How to write a roofing scope of work subs will price the same way

Write a roofing bid scope around the complete assembly, finished elevations, trade handoffs and warranty basis so subcontractors price the same obligation.

Guide10 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Establish the documents and the pricing basis first
  2. Describe the assembly from the deck upward
  3. Check the taper against the curb, not just the insulation price
  4. Assign the handoffs with verbs and completion conditions
  5. Price the installation sequence and acceptance work
  6. Show the price movement before issuing the package
  7. Use a reusable scope outline without hiding unresolved choices
  8. General and document basis
  9. Inclusions
  10. Exclusions
  11. Work by others and receiving conditions
  12. Clarifications and bidder response
  13. Alternates
  14. Unit prices
  15. Final issue check
  16. Keep the roof assembly and its evidence connected

For a GC estimator issuing a low-slope roofing package at bid CDs or GMP pricing, write the scope around one defined roof assembly and its completed interfaces, not just the membrane specification. Every bidder should price the same insulation build-up, attachment basis, metalwork allocation, penetration treatment, temporary protection and warranty obligation.

The useful test is not whether the scope says “complete watertight system.” It is whether the roofing, sheet metal, carpentry and MEP packages can each identify what they furnish, install and leave ready for the next trade.

This guide focuses on insulated low-slope membrane roofs on commercial buildings. Do not use the assembly checklist unchanged for standing-seam metal, shingles, protected membrane roofs or vegetated roofs. The package structure still works, but those systems need different inclusions. For the broader process, use the construction scope generation guide.

Establish the documents and the pricing basis first

Start the scope with a document register, not a blanket reference to “all plans and specifications.” Record the drawing issue, specification issue, addenda and roof areas covered. Include architectural roof plans, roof assembly schedules, sections, parapet and edge details, drainage plans, structural deck information, equipment schedules and relevant Division 01 requirements.

List the actual project specification sections. Common references include roof insulation, the selected membrane system, flashing and sheet metal, rough carpentry, roof accessories, air barriers and plumbing drainage. A section reference identifies requirements to read. It does not, by itself, assign the work to a subcontractor.

The public guide specifications illustrate why. UFGS 07 54 23, Thermoplastic-Polyolefin Roofing, August 2025, directs coordination with insulation, rough carpentry and sheet metal sections. UFGS 07 22 00, Roof and Deck Insulation, August 2023, separately addresses cover board, moisture-control layers, attachment and tapered components.

These are military guide specifications requiring project editing, not universal requirements for private commercial roofs. The editions cited here were checked on November 24, 2026. The sheet metal guide cited below is August 2023 with Change 1, May 2025. Use the requirements incorporated into your contract, including its applicable code basis, rather than importing these examples as new obligations. See the applicable-code scope review for that separate decision.

Before solicitation, settle four pricing inputs:

  • Which roof system and acceptable manufacturers form the base bid?
  • Which insulation, membrane attachment and fire/wind performance basis applies to each roof area?
  • Which trade carries each adjacent component?
  • Which unresolved design item needs a common written assumption or prebid clarification?

On a hard bid, obtain an authorized clarification through the solicitation process rather than privately substituting your preferred assembly. At an incomplete-design GMP, record the agreed pricing assumption and its unresolved design dependency. Neither approach should silently turn a bidder's standard roof into the project's specified roof.

Describe the assembly from the deck upward

Use a short assembly description for each distinct roof area. Give it an identifier tied to the drawings. If two roofs have different decks or attachment systems, give them different descriptions even when they use the same membrane.

