How to write a specialties scope of work bidders can price consistently
Write a specialties bid scope that reconciles partitions, accessories and signage by location, assigns furnish and install duties, and defines pricing options.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 11 min
- Published
On this page
- Establish the document basis and package limits
- Build three registers that force a comparable price
- Write partitions as assemblies, including accessory interfaces
- Define accessories through the installed condition
- Separate sign fabrication from sign-program design
- Add cabinets only with their wall and equipment basis
- Carry one illustrative package through the pricing instructions
- Reusable specialties bid-scope outline
- Keep location, source and responsibility connected through revisions
For a GC estimator issuing a commercial school, office or tenant-improvement bid package at the construction-document stage, the specialties scope should be a location-based responsibility schedule with written execution requirements. Every partition assembly, accessory and sign needs an identified location, product basis, furnish/install assignment and pricing treatment. “Include Division 10 complete” is not an adequate substitute.
The position here is deliberate: write the room and sign registers before writing the blanket inclusions. That makes bidders price the same assemblies and services, rather than three different interpretations of a specification division.
This guide covers toilet partitions, toilet accessories and architectural signage, with fire extinguisher cabinets where assigned to the package. It is not a universal Division 10 subcontract. For an early GMP with unresolved selections, use explicit pricing assumptions or allowances rather than presenting this outline as a final design. The broader construction scope-generation process explains that maturity distinction.
Establish the document basis and package limits
Start the scope with the project name, package identifier, work areas, bid issue and drawing/specification revision basis. List every included addendum and formally issued clarification. Identify excluded phases or floors by name.
Then identify the actual project sections. As reference examples, UFGS uses 10 21 13, Toilet Compartments, and 10 28 13, Toilet Accessories. Its 10 44 16, Fire Extinguishers, also includes cabinet provisions. These are federal guide specifications, not automatic requirements for a commercial project. The currently posted compartment and accessory sections carry August 2020 section dates; the extinguisher section carries November 2019. All three fetched versions identify an October 2026 reference update. Use the edited sections incorporated into your contract, not an unedited guide with bracketed choices still in it. Sources: compartments, accessories, extinguishers and cabinets.
For signage, copy the project's section number and title rather than assuming every sign belongs to one architectural package. List room identification, wayfinding, exterior identification and illuminated signs separately. State whether electrical exit signs and equipment labels belong elsewhere.
The source appendix should identify:
- Toilet-room plans, enlarged plans and interior elevations.
- Partition details, accessory schedules and product legends.
- Room finish and wall-type schedules, including rated-wall locations.
- Sign schedules, location plans, message lists and graphic standards.
- Structural or framing support details relevant to mounted specialties.
- Electrical sheets for powered accessories and illuminated signage.
- Owner equipment lists, landlord criteria and furnishing assignments.
- Relevant Division 01 requirements for submittals, access, protection and closeout.
This is a recommended review set, not a new contract hierarchy. Do not silently decide that a schedule overrides an elevation. Record the conflict and obtain the project's authorized resolution, or issue a common bid assumption through the permitted process.
On a fit-out, establish landlord and tenant responsibilities before assigning signage or owner accessories; the tenant-improvement scope review addresses that separate decision.
Build three registers that force a comparable price
Use a partition assembly register, an accessory location register and a sign register. Give each record a stable identifier so a bidder can take an exception to a specific line.
For partitions, a record should define the room, number and type of compartments, layout reference, material, mounting system, panel height, privacy treatment, door hardware, urinal screens and required support. A stall count alone does not establish those assemblies.
For accessories, record tag, description, product basis, room, quantity, mounting type, backing reference and furnishing/installation duties. UFGS 10 28 13 expressly calls for a product schedule showing types, quantities, sizes and installation locations by room, plus anchoring and mounting information. That supports a useful bid instruction: require the bidder to return the same location schedule with exceptions marked, rather than only a lump sum. Source: UFGS 10 28 13, submittals.
