How to write a structural steel scope of work subs will price the same way

Define steel fabrication, connection design, erection and trade handoffs in one bid scope, with a reusable outline and a worked package-cost comparison.

Guide11 min read

Published

Tower crane above steel reinforcement

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Establish the document basis before listing steel
  2. Separate detailing from connection design
  3. Write inclusions around operations and deliverables
  4. Frame materials and fabrication
  5. Erection and temporary works
  6. Inspection support and completion
  7. Assign both sides of each trade handoff
  8. Define the coating condition, not just the coating trade
  9. Test the written scope with a package-cost example
  10. Reusable structural steel bid-scope outline
  11. General and controlling basis
  12. Inclusions
  13. Exclusions and work by others
  14. Clarifications, alternates and unit prices
  15. Keep the steel scope connected as the project changes

For a GC estimator buying the frame on a ground-up commercial building, a comparable structural steel bid requires more than “furnish and erect per plans.” Write the package as a chain: design inputs, detailing, fabrication, delivery, erection, inspection support and release to following trades. Assign the handoff at each step.

The strongest scope is not the one with the longest inclusion list. It is the one that lets every bidder price the same connection responsibility, crane arrangement, embedded-item handoff and coating condition.

This guide assumes a conventional building frame, with joists, deck and miscellaneous metals potentially bought separately. It is not a bridge specification or a substitute for the structural engineer's design. On an incomplete CMAR package, first identify what is sufficiently defined to buy and what remains an agreed pricing assumption. Do not turn an unresolved design choice into a subcontractor obligation by adding “complete.”

Establish the document basis before listing steel

Create a scope cover sheet that identifies the drawing and specification register, revision dates, addenda, pricing deadline and scope-sheet revision. Include structural general notes, foundation and framing plans, sections, connection details and schedules. Add architectural exposed-steel requirements and referenced roof, facade or equipment-support details where they affect this package.

Use actual project section titles and numbers. Start with the structural steel section, commonly 05 12 00, then identify the project's joist, decking, metal fabrication, coating, fireproofing and concrete sections. Include applicable Division 01 submittal, quality, logistics and sequencing provisions. A section reference identifies requirements to review; it does not, by itself, assign every operation in that section to the steel subcontractor.

The current public UFGS 05 12 00 guide specification illustrates why drawings and specifications must be read together. Its drawing-preparation notes call for connection types and loads, nondestructive-testing locations, and coating limits. Its text separately addresses fabrication drawings, delegated connection design, erection bracing and field quality control. This is a military guide specification to be edited for a project, not a requirement automatically imposed on private commercial work. The file checked for this guide is dated August 2018, Change 2 May 2021, with references aligned to October 2026.

Also record the contract's incorporated standards and editions. AISC's current standards page identifies ANSI/AISC 303-22 and explains that its customary practices apply unless the contract documents contain specific provisions to the contrary. Make any intended departure visible rather than relying on an unrelated boilerplate clause to change the steel bidder's basis.

Use a two-part document test: Does the register tell the bidder which information controls, and does the scope tell the bidder which work that information assigns to this package? A complete document list answers only the first question.

For the general process, use the construction scope generation guide; the decisions below are specific to the steel package.

Separate detailing from connection design

Do not use “engineering and detailing included” as a catch-all. Assign connection responsibility by family: simple shear, moment, brace, splice, base and any special connections. Identify the controlling drawing or note for each family.

AISC's 2025 connection-responsibility guidance, explaining Section 3.2.3 of ANSI/AISC 303-22, distinguishes three options:

Connection basisRequired information and responsibilityScope-writing instruction
Option 1Complete connection design shown in structural design documentsInclude detailing and execution of that design; identify unresolved details for clarification
Option 2Experienced detailer selects or completes connections using provided reference informationIdentify permitted references, design criteria and required substantiation
Option 3Licensed engineer working for the fabricator designs designated connectionsInclude the assigned connection engineering, substantiating information and review obligations

The options can differ within one frame. Option 3 does not remove the structural engineer of record's review, and Option 2 is not intended for work requiring the practice of engineering. AISC also requires design criteria for Options 2 and 3, including loads, restrictions and the applicable design method.