The inclusions should identify:

  • Receiving substrate: deck type, examination and preparation included, and treatment of unacceptable conditions.
  • Layers below the insulation: specified vapor retarder, air-control layer, underlayment or thermal barrier, with seams and penetrations addressed at that layer.
  • Insulation: type, specified thermal basis, flat-board thickness and layers, taper layout, fill boards, crickets, saddles and drain sumps.
  • Cover board: type, thickness, attachment and extent. Do not let “insulation included” stand in for cover board.
  • Membrane: material, reinforcement, thickness, application method, seams, terminations and accessories.
  • Securement: insulation and membrane attachment, substrate-specific fasteners or adhesives, and applicable field, perimeter and corner requirements.
  • Details: base flashing, pipe boots, drain connections, expansion-joint treatment, termination bars and related sealants.
  • Service routes: permanent walkway pads or other specified protection, with locations and extent.

Do not write a new design inside the scope. Reference the designer's assembly and make the subcontractor's execution obligations explicit.

The insulation guide calls for shop drawings showing material thicknesses, tapered components, transitions, ridges, valleys, crickets and drainage interfaces. It also distinguishes the indicated thermal resistance from the insulation thickness calculation, including an optional average-thickness basis for tapered systems. That makes “R-value per plans” insufficient when the plans and specification leave different interpretations of the taper build-up. Resolve whether the contract uses a minimum or average thermal basis before asking everyone to price it. Source: UFGS 07 22 00, paragraphs 1.3 and 2.1.5.

Check the taper against the curb, not just the insulation price

Illustrative review, not a design recommendation or project result: assume a flat deck, a roof taper rising at 1/4 inch per foot over a 24-foot run, and 4 inches of insulation at the low point. The rise is 24 × 1/4 = 6 inches, making the insulation 10 inches thick at the high point. Add a 1/2-inch cover board. Ignoring membrane thickness solely for this example, the finished roof is 10.5 inches above the deck there.

A curb top at 16 inches above the deck leaves only 16 − 10.5 = 5.5 inches above the finished roof. If the illustrative project detail requires 8 inches of clearance, the curb is short by 2.5 inches. A scope that assigns “curbs by MEP” and “tapered insulation by roofing” can price both components accurately while pricing an interface that cannot meet the detail.

The TPO guide's optional prefabricated-curb provision measures curb height above the finished membrane, while the insulation guide requires tapered layouts and material thicknesses. Read together, those requirements suggest a better bid check: reconcile curb elevation, local taper thickness and flashing detail before releasing both packages. Sources: UFGS 07 54 23, paragraph 2.1.8.1, and UFGS 07 22 00, paragraph 1.3.

The estimator should not improvise a curb extension. Ask the design team to resolve the geometry, then assign the resulting curb or adapter work and flashing work in both packages. This is a quantity-to-scope decision, not an insulation allowance problem.

Assign the handoffs with verbs and completion conditions

“By others” should name an owner and the condition that owner must deliver. Use the following as a drafting schedule, edited to the project rather than treated as a standard trade split.

InterfaceRoofing package should stateCompanion package should state
Sheet metal edges and copingMembrane termination, compatible interface and warranty coordination; metal furnish/install if assignedMetal type, finish, cleats, joints, securement and installation if separately assigned
Equipment curbsFlashing, local insulation treatment and finished-height verificationFurnish, install, anchor and set curb or adapter to coordinated elevation
Blocking and nailersRequired receiving condition and inspection before coveringFurnish, install, anchor and set top elevation; identify concealed inspection hold point
Roof hatchesFlashing and surrounding roof assembly treatmentFurnish and install hatch/curb assembly and associated access work as assigned
Roof drainsSump/taper work, membrane connection and roofing-side test participationDrain body, piping, supports and drainage-side testing as assigned
Air barrier tie-inIdentify the roof control layer and assigned transition workIdentify wall control layer, transition termination and readiness for roof connection
WalkwaysPermanent pads with defined routes and extentTemporary construction access and protection if not assigned to roofing

For metalwork, separate membrane flashing from counterflashing, coping, fascia, gutters, downspouts, scuppers and conductor heads. Identify each item rather than issuing an exclusion for “all sheet metal.”