For signs, add message, sign type, dimensions, material, graphic treatment, tactile/visual classification, mounting method and approval responsibility. Separate “final message pending” from “sign type not designed.” The first can be a controlled content decision; the second leaves the fabrication basis unresolved.
A recommended responsibility format is:
| Scope record | Specialties duty | Named handoff to another party |
|---|---|---|
| Partition assembly P-01 | Furnish, install, anchor, adjust and clean the specified assembly | Framing or metals provides identified building support; specialties submits attachment requirements |
| Accessory A-01, contractor-furnished | Furnish mounting hardware and accessory; install at approved location | Framing provides backing shown in coordinated detail |
| Accessory A-02, owner-furnished | Receive, inspect, store and install; identify missing mounting components | Owner supplies approved model and delivery information; electrical provides any assigned connection |
| Sign S-01, permanent room identification | Prepare fabrication submittal, furnish and install approved sign | Design team or owner approves message and graphic basis |
| Cabinet C-01 in rated wall | Furnish and install specified compatible cabinet and trim | Framing provides opening; assigned trade completes approved wall restoration |
These are proposed assignments, not universal trade customs. Replace the party descriptions with your actual packages and mirror each handoff in the receiving scope.
Write partitions as assemblies, including accessory interfaces
Spell out furnishing and installation of panels, doors, pilasters, brackets, shoes, headrails where applicable, anchors, latches, pulls, hinges, stops and specified hooks. Identify room entrance screens and urinal screens independently. Include field measurement, fabrication/installation submittals, adjustment, cleaning and protection under the project's requirements.
UFGS 10 21 13 describes a complete partition system with panels, hardware and support components. It also directs coordination of separately specified accessories with partition cutouts and reinforcement, and of ceiling-hung partitions with supporting members. Source: UFGS 10 21 13.
The important interaction is not simply “blocking by others.” An accessory mounted on a partition can change the partition fabrication itself. Wall backing assigned to framing does not resolve reinforcement inside a manufactured panel. Require accessory mounting requirements to be incorporated into the partition submittal before fabrication release.
Recommended scope language:
Furnish and install partition assemblies identified in the partition register, including specified hardware, anchors and partition-integral reinforcement or cutouts for scheduled accessories. Submit coordinated accessory mounting locations with the partition fabrication drawings. Building-wall backing and overhead building supports are assigned in the responsibility schedule and are not included solely by reference to partition-integral reinforcement.
Also reconcile partition geometry with plumbing. Under the 2010 ADA Standards, adult wheelchair-accessible compartments have a minimum depth of 56 inches with wall-hung water closets and 59 inches with floor-mounted water closets; minimum width is 60 inches. Door and toe-clearance provisions also apply. Source: Access Board, section 604.8.1.
That creates a pre-fabrication check: compare the partition layout with the current plumbing fixture selection and finished dimensions, not only the architectural stall label. If a nominally 56-inch-deep layout remains after a change to a floor-mounted fixture, obtain design resolution before releasing the partition assembly. Do not tell the specialties bidder to redesign the room through a blanket compliance clause.
The Department of Justice's 2010 ADA Standards establish federal scoping and technical requirements for covered facilities. Confirm project applicability and the adopted local requirements separately; the dimensions above are not a complete accessibility review.
Define accessories through the installed condition
Identify grab bars by configuration and length, mirrors by size and mounting, dispensers by exact product basis, and changing stations by mounting and approved location. Include scheduled shelves, hooks, sanitary disposal units and other accessories instead of assuming that “toilet accessories” communicates a uniform set.
For owner-furnished, contractor-installed items, write out the duties hidden inside OFCI:
- Who receives and records delivery condition?
- Who supplies mounting plates, fasteners, keys and adapters?
- Who stores and protects the units?
- Who provides backing and rough openings?
- Who installs, connects where applicable, adjusts and demonstrates operation?
- What is the pricing treatment if the approved model or delivery sequence changes?
Do not exclude “owner-furnished items” if installation is in your package. Exclude their purchase cost, then positively include the assigned handling and installation work.
