Texas coastal windstorm requirements and roofing and openings takeoff
Texas coastal takeoff needs more than roof area and opening counts. Use the current TDI basis to separate underlayment, anchorage and assembly quantities.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 10 min
- Published
On this page
- Establish the address and edition before assigning quantities
- Underlayment alternatives change what you measure
- Worked example: “two layers” is not simply twice the deck area
- The joint-sealing route needs a quantity the roof outline cannot supply
- A listed window can still be the wrong assembly
- Count mulled assemblies without losing the internal connections
- Separate pressure resistance from debris protection
- Make certification visible in trade coverage
- Keep coastal assembly quantities reviewable in Piper
For a GC estimator pricing roofing and exterior openings in Texas's designated catastrophe areas, the windstorm basis belongs in the takeoff before the trade quote arrives. Do not carry one roof-area quantity and one window count against a generic coastal premium. Separate the selected underlayment method, opening assemblies, attachment substrate and project-specific performance requirements.
The local distinction is concrete. Under 28 TAC §5.4013(a), structures constructed, repaired or added to on and after April 1, 2026, in the designated areas must comply with the adopted 2024 IRC and IBC to be eligible for catastrophe property insurance. That changes the estimating basis, not merely the paperwork.
This guide addresses the TDI windstorm certification path for projects seeking TWIA eligibility. It is not a statewide roofing rule, a wind-load calculation procedure or a substitute for the project's designer and inspector. The worked quantities below are illustrative, not engineered fastening schedules.
Establish the address and edition before assigning quantities
Start the takeoff basis with the exact project address, work description, applicable construction date and certification responsibility. Do not use the bid date as a substitute for the date that determines the applicable construction standards.
The adopted rule, §5.4013(a)(1) through (3), covers the specified seaward and inland catastrophe areas. TDI's current Adopted Building Codes guidance, “Designated Catastrophe Areas”, says the designated areas did not change with the new codes. Except for Harris County, the entire mapped county participates; within Harris County, TDI specifies locations east of Highway 146 and within the city limits shown on its map.
Two classifications must remain separate:
- Program location: Is this address in the designated catastrophe area?
- Design requirements: What wind speed, exposure, pressures and debris-protection requirements apply to this structure?
TDI's “Wind Speeds” and “Windborne Debris Protection” guidance requires determining wind speed for each structure by location and says most, not all, designated areas are now in the windborne debris region. Do not turn a county name into one universal pressure or an automatic impact-glazing specification.
The estimating decision is to establish the applicable basis before choosing an assembly. For broader applicability questions, use the code-basis scope review, rather than treating this windstorm guide as a complete permit review.
Underlayment alternatives change what you measure
TDI's April 7, 2026, building code update, citing 2024 IRC Table R905.1.1(2), identifies all sections of the catastrophe area as high wind areas for the underlayment requirements it describes for asphalt shingle and modified bitumen roof coverings. It sets out three methods:
- Two layers of mechanically fastened No. 30 asphalt felt or synthetic underlayment conforming to ASTM D8257, with the prescribed starter strip and laps.
- A minimum 4-inch-wide self-adhering polymer-modified bitumen strip conforming to ASTM D1970 over all roof-deck joints, followed by a single layer of the specified felt or synthetic underlayment.
- For the full-coverage route, use one self-adhering underlayment layer that meets ASTM D1970. Follow both the underlayment manufacturer's and roof-covering manufacturer's installation instructions, including their requirements for deck material, roof ventilation and climate exposure.
This is not a choice between three prices applied to the same quantity. Each method asks for a different measurement artifact.
| Underlayment basis | Takeoff artifact to produce | Decision that cannot be hidden in waste |
|---|---|---|
| Two mechanically fastened layers | Sloped deck area, course layout, starter length and fastening basis | Determine course exposure from the required overlap |
| Sealed deck joints plus one layer | Sloped deck area and a separate deck-joint length | Establish the deck panel layout or qualify the joint-length basis |
| Full self-adhering layer | Sloped deck area and product-specific lap layout | Confirm compatibility with deck, ventilation and roof covering |
These are estimating artifacts derived from the methods, not additional TDI requirements. Confirm the selected route with the project documents and inspector. Do not apply this particular IRC table as an unexplained default to every commercial membrane or metal roof.
For roof setup beyond the jurisdictional issue, use the roofing takeoff structure guide.
Worked example: “two layers” is not simply twice the deck area
Illustrative example: Consider one rectangular roof plane measuring 48 feet along the eave and 40 feet upslope, measured on the sloped surface. There are no penetrations, valleys or end laps in this simplified layout. Assume a permitted mechanically fastened underlayment has a 36-inch full-sheet width.
The deck area is:
48 × 40 = 1,920 square feet.
For the two-layer method, TDI's bulletin specifies a starter strip half the full-sheet width, then full-width sheets with successive overlaps of half the full-sheet width plus 2 inches. With this illustrative sheet width:
- Full-sheet width: 36 inches.