Translate those distinctions into deliverables. Request fabrication and erection drawings, connection information, required calculations and seals, and the planned review sequence. Identify representative connection submissions before full detailing where required. Do not invent a blanket requirement to seal every drawing sheet: carry the actual project requirement and applicable professional requirements.

The decision-changing interaction is between delegation and design readiness. A note assigning connection engineering does not supply the forces needed to perform it. If the framing drawings show member sizes but omit required connection criteria, asking all bidders to “include connection design” can still produce different fabrication allowances.

For an incomplete package, request a common written pricing basis from the design team. Record the connection families covered, assumptions permitted and items awaiting resolution. Keep detailing, connection engineering and unresolved connection material allowances distinct. Use the guide to estimating design intent on incomplete drawings for the broader pricing-stage decision.

Write inclusions around operations and deliverables

Organize the inclusion section into the following work blocks. Use affirmative verbs and source references rather than copying an entire specification into the scope sheet.

Frame materials and fabrication

Define the frame limits by building area, grid, level and detail references. Identify columns, beams, HSS members, braces, trusses or built-up members where applicable. Include the specified connection plates, stiffeners, gussets, base plates, bolts, nuts, washers and welding associated with assigned work.

Then state the supporting deliverables: material identification and certificates, fabrication drawings, required qualifications, shop work, delivery marks and sequencing. Identify camber, special surface appearance, galvanizing and other project-specific fabrication conditions by location rather than treating them as universal requirements.

For attachments serving another package, identify the actual item. “Miscellaneous steel excluded” should not accidentally remove a connection plate shown as part of the structural frame. Conversely, “all steel shown” should not quietly buy stairs, railings and ladders intended for a separate metal-fabrication package.

Erection and temporary works

State whether the price includes unloading, sorting, staging, erection equipment, cranes, rigging, hoisting labor, field connections, temporary erection bracing, plumbing and alignment, and removal of temporary work. Identify the required erection and bracing submissions without prescribing an unreviewed erection method.

The UFGS guide's Sections 1.5.1 and 1.5.2 address erection sequence, temporary shoring and bracing, and fabrication information. Use that as a prompt to inspect the project requirements, not to impose every bracketed guide provision.

Define the assumed work areas, delivery restrictions and erection phases in a logistics attachment. “Crane included” must have a site basis: where equipment can stand, what access is available and how often it must move.

Inspection support and completion

Distinguish contractor quality control from separately procured special inspection or owner quality assurance. Identify who orders and pays for each inspection service, who provides access and notice, which records are required, and how correction and reinspection are treated under the contract.

Do not let “special inspections by owner” erase the steel contractor's own specified quality-control obligations. UFGS 05 12 00, for example, includes contractor field tests, certified welding inspection and reports. The project's adopted text, inspection schedule and contract allocation must be reconciled before using a blanket exclusion.

Define the closeout condition: completed connections, required records, resolved nonconforming work, coating repairs and the agreed release of temporary work. Avoid a finish line described only as “steel erected.”

Assign both sides of each trade handoff

Use a boundary schedule with separate columns for furnishing, installation, prerequisite and acceptance evidence. The point is not to list every possible miss. For a diagnostic review after drafting, use the structural steel scope gaps guide.

For this package, settle these boundaries explicitly:

  • Joists and deck: Name the furnishing and erection packages separately. Assign bridging, perimeter and opening supports, deck attachments and shear studs where applicable. If another erector uses the same crane, define that service rather than assuming it follows material ownership.
  • Miscellaneous metals: Identify included structural attachments and excluded stairs, railings, ladders or other fabrications by item and location.
  • Embedded items: Assign anchor rods, templates, embedded plates and accessories for furnishing, delivery, setting and survey separately.
  • Grout: Assign material supply, preparation, forming, placement and the release condition for the base. Distinguish temporary erection support from final grout work.
  • Coatings and fireproofing: Define shop preparation, primer, omitted-primer areas, field repairs, finish paint and fireproofing application separately.