Backing deserves a defined handoff. ADA section 609.8 addresses the grab bar, fastener, mounting device and supporting structure under a 250-pound applied force without exceeding allowable stresses. UFGS 10 28 13 separately calls for anchors suited to the supporting construction. Read together, those provisions mean that a compliant product description alone does not establish a supported installed assembly. Sources: ADA section 609.8 and UFGS accessory anchors.
The GC's bid-stage decision is to assign both sides: specialties provides mounting and anchor requirements before wall closure; framing provides the specified backing; the GC coordinates confirmation that the two match. Any engineered support obligation must be expressly assigned, not implied by this checklist.
Separate sign fabrication from sign-program design
“Provide ADA signage” leaves both the count and design responsibility unclear. The 2010 ADA Standards distinguish permanent room/space designations from directional and informational signs. Section 216 establishes which provisions apply; section 703 addresses raised characters, braille, visual characters and installation. Not every sign needs the same treatment. Sources: section 216 and section 703.
Require a sign-by-sign classification approved by the responsible design party. For tactile signs, the installation check must include the door condition and available wall space, not merely an elevation note: section 703.4 specifies character-baseline heights, door-side locations and clear floor space. Source: section 703.4.
This is where competent estimators may choose different procurement strategies. If the sign program is designed, buy fabrication submittals, manufacture and installation against that program. If wayfinding strategy or graphics remain undeveloped, obtain a separately defined design service or establish a common allowance and deliverable. Do not compare a fabricator's price against a price that includes developing the entire sign program.
For illuminated signage, assign sign equipment, internal components, support, power provision and final connection expressly. “Electrical by others” should identify the receiving package and the connection boundary, not leave the sign vendor and electrical bidder to discover it after award.
Add cabinets only with their wall and equipment basis
If fire extinguisher cabinets are included, list cabinet tags, mounting type, finish, dimensions, wall type and whether the extinguisher itself is furnished and installed by this package. UFGS 10 44 16 calls for coordinating extinguisher and cabinet schedules for fit and function and offers a listed/labeled fire-rated cabinet provision. Source: UFGS 10 44 16, paragraphs 1.5 and 2.2.1.
The recommended check joins three records: cabinet schedule, wall-type plan and extinguisher selection. A correct total cabinet count is not a purchasing basis if it combines different wall conditions into one generic unit. Require the project-approved cabinet/wall detail and assign rough opening, installation, trim and restoration separately. Do not substitute a different mounting type without authorized review.
Carry one illustrative package through the pricing instructions
Illustrative example only. All quantities, rates and prices below are invented to demonstrate scope writing, not market benchmarks. Assume an office fit-out with two multiuser toilet rooms. The draft scope lists 24 purchased accessories and 12 owner-furnished dispensers but says nothing about dispenser installation. A cabinet total of four also combines two standard units and two units requiring the project's approved rated-wall cabinet detail.
Before issue, write a common pricing basis:
- Purchased accessories: 24 units at an illustrative $140 furnished and installed = $3,360.
- OFCI dispensers: 12 units at an illustrative $45 for defined handling and installation = $540, with no dispenser purchase cost.
- Standard cabinets: two at an illustrative $260 furnished and installed = $520.
- Rated-wall cabinet assemblies: two at an illustrative $460 furnished and installed = $920; assigned wall restoration remains in the separate framing/finish package.
The corrected accessory/cabinet subtotal is $5,340. The incomplete basis would have been $3,360 + four cabinets at $260 = $4,400. The $940 movement consists of $540 in omitted OFCI service and $400 in cabinet-type differentiation. Neither change came from increasing the item count.
Partitions and signs would remain separately priced in this example. If the owner requests a partition-material alternate, ask for the net change for the complete affected assemblies, including changed hardware, reinforcement and installation. Do not request a panel-material delta that leaves the rest of the assembly on an unidentified basis.
Reusable specialties bid-scope outline
Use the following as an authoring outline. Fill every assignment and reference before issue; it is not a ready-made legal exhibit.
