has an affirmative duty to cooperate. Article 5.1(A)(2) says a retained construction manager assists coordination without relieving prime contractors of their responsibilities. Article 6.2 likewise preserves each prime's coordination duty. These provisions apply when incorporated into the project contract, not automatically to every municipal or school job. DGS 2020 General Conditions, §§4.3, 5.1, 6.2.
The source interaction matters: Act 104 separates procurement; the general conditions reconnect execution through affirmative coordination duties. “Separate prime” is not a valid reason to omit coordination labor, and “lead contractor” is not proof that the lead contractor owns every MEP interface.
For the general-construction estimator, record the lead-contractor role exactly as assigned. Then price its actual responsibilities: receiving opening information, reviewing conflicts, coordinating affected work and supporting the specified schedule process. Keep those costs visible rather than burying them in a broad MEP allowance.
The wider MEP interface review belongs upstream of the price comparison, but on this Pennsylvania arrangement the review must also identify which owner-held contract can implement each decision.
Write openings as a chain of obligations
Openings are a strong test of whether the scope follows the contracts or only the drawing disciplines.
Under DGS's 2020 conditions:
- Section 6.25 assigns penetration identification and dimensions, along with sleeves, fire safing, escutcheons and inserts, to the contractor requiring the penetration.
- Section 6.30 assigns construction of required chases and openings in new walls, partitions and floors to the general contractor, or the contractor designated when there is no general contractor.
- Section 6.25 requires advance information and makes inadequate notification, existing-system penetrations and penetrations through previously completed systems consequential to responsibility for the opening work.
- Section 6.31 permits more extensive restoration, including removal and rebuilding, at the responsible contractor's cost when openings are cut after construction is complete.
Read these provisions together, and check project-specific modifications before assigning work. DGS 2020 General Conditions, §§6.25, 6.30, 6.31.
A scope saying “all penetrations by mechanical” can therefore misallocate new opening construction. A scope saying “all openings by general” can misallocate sleeves, existing-system cutting or consequences of late information.
Use an interface register with separate rows for the work states:
| Interface state | Responsibility to check | Evidence needed before carry |
|---|---|---|
| Opening in new construction | General or designated prime constructs; penetrating prime supplies required information and associated items | New-work detail, opening sketch requirement and §§6.25 and 6.30 |
| Opening through an existing system | Penetrating prime's cutting and patching obligation | Existing-condition detail and §6.25 |
| Opening needed after the system is complete | Responsible prime and restoration treatment | Information history, work sequence and §§6.25 and 6.31 |
| Conflict between proposed penetrations | Prime review duties and lead-contractor coordination role | Coordination sketches and §6.25 |
The register should identify the system and location, not merely a specification section. For each row, add the current drawing revision, construction status, information provider, physical performer, associated sleeve or fire-safing owner, prerequisite and unresolved question.
That is the jurisdiction-specific change to scope writing: the register is a proposed reconciliation between separate owner contracts, not just a GC's internal subcontract coverage chart. The general scope gap register provides the broader artifact structure.
Worked review: the cheaper opening method may belong to another prime
Illustrative example, not a project result or market-price benchmark: assume a DGS multiple-prime renovation incorporating the cited 2020 conditions has 30 comparable wall penetrations. Twenty-four pass through new masonry walls; six pass through retained existing walls.
Assume the general prime's draft allowance prices all 30 as built-in new openings at $140 each:
30 × $140 = $4,200.
The estimator then reads the wall-status drawings against sections 6.25 and 6.30. Only 24 are new-construction openings assigned to the general prime under the stated assumptions:
24 × $140 = $3,360.
For this illustration, the six existing-wall penetrations require a cutting-and-restoration operation priced at $520 each, carried by the prime requiring them:
6 × $520 = $3,120.
The properly allocated direct opening work is therefore $3,360 + $3,120 = $6,480, before separately priced associated items and coordination. The original $4,200 allowance understated the illustrated project-wide work by $2,280 even though the general prime's correct execution scope decreased by $840.
The useful conclusion is not that cutting costs more. It is that the GC's number can go down while uncovered project exposure goes up. A lower general-construction estimate does not prove that the separate penetrating prime carries the existing-wall operation.
The failure starts when a reviewer counts holes without classifying wall status. It survives when every prime uses “by others” without naming the other contract. Catch it by reconciling the opening location, new-versus-existing condition and contractual performer before accepting the carry.