UFGS 07 60 00, Flashing and Sheet Metal, calls for roof-associated metal materials to be supplied or approved by the roof system manufacturer and to form part of the applicable roof warranty. The TPO guide's warranty provisions separately address flashing, insulation and accessories.

The estimating consequence is important: a separate metal subcontract does not necessarily create a separate warranty boundary. If your contract requires those metals within the roof warranty, both scopes need the same compatibility, submittal and acceptance obligations. Otherwise the GC may buy the right metal profile and the right membrane but still lack support for the promised warranty.

Competent estimators can reasonably choose different package splits. A combined roofing-and-metal package may be preferable where acceptance of the complete system is difficult to separate. A specialist metal package may be preferable for extensive custom coping or architectural metalwork. Let the project's fabrication demands and warranty requirements decide, not the section number. In either case, name who obtains manufacturer acceptance of the interface and who corrects rejected work.

For air barriers, identify the layer being connected. WBDG's Air Barrier Systems in Buildings explains continuity between roof and wall assemblies, compatible materials, installation sequence and sealing penetrations at the targeted air barrier layer. A membrane boot at roof level should not be used as evidence that a separate lower air-control layer has been sealed. Require the transition detail and assigned installer for each relevant plane.

For a broader boundary audit after the scope is drafted, use the roofing scope gaps review.

Price the installation sequence and acceptance work

A roofing package should define what the subcontractor must leave protected each day and what happens when another trade returns later.

The insulation guide requires each day's installed insulation to be covered with finished roofing the same day. The TPO guide separately addresses coordination of permanent flashings, water cutoffs, temporary flashing and protection of applied roofing. Those provisions describe an installation sequence, not merely a cleanup obligation. Sources: UFGS 07 22 00, paragraph 3.5.1, and UFGS 07 54 23, paragraphs 1.7 and 3.7.

Distinguish three obligations in the scope:

  1. Daily weatherproofing needed to execute the roofing work.
  2. An intentional temporary roof or temporary enclosure serving a longer project phase.
  3. Protection and authorized repair after following trades use the completed roof.

An exclusion for “temporary roofing” must not erase included daily cutoffs or temporary flashing. Conversely, daily weatherproofing should not silently become a temporary roof maintained for months. State the phase, duration or defined handoff condition, access arrangement and number of planned returns.

Show the price movement before issuing the package

Illustrative arithmetic using invented quantities and rates: a preliminary $300,000 roofing carry excludes separately assigned coping and assumes one uninterrupted mobilization. The coordinated package requires:

  • 800 linear feet of coping at an illustrative $42 per linear foot: $33,600.
  • A second planned roofing visit after equipment installation: $6,400.
  • Defined temporary protection during that handoff: $4,000.

The complete roofing-and-interface budget is $300,000 + $33,600 + $6,400 + $4,000 = $344,000. That is $44,000 above the preliminary carry, without changing the roof area.

If coping remains in the metal package, keep its $33,600 there and carry $310,400 in roofing. If coping moves into roofing, transfer the amount rather than adding it twice. The lesson is not the rate: assigning metal and sequencing separately changes where the money sits, while the total obligation remains.

Acceptance work needs the same treatment. State required submittals, pre-roofing conference participation, inspections, testing, deficiency correction and closeout. The TPO guide includes wind-load/attachment shop drawings, a sample warranty, manufacturer's inspections and a roof drain test. Its requirements concern the complete assembly, not membrane material alone. Source: UFGS 07 54 23, paragraphs 1.3, 1.4.4, 1.8 and 3.8.

For your project, name who supplies calculations if required, who obtains approvals, who schedules testing and who provides access or attendance. Do not replace the specified uplift basis with a wind-speed shorthand or an undefined “standard warranty.”

Use a reusable scope outline without hiding unresolved choices

Use these headings as the bid scope and preserve the agreed allocations through buyout. The bid scope sheet versus subcontract exhibit guide addresses that handoff.