The anchor-rod handoff deserves a release record, not just a trade name. AISC's 2025 embedded-item guidance, explaining Section 7.5 of AISC 303-22, assigns setting and the as-built survey to the owner's designated representative for construction under the standard practice. Corrective action requires design guidance and approval. Translate that responsibility into the actual concrete and survey package assignments.

For US work subject to the cited federal OSHA provisions, 29 CFR 1926.752 also requires the controlling contractor to provide written notifications before authorizing erection and to ensure maintained access and a firm, graded, drained operating and storage area. 29 CFR 1926.755 prohibits anchor-rod repair, replacement or field modification without the structural engineer of record's approval and requires notification of changes before column erection. Check the applicable state-plan requirements as well.

Combined scope rule: release erection only after the embedded-item survey and discrepancy disposition are complete, the required written notifications are provided, and the agreed operating area is ready. This combines dimensional readiness, authorization and logistics. Buying an erection crane does not buy those prerequisites or shift the controlling contractor's regulatory duties.

Define the coating condition, not just the coating trade

A workable coating boundary describes what the next trade receives. For each member group or area, record substrate preparation, shop coating or deliberately uncoated condition, repair responsibility and finish treatment.

This matters even when the fireproofing subcontractor owns application. UFGS 05 12 00 Section 2.6.3 links preparation for sprayed fireproofing to manufacturer recommendations and Section 07 81 00. Sections 3.5 and 3.5.1 separately address shop-primer repair and field priming. Those linked provisions demonstrate why “painting excluded” is insufficient as a scope instruction.

For the project package, distinguish repair of the assigned steel coating from final architectural painting and preparation for fireproofing. Confirm compatibility with the specified assembly through the design and submittal process. Do not select a different primer solely to simplify buyout.

Failure analysis: if the steel scope promises a generally primed frame while the fireproofing scope assumes a different substrate condition, each bid can look complete on its own. The cost appears later as preparation or coating correction, not necessarily as missing steel tonnage. The prebid check is a member-area coating schedule reviewed against both sections, with one accepted receiving condition.

Test the written scope with a package-cost example

The following figures are illustrative, not market rates, customer results or a benchmark. Assume the issued base scope requires assigned Option 3 connection engineering, erection hoisting, 40 base locations grouted, and field repair of the specified primer. Independent special inspection remains outside both steel bids.

Bid A is $860,000 and includes all four operations. Bid B is $805,000 but excludes them. Obtain separate illustrative coverage prices for B's omissions:

Required operationBid A treatmentBid B coverage to add
Connection engineeringIncluded$18,000
Erection crane and hoistingIncluded$36,000
Grout at 40 basesIncluded40 × $250 = $10,000
Specified primer repairIncluded$8,000

Bid B's package position becomes $805,000 + $18,000 + $36,000 + $10,000 + $8,000 = $877,000. Its apparent $55,000 advantage becomes a $17,000 disadvantage against A's $860,000.

That arithmetic is only a coverage test. Before accepting it, confirm that the separate crane service includes mobilization, operator, rigging responsibilities and the same erection phases. Confirm that the grout price includes the same preparation and placement scope. Do not add a generic crane rental to a price that also excludes hoisting labor.

Now make the judgment call explicit. A GC may prefer separate grout placement because the concrete package controls that work, or prefer a combined steel package with fewer commercial handoffs. Either can work. Choose based on site sequencing, accountable ownership and the receiving condition, then request every bidder's base price on that same allocation.

If the GC moves the four operations outside both steel contracts, request corresponding deducts from A. Do not compare A's inclusive number against B's exclusive number merely because the GC plans to buy the omissions later.

The useful output of this exercise is a revised scope, not just a leveled spreadsheet. Resolve the ambiguity for every bidder before treating the prices as a common basis.

Reusable structural steel bid-scope outline

Use this outline as a drafting artifact. Replace bracketed fields with project information; delete inapplicable work rather than leaving choices unresolved.

General and controlling basis

  • Package: [building, areas, grids and levels].
  • Documents: [drawing/specification register, revisions, addenda and scope revision].
  • Standards: [contract-incorporated editions and explicit modifications].
  • Pricing stage: [defined work and agreed incomplete-design basis].
  • Schedule basis: [required submissions, releases, deliveries and erection phases].

Inclusions

  • Detail, fabricate, deliver and erect [identified frame and attachments].
  • Include [connection materials, shop and field connections].
  • Provide connection services by [family, option, design criteria and source].
  • Submit [fabrication drawings, erection/bracing documents, calculations and records].
  • Include [unloading, crane/hoisting services, staging and temporary works].
  • Furnish [anchor rods, templates and embeds] for delivery by [agreed requirement].
  • Provide [specified coating condition, repairs and finish limits].
  • Provide [contractor quality control, inspection support and closeout records].

Exclusions and work by others

Pair every exclusion with a receiving package and retained interface obligation:

  • [Deck/joists]: furnished by [package], erected by [package], with [attachments/supports] assigned to [package].
  • [Embeds]: furnished by [package], set by [package], surveyed by [package].
  • [Grout]: supplied and placed by [package], after [release condition].
  • [Fireproofing/finish paint]: by [package], receiving steel in [agreed condition].
  • [Special inspection]: procured by [party], with steel-contractor support defined as [work].
  • [Access and operating area]: provided and maintained by [party] to [agreed logistics basis].

An exclusion is not closure until the companion package accepts it.

Clarifications, alternates and unit prices

Record open design questions separately from permitted pricing assumptions. Require proposed deviations and exclusions to be itemized against the scope revision. Give all bidders the same written clarifications.

For an alternate, define the complete changed assembly and its effect on detailing, connections, coatings, delivery and erection. Request an add or deduct to the stated base, not a second unexplained total.

For unit prices, define the work unit and included operations. State whether a steel-weight adjustment covers material only or also detailing, fabrication, coating, freight and erection. Keep remobilization and materially different connection work separate where the agreed unit cannot represent them. A dollar-per-ton figure without those limits is not a complete change-pricing mechanism.

Before issue, have the estimator, superintendent and package buyer test one connection submission, one embedded-item release and one coating handoff against the outline. Each should be able to name the responsible party, prerequisite and acceptance evidence without filling the blank from memory.

At award, reconcile accepted clarifications into the same scope basis; use the bid scope sheet versus subcontract exhibit guide for that handoff rather than rebuilding the steel obligations from a different template.

Keep the steel scope connected as the project changes

The scope should remain attached to the information that established it: connection criteria, embed drawings, coating limits, logistics and clarification decisions. When those inputs change, the affected obligations need another review rather than a wholesale copy of the previous package.

Piper's Scope Generation workflow organizes drawings, specifications, addenda and company knowledge into trade-specific scopes with source references. It surfaces uncertain boundaries and affected scope for review using an evolving understanding of the project. The team still decides connection responsibility, package ownership and the scope issued to bidders.

The practical target is a steel scope whose commitments can be traced and updated, not merely a document that looks complete on solicitation day.

FAQ

Should joists and metal deck be included in the structural steel scope?

Include them only when that is the chosen package arrangement, and separate furnishing from erection responsibilities. Define associated attachments, supports and shared hoisting services explicitly. A combined contract and separate contracts can both work; bidders need one common allocation rather than an assumption that all Division 05 work travels together.

Does including detailing also include connection engineering?

Do not treat the two as interchangeable. Identify the connection option by family and the required design inputs, substantiating information and review obligations. Under AISC 303-22, complete engineer-designed connections, detailer-selected connections and delegated engineer-designed connections have different responsibilities even though all require approval documents.

Can the steel scope exclude cranes and special inspections?

Yes, if the contract arrangement assigns those services elsewhere and retains the steel contractor's applicable obligations. Define hoisting labor, equipment, access and inspection support separately. A commercial crane exclusion does not remove controlling-contractor site-readiness duties, and a special-inspection exclusion does not automatically exclude specified contractor quality control.

What should a structural steel unit price include?

It should include exactly the operations stated in the pricing schedule, with a defined measurement basis. Identify whether material, detailing, fabrication, coating, delivery and erection are covered. Establish limits for different connection work and remobilization instead of expecting one weight-based rate to represent every possible change.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.