Now assume four of the 24 planned new openings are missed before wall construction. At the same illustrative $520 restoration rate, replacing four $140 built-in operations would add:
4 × ($520 − $140) = $1,520.
That amount is a scenario for the consequence, not an automatic charge to the general prime. Under the cited conditions, inadequate information and the responsible contractor matter. The estimating check should preserve the information handoff and the affected sequence rather than converting every late opening into a GC contingency. DGS 2020 General Conditions, §§6.25, 6.31.
Resolve the boundary through the bid documents, not a private scope rewrite
Competent estimators can disagree about whether to centralize an interface under the general prime or leave it with the penetrating trade. On a private single-prime job, a GC may prefer one specialist for consistency. On a covered Pennsylvania public solicitation, that preference is not authority to rewrite the owner's allocation.
Recommended decision rule: retain the issued allocation unless the owner formally changes or clarifies it through the solicitation process. If you propose centralizing a service, identify every affected prime, inclusion, deduction and coordination obligation. Obtain a common documented basis before treating the transfer as settled.
For a general-prime bidder, a private conversation with a prospective mechanical bidder does not establish what the eventual separately awarded mechanical contract will require. Do not use that conversation alone to remove work assigned to your prime.
During prebid review, classify each issue:
- Clear and assigned: price the work in its required contract.
- Clear but operationally awkward: price the required allocation and ask whether the owner will revise it.
- Conflicting: submit a focused question identifying both sources and the affected contracts.
- Silent: request an assignment; preserve any permitted pricing treatment explicitly rather than calling it covered.
A useful question is: “Detail X shows an opening through a retained wall; section Y assigns new-wall openings to the general prime. Please confirm the contract responsible for existing-wall cutting, restoration and the associated sleeve.” It identifies the decision needed without asking the owner to redesign the entire package.
The broader Division 01 scope review should supply the project-specific obligations that sit outside the obvious trade section.
Keep the prime boundary connected to the changing project
The final artifact should show more than who carries an item. Keep the governing contract, physical location, source revision, prerequisite and unresolved assignment together. When an addendum moves equipment or changes a wall from retained to replaced, recheck both the work and its contractual owner.
For teams systemizing that review, Piper's Scope Generation workflow organizes drawings, specifications, addenda and company knowledge into trade-specific scopes, connects items to sources and surfaces unclear responsibilities for estimator review. A shared, evolving project understanding is useful here because one changed opening can affect several scopes rather than just one quantity. Piper does not decide the applicable legal exemption or authorize a transfer between prime contracts; those decisions remain with the owner and the reviewing team.
Use the AI-assisted scope-writing process for the general drafting method. The Pennsylvania-specific acceptance test is whether the draft respects the verified procurement arrangement and makes each cross-prime handoff inspectable before the number is committed.
FAQ
Does every Pennsylvania public project require four prime contracts?
No. Act 104 addresses covered public-building work, and owner-specific statutes and authorized exceptions change the answer. DGS has a specific $25,000 rule; the Borough Code uses permissive separate-bid language. Confirm the owner's governing law and the issued solicitation rather than applying one statewide slogan.
Can DGS avoid separate primes simply by calling the project design-build?
No. Section 322(2) expressly subjects DGS design/build contracts to Act 104 to the extent provided in section 322(6). The delivery-method label alone does not establish an exemption. Check any independently authorized procurement basis and its conditions before changing the scope structure.
Does a construction manager take over the primes' coordination duties?
Not under the cited DGS 2020 conditions. Sections 5.1 and 6.2 preserve each prime's coordination responsibilities even when a construction manager assists. Review the conditions actually incorporated into your solicitation, then price the assigned coordination role separately from physical MEP installation.
Who carries sleeves and openings on a multiple-prime job?
Read the contract's separate assignments rather than using one universal trade rule. In the cited DGS conditions, the penetrating contractor has specified information and associated-item duties, while the general or designated prime constructs new chases and openings. Existing construction and late information can change the treatment.
Related reading
Construction scope generation: a practical guide for GCs
How general contractors turn drawings, specifications, addenda, and company standards into trade scopes a subcontractor can price, an estimator can trace, and a senior reviewer can challenge.

MEP coordination in preconstruction: assign the interfaces before comparing trade prices
MEP coordination can reveal responsibilities beyond one trade’s drawings. Review supports, openings, controls, access, testing and complete package coverage.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.