General and document basis

Record roof areas, document issues, addenda, applicable sections, bid form, performance basis and project-specific access/phasing requirements. Identify open design clarifications separately from established requirements.

Inclusions

List assemblies by roof identifier. Include layers, thickness/thermal basis, taper, attachment, flashings, drainage interfaces, expansion joints, walkway pads, assigned metalwork and accessories. Add delivery, hoisting, substrate review, weatherproofing, planned returns, inspection participation and closeout obligations.

Exclusions

Limit exclusions to specifically allocated work. For each exclusion, cross-reference its named owner. Review sheet metal, curbs, nailers, warranty upgrades, testing and temporary roofing against the actual contract before accepting them. An exclusion is not authority to delete required project work.

Work by others and receiving conditions

For every handoff, identify furnish, install, anchor, flash, seal and test responsibilities. State the receiving elevation, substrate readiness and relevant inspection condition. Require matching language in the companion scope.

Clarifications and bidder response

Ask bidders to identify the proposed manufacturer/system, warranty basis, insulation build-up, sheet metal inclusion, attachment basis and exceptions. Request departures as a separate list rather than letting them disappear into proposal boilerplate. Resolve material differences before selection; do not treat silence as confirmation.

Alternates

Define a complete alternate assembly and its affected interfaces. A warranty upgrade alternate should identify the warranty form and any associated assembly or acceptance changes, not just a longer term. Keep the compliant base bid visible and separate from voluntary substitutions.

Unit prices

Use unit prices for bounded variable work, especially on reroofing. Define the material, thickness, layer count, removal/disposal, replacement, attachment, measurement basis and authorization process. “Wet insulation replacement per square foot” is incomplete unless bidders know which build-up the unit price replaces.

Final issue check

Trace each roof identifier from assembly to detail, companion package and acceptance obligation. Then ask whether any clarification changes the priced base, an alternate, a unit price or a by-others allocation. Issue the revised scope consistently to affected bidders. For wording problems beyond this outline, see roofing scope writing mistakes.

Keep the roof assembly and its evidence connected

The maintainable record is not a longer roofing checklist. It is a connected set of assembly definitions, interface assignments, source details and decisions that can be revisited when a curb, taper layout or warranty requirement changes.

Piper's Scope Generation workflow organizes drawings, specifications, addenda and company requirements into trade-specific scopes with source references. It surfaces unclear responsibilities and potential gaps or overlaps for estimator review, and affected scope can be surfaced when upstream information changes. Those capabilities support the record described here; they do not choose the roof design or settle a disputed trade boundary. The team reviews the generated scope and decides the commitment.

FAQ

What should a roofing scope of work include?

Include the document basis, each roof assembly, assigned interfaces, installation conditions and acceptance work, followed by exclusions, by-others allocations, clarifications, alternates and unit prices. For low-slope membrane roofing, spell out insulation, cover board, attachment, flashing, drainage connections, metalwork, protection and warranty obligations rather than relying on the membrane section alone.

Should sheet metal be included in the roofing subcontract?

Include it when that package split serves the project's fabrication and acceptance requirements; otherwise assign it explicitly to a separate package. Either way, connect metal compatibility, interface details and warranty acceptance to the roofing scope. Separating purchasing responsibility should not leave the complete roof-system obligation unresolved.

Who should furnish equipment curbs?

Assign curb furnishing and installation to a named package based on the equipment and project details, then assign roof flashing separately. Before solicitation, check curb height against the local finished roof elevation, including taper and cover board. A curb dimension above the deck does not establish clearance above the finished roof.

Can a roofer exclude temporary roofing?

Accept that exclusion only after defining which temporary work it covers. Separate an intentional temporary roof from daily cutoffs, temporary flashing and protection required for the permanent installation. State planned return visits and following-trade protection so the exclusion does not remove required weatherproofing or conceal a longer maintenance obligation.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.