Put experience into every bid: turn lessons into pre-bid survey questions

Turn your best estimator’s questions and past lessons into a pre-bid survey that runs on every bid. A worked example with red-flag rules and a 12-question starter list.

Guide3 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. A lesson only changes the next bid if it becomes a question
  2. Worked example: four of a company’s 24 questions, on one new bid
  3. Twelve questions to seed a pre-bid survey
  4. Questions the documents and the law make worth asking
  5. Related guides
  6. Where Piper fits

A company’s hardest lessons usually sit in closeout reports and in the heads of two or three senior people. They only change the next bid when they are written as questions, with a rule for what counts as a red flag, and asked of every bid’s documents.

A lesson only changes the next bid if it becomes a question

On a fast bid, with the senior person on another job, the questions that came from past losses do not get asked.

Putting experience into every bid means writing each lesson as a question with a red-flag rule, asking it of every bid’s documents, and treating “not found in the documents” as a finding rather than a blank.

Worked example: four of a company’s 24 questions, on one new bid

Hypothetical: a GC’s survey template, owned by the chief estimator, has 24 questions in four sections. Three of these came from jobs that hurt. The red-flag rules are the company’s own.

WhereWhat it saysIf nobody connects it
Who provides temporary heat and winter protection?Rule: red if the GC provides it and exterior work runs December to March. Answer: Spec 01 51 00 puts temporary heat on the contractor, and Addendum 2 moves the structural pour to January.Red. Without the question, winter protection is assumed to sit with the concrete sub, who will exclude it.
Liquidated damages, and is there a cap?Rule: red if over $2,500 a day or no cap. Answer: Agreement Article 5, $3,000 a day, no cap stated.Red. The final review checks this against the schedule duration you carry.
Is a geotechnical report part of the bid documents?Rule: red if not found. Answer: not found in the bid documents.Red. “Not found” becomes a pre-bid question before the deadline, not an assumption.
Is a project labor agreement required?Rule: note only. Answer: yes, Instructions to Bidders, item 14.Cited, so labor pricing starts from the right basis.

The temporary heat answer is why the estimator adds winter protection to the GC’s own scope, and why it matters again when both concrete bids exclude it in leveling. One question, three workflows.

Bring the questions your team asks on every bid. Send ten of your standard pre-bid questions and one current bid package. In the demo we run them on your documents together and look at the red flags and the answers that were not found. Book a project demo

Twelve questions to seed a pre-bid survey

A starting point. The value is in your own list and your own red-flag rules.

  1. Delivery method and contract form. And who holds design risk.
  2. Bid security and bonds. Form, percentage, surety rating, and whether you have the capacity.
  3. Liquidated damages. Rate, cap and any consequential damages language.
  4. Schedule constraints. Duration, milestones, phasing, occupied building or night work.
  5. Work assigned to the GC. Temporary utilities, winter conditions, hoisting and site logistics.
  6. Owner-furnished items. Who receives, stores and installs them.
  7. Allowances, alternates and unit prices. The ones the owner sets.
  8. Labor requirements. Prevailing wage, PLA, apprenticeship, local hire, and M/WBE or SDVOB goals.
  9. Missing documents. Geotechnical report, hazmat survey, existing-conditions drawings.
  10. Insurance beyond your standard program. Builder’s risk, wrap-ups, limits.
  11. A past lesson, as a question with a trigger. “If an occupied hospital, does the spec require ICRA Class IV containment?”
  12. Go/no-go signals your company agreed on. Answered by people, with the document answers in front of them.

Questions the documents and the law make worth asking

  • To get a bond, a contractor must meet the surety’s credit, capacity and character requirements, so bonding capacity is a go/no-go input, not a formality. Source: U.S. Small Business Administration.
  • Performance and payment bonds are required on federal construction contracts over $150,000. Source: FAR 28.102-1.
  • On New York public work above set cost thresholds, the owner prepares separate specifications for plumbing, HVAC and electrical, which changes who the GC can coordinate and carry. Source: NY General Municipal Law §101.

Where Piper fits

  • Keep company survey templates with your own questions, instructions and red and green flag rules.
  • Run a survey on each project. Answers cite the page in the bid documents they came from.
  • When an answer is not in the documents, Piper says so instead of guessing.
  • Attach a survey template to a project template so every new project starts with it.
  • The answers stay in the project where scope generation, bid leveling and final review can read them. Your team makes the go/no-go call.

See how the pre-bid survey workflow works, or book a project demo and bring the documents from a bid you are working on now.

ShareLinkedInX

Related reading

Guide7 min

Surveys: the questions worth asking before you bid

A standing pre-bid questionnaire turns the things your best estimator always remembers to check into something the whole company checks every time. How to build one, who answers what, and how to keep it alive.

Tower crane above steel reinforcement

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.