- Required successive overlap: 18 + 2 = 20 inches.
- Effective advance of each successive course: 36 − 20 = 16 inches.
The first full-width course covers 36 inches of the 480-inch slope. The remaining extent needs:
(480 − 36) ÷ 16 = 27.75, rounded up to 28 additional courses.
That is 29 full-width courses. Before cutting losses or roll-end laps, their gross sheet area is:
29 × 48 × 3 = 4,176 square feet.
The half-width starter strip adds:
48 × 1.5 = 72 square feet.
The resulting layout quantity is 4,248 square feet, compared with 3,840 square feet if the estimator simply doubles the deck area. The 408-square-foot difference arises from the specified overlap and whole-course layout, not a discretionary waste percentage.
The installation dimensions come from TDI's reproduction of 2024 IRC Table R905.1.1(2). The sheet width and roof geometry are illustrative inputs. Actual roll widths, breaks, end laps and roof geometry require a new layout.
Do not carry 4,248 square feet as a universal multiplier. Preserve the deck area and layout calculation separately so changing the selected product changes the purchase quantity without changing the measured roof.
The joint-sealing route needs a quantity the roof outline cannot supply
For the second method, TDI's same bulletin calls for a minimum 4-inch strip over all roof-deck joints. A roof-area polygon alone cannot establish that length.
Illustrative comparison: If the documented panel layout contains 1,000 linear feet of joints, a 4-inch strip represents:
1,000 × 4 ÷ 12 = 333.33 square feet of strip material, before splice laps, cutting or other installation allowances.
Keep the primary quantity as 1,000 linear feet of deck joints. The strip-area conversion is secondary. It does not replace the separate full-sheet underlayment quantity.
On a re-roof with an undocumented existing deck, the judgment call is whether to carry an assumed panel layout or qualify the joint quantity pending verification. Either can be defensible. What is not defensible is treating an unknown joint length as zero while quoting the joint-sealed route as complete.
A listed window can still be the wrong assembly
The most useful opening distinction is between a product evaluation and a project-compatible installation.
TDI's current Submittal Requirements for Product Evaluation: Windows, dated May 20, 2026, §§1.3 and 2.1, directs design-pressure determination to IRC Chapter 3 or ASCE 7-22, recognizes different exposure conditions and explicitly says evaluation is not approval for use on all structures. Section 2.1 requires the reported product pressure rating to exceed the required project pressure and its debris-resistance rating to satisfy the project's criteria.
These are product-evaluation criteria. They are not a universal anchor schedule or an instruction for the estimator to perform the structural design.
Create an opening register with one row per installation condition, not just one row per nominal size:
- Drawing mark and overall assembly dimensions.
- Individual unit count within that assembly.
- Required project pressures, with their source and basis.
- Required debris protection and the proposed route.
- Evaluation report and exact applicable configuration.
- Fin or frame attachment, substrate and installation detail.
- Mullions, clips, anchors and any unresolved alternate-substrate analysis.
The critical failure is a quote marked “TDI evaluated” that closes the product-selection question but leaves the installation question open. Under §2.2 of the 2026 Windows requirements, the evaluation is based on how the product was tested, including attachment to the test buck and the buck material.
Estimator's decision rule: Treat a proposed change of substrate or anchoring method as an unresolved assembly change until its applicable evidence is identified. Do not assume a stronger-looking screw closes the issue. Sections 2.3 and 4.5 allow alternative-fastener and substrate analysis, specify its required information and require a Texas licensed professional engineer's signed, sealed and dated analysis for that evaluation route.
The quantity consequence can be different fasteners, added supporting material or revised mullion connections. The count must come from the applicable installation detail, not a coastal percentage added to the window price.
Count mulled assemblies without losing the internal connections
TDI's 2026 Windows requirements, §2.4, distinguishes products tested as individual windows from products tested as mulled assemblies. For a mulled listing based on individually tested products, it calls for assembly testing or a mullion analysis. That analysis includes both mullion-to-substrate and window-to-mullion attachment information.
This creates two estimating quantities that should not be collapsed: the number of purchased window units and the number of installed assemblies.
Illustrative example: An elevation has 12 assemblies. Each consists of three side-by-side windows, each 3 feet wide and 5 feet high.
The supply count is 12 × 3 = 36 window units. The installation register contains 12 assemblies, each 9 feet wide by 5 feet high.
There are two internal vertical mullions per assembly:
12 × 2 × 5 = 120 linear feet of internal mullions.
The overall assembly perimeter is:
12 × 2 × (9 + 5) = 336 linear feet.
If each individual window is counted as independently attached around its entire perimeter, that calculation becomes:
36 × 2 × (3 + 5) = 576 linear feet.
The 240-linear-foot difference is exactly twice the internal mullion length. It is not an instruction to deduct 240 feet of fastening. It shows that internal interfaces have been represented as duplicate exterior perimeters, even though the required connection may be window-to-mullion rather than window-to-building.
Carry 36 units, 12 assemblies and 120 feet of mullions as distinct quantities. Then obtain the connection detail. The test that catches the error is reconciliation of elevation geometry with the evaluated assembly, not another count of 36 symbols.
Use the opening-item setup guide for organizing the broader opening package; do not use a door or window count as a substitute for this assembly reconciliation.
Separate pressure resistance from debris protection
A pressure-rated product does not automatically answer the debris-protection question. TDI's 2026 Windows requirements, §1.4, states that a product need not be impact resistant for TDI to develop an evaluation report. Read that beside §2.1's project-specific applicability conditions, not in isolation.
TDI's opening-protection guidance, “Are both impact-resistant windows and shutters necessary?”, says both are not necessary. Its guidance also explains that windows are tested as units including glass, frame, attachment hardware and installation method.
For estimating, compare complete proposed protection routes. An impact-resistant assembly and a non-impact assembly with a separately supported protective system should not be compared using only their window supply prices. For the separate-protection route, ask who carries the protective units, attachment hardware, installation and required handover information.
TDI's same guidance calls for removable panels to be pre-marked and accompanied by a layout plan and installation instructions. That makes opening identification part of the handover artifact, not just the takeoff label.
Do not presume an emergency plywood solution is an acceptable commercial bid substitution. Get confirmation of the proposed route for the actual structure. Competent estimators may favor different routes; the deciding evidence should be the project's required performance, compatible installation and operational acceptance, not the lower isolated supply price.
Make certification visible in trade coverage
The assembly register should end with responsibility, not merely quantity. Identify who supplies the evaluation evidence, who resolves design questions, who coordinates inspections and who obtains the certificate.
TDI's Inspection Process guidance, “When is the inspection performed?” and “How do I apply for an inspection?”, explains that TDI inspectors inspect in-progress work and that projects should be notified before construction starts. It also describes post-construction inspection by an appointed engineer, noting that inspection during construction can be less invasive and less expensive.
The estimating implication is to ask the inspector which connections must remain visible and incorporate those inspection interfaces into the roofing and opening packages. Do not invent a standard waiting allowance or promise a guaranteed inspection turnaround.
Before carrying either package, reconcile four things:
- The measured roof plane or opening assembly.
- The applicable underlayment or installation method.
- The evidence supporting the proposed configuration.
- The trade and inspection responsibility for completing it.
A useful final status is measured, supported and assigned, or measured with an explicit unresolved basis. “TDI included” is not enough.
For the general process, follow the AI takeoff workflow; for method-independent errors, use the construction takeoff mistake checks.
Keep coastal assembly quantities reviewable in Piper
The workflow needs one project basis connecting the drawing quantity to its installation assumptions. A roof polygon, deck-joint length and opening count should remain distinguishable even when they support the same trade package.
Piper's takeoff workflow supports manual, assisted and agentic takeoff from PDF drawings in an editable takeoff file. Assisted tools propose boundaries, traces or symbol matches for the estimator to inspect and correct. Agentic takeoff starts with a measurement task and produces editable measurements grouped into items for review.
For this work, keep roof areas, documented joint lengths, individual windows and assemblies in separate items. Review the source sheet, scale, geometry and coverage before using quantities. Piper keeps takeoff in the same project as drawings, specifications, trade scopes and bid review, but the team still supplies and reviews the pricing basis. Measurement does not establish windstorm compliance or approve an alternate connection.
FAQ
Which code edition applies to current Texas windstorm work?
Under 28 TAC §5.4013(a), the adopted 2024 IRC and IBC apply to designated-area structures constructed, repaired or added to on and after April 1, 2026, for catastrophe-property-insurance eligibility. Confirm the applicable construction date and certification path rather than using the bid date or a statewide assumption.
Does a TDI product evaluation mean a window works anywhere on the coast?
No. Section 2.1 of TDI's May 20, 2026, Windows evaluation requirements makes applicability project-specific. Match required pressures, debris criteria and the evaluated configuration. Sections 2.2 through 2.4 also make substrate, attachment and mulled-assembly evidence relevant to the installation being priced.
Can I estimate high-wind underlayment as twice the roof area?
Not as a finished purchase quantity. TDI's April 2026 bulletin reproduces the overlap and starter requirements from 2024 IRC Table R905.1.1(2). Those dimensions, product width and whole-course rounding determine the layout quantity. Preserve measured deck area separately from laps, cutting and procurement allowances.
Should mulled windows be counted as units or assemblies?
Count both, for different purposes. Individual units support the supply count; assemblies support configuration and installation review. Record internal mullions separately and derive their connections from the applicable detail. TDI's 2026 Windows requirements §2.4 distinguishes individual-product listings from mulled-assembly listings and analysis.
Related reading
Construction code requirements: confirm the applicable basis before assigning scope
A model-code reference is not a project applicability decision. Review connecting adopted requirements, issued design information, trade scope and pricing.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.