General and document basis
State package limits, current source register, addenda, access/phasing requirements and the required bid breakdown. Identify the project-approved accessibility basis and the party responsible for resolving design conflicts.
Inclusions
Attach the three registers. Include defined furnishing, installation, delivery, storage, field verification, submittals, samples, hardware, anchoring, adjustment, protection, cleaning and closeout. Add cabinets only if expressly assigned. Identify required mobilizations and turnover areas.
Exclusions
List excluded work by function, not vague product category: building-wall backing, sign-program design, specified purchase costs of OFCI items, electrical supply/connections or finish restoration, as applicable. An exclusion should not contradict an inclusion elsewhere.
By others
Name the receiving package or owner duty for each exclusion. Record the input specialties must supply, the required handoff milestone and the party coordinating acceptance. Confirm that the other scope contains the matching obligation.
Clarifications and unresolved selections
Require bidders to identify exceptions by register line. State common assumptions for unresolved product or message selections, subject to the project's authorized process. Distinguish fabrication detailing from delegated design and owner content approval.
Alternates and allowances
Identify affected locations and the base assembly being replaced. Require net additions or deductions covering the full change. Define any allowance's quantity, quality basis, included labor/services and reconciliation treatment.
Unit prices
Request additions and deletions separately by accessory model, sign type or partition configuration where useful. State whether unit prices include installation, handling, mounting hardware and additional mobilization. Avoid one “each sign” rate for unlike sign types.
Bid return and award reconciliation
Require base price by partitions, accessories, signage and cabinets; OFCI services separately visible; alternates; allowances; unit prices; lead-time assumptions; addenda acknowledgment; and line-specific exceptions. Reconcile accepted clarifications into the award scope rather than attaching a contradictory proposal behind an unchanged scope sheet.
For the next review, use the specialties scope-gap guide to test uncovered interfaces and the specialties scope-writing mistakes guide to challenge ambiguous language.
Keep location, source and responsibility connected through revisions
The maintained record should connect each location to its current detail, product basis, furnishing duty, installation duty and accepted clarification. A changed dispenser selection should reopen its mounting and support review; a revised room designation should reopen its sign message, not unrelated partition quantities.
Piper's Scope Generation organizes drawings, specifications, addenda and company requirements into trade-specific scopes with source references. It can surface unclear boundaries and affected scope when upstream information changes. The useful application here is keeping the location registers and written scope grounded in one evolving project understanding. The team still approves trade assignments, design clarifications and the scope issued to bidders.
FAQ
Should specialties include every item in Division 10?
No. Define the actual package through included sections, locations and duties. Toilet partitions, accessories, signage and cabinets may be procured together or separately. The scope must positively identify its work and name the receiving party for excluded functions instead of relying on the division title.
How should owner-furnished accessories appear in the bid scope?
Exclude their purchase cost only when the owner supplies them, then state the contractor's handling and installation duties. Identify model, quantity, location, mounting components, backing and delivery assumptions. OFCI is a responsibility split, not a reason to remove the item from the location register.
Who should provide blocking for toilet accessories?
Assign building-wall backing to the chosen framing or carpentry package and mounting requirements to the accessory installer, unless the project uses another explicit arrangement. Partition-integral reinforcement is a separate obligation. Coordinate the approved mounting details before wall closure or partition fabrication, rather than writing only “blocking by others.”
Is “ADA signage included” enough to obtain comparable prices?
No. Issue a sign register with location, message basis, type, dimensions, tactile/visual classification and installation requirements. State who approves content and whether sign-program design is included. Bidders can price fabrication consistently only when they share the same sign and service basis.
Related reading
Construction scope generation: a practical guide for GCs
How general contractors turn drawings, specifications, addenda, and company standards into trade scopes a subcontractor can price, an estimator can trace, and a senior reviewer can challenge.

Tenant improvement allowances: separate the lease budget from the contractor’s scope
A tenant improvement allowance is not a complete construction scope. Review separating funding, landlord work, tenant work, interfaces and pricing decisions.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow