How to write a waterproofing and sealants scope subs will price the same way

Write waterproofing scopes around complete assemblies, named transitions and substrate handoffs so bidders price the same preparation, testing and warranty.

Guide11 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Define assemblies before assigning specification sections
  2. Make the document register a map of scope, not a reading list
  3. Assign the interface by layer and operation
  4. The judgment call: one interface installer or split packages?
  5. Define substrate turnover without giving away unlimited repair
  6. Price protection and testing as a sequence
  7. Illustrative carry: the area stays the same, the package changes
  8. Require the actual warranty, not just a duration
  9. Reusable waterproofing and sealants scope outline
  10. General and basis of bid
  11. Inclusions
  12. Exclusions and by-others assignments
  13. Clarifications and unresolved conditions
  14. Alternates and unit prices
  15. Final scope reconciliation
  16. Keep the assembly, boundary and revision connected

For a GC estimator issuing a commercial building waterproofing package at bid-ready CDs or a GMP release, the scope should define complete assemblies and their handoffs, not simply assign Division 07 or request a price per square foot. Give every bidder the same system, limits, preparation basis, transition ownership, testing sequence and warranty obligation.

The decisive question is not “Does this sub include waterproofing?” It is “Where does its responsibility start, what does it connect to, and when is the work accepted for covering?” Two bidders can include the same membrane area and still price different jobs.

This guide provides a reusable bid-scope structure for below-grade waterproofing, protected horizontal membranes and general joint sealants. It also shows how to assign interfaces with air barriers, roofing, glazing, expansion joints and traffic coatings. It is not a design specification or a substitute for resolving an incomplete enclosure detail. On a renovation involving unknown substrates or hazardous existing sealants, add a project-specific investigation and removal basis before using this outline.

Define assemblies before assigning specification sections

Start with an assembly schedule. Give each system a scope identifier tied to its actual location: foundation wall, occupied-space plaza deck, planter, window perimeter or exposed floor joint. Do not let one line called “waterproofing” combine them.

The current public UFGS 07 14 00, Fluid-Applied Waterproofing, dated August 2023, illustrates why. Its stated application is a horizontal membrane protected by a separate wearing course. It includes membrane, protection board, drainage layer and insulation, but not the structural deck, protection slab or wearing course. Its editorial notes specifically direct hydrostatic-pressure applications to a different section.

The August 2025 UFGS 07 13 53, Elastomeric Sheet Waterproofing, addresses sheet waterproofing, including wall and foundation applications, and calls for drawings showing extents, substrates, terminations, flashings, penetrations and wall-to-floor junctions.

These are federal guide specifications to be edited for a project, not universal requirements for private commercial work. The copies checked for this guide reference the October 2026 UMRL. Use your issued contract sections and their selected requirements, not unedited guide options.

Scope-writing rule: classify the assembly by exposure and use before copying its inclusions. “Fluid applied” describes a method; it does not establish that two locations have the same system or acceptance basis.

For each assembly, record:

  • Location and drawing limits, including vertical returns and concealed extensions.
  • Specified system type, thickness and application orientation.
  • Substrate and required condition at turnover.
  • Reinforcement, joint treatment, primers, flashings and terminations.
  • Protection, drainage and insulation, where specified.
  • Testing and release for concealment.
  • Manufacturer and installer warranty obligations.

For the overall process of assembling a trade package, use the construction scope generation guide; the waterproofing-specific work starts with this assembly schedule.

Make the document register a map of scope, not a reading list

Reference specifications by section title, number and issued revision. Include the applicable waterproofing and joint-sealant sections, then identify related concrete, masonry, air-barrier, roofing, glazing, sheet-metal, expansion-joint, coating and Division 01 requirements that affect this package.

Add drawing sheet and detail references beside the corresponding assembly. A foundation plan establishes a run, but the wall section should establish its height and termination. A plaza plan establishes horizontal limits, while drain, curb and expansion-joint details establish associated work. Window details should distinguish the concealed transition from exposed perimeter joints.

The UFGS joint-sealants guide, 07 92 00, August 2023, asks designers to show where each sealant type is used and provide joint details with symbols or designations. It separately addresses interior, exterior, floor and acoustical sealants. That makes a location-based sealant schedule a better pricing instruction than “all caulking.”

Complete the register with addendum numbers and dates, answered prebid RFIs, scope-basis clarifications, phasing plans and applicable testing or enclosure-commissioning requirements. Identify unresolved information as unresolved. Do not silently turn a GC assumption into a design requirement.

A useful entry reads:

Assembly WP-02: protected plaza membrane; limits per plaza plan and perimeter sections; drains and penetrations per listed details; system and acceptance per issued waterproofing section; revised north termination per named addendum. Clarification C-02 defines temporary protection pending test acceptance.

Replace every reference with an actual project identifier before solicitation.

Assign the interface by layer and operation

Avoid boundary statements that assign only an object: “windows by glazing,” “roofing by roofer” or “expansion joints excluded.” Name the operation and the layer it completes.

The UFGS building air-barrier guide, 07 27 10, August 2023, calls for a continuous air-barrier boundary and details connecting walls to foundations, roofs, windows and doors. It also places air-barrier testing in a companion enclosure-commissioning section. Read that alongside the joint-sealant location schedule: an exposed window bead is not, by itself, proof that the concealed air-barrier connection has been assigned.

Use a boundary schedule like this. The allocations below are illustrative choices, not standard trade ownership.

InterfaceWaterproofing or sealant packageNamed adjacent package and acceptance
Foundation to wall air barrierComplete below-grade termination to designated connection lineAir-barrier package completes compatible transition to termination; inspect before concealment
Window openingGeneral exterior perimeter joint only if scheduled hereGlazing owns assembly seals; air-barrier package owns concealed frame transition and opening flashing if assigned there
Roof to wallComplete assigned wall membrane and identified receiving surfaceRoofing owns roof membrane tie-in and integral roof flashings; sheet metal owns separately scheduled metal work
Expansion jointMembrane continuity beneath or beside cover, plus scheduled sealantJoint-cover package owns cover assembly, anchors and its specified seals
Traffic-coated deckCarry only the scheduled membrane or coating assembly and identified joint treatmentConcrete owns specified substrate turnover; coating package owns named wear layers and reopening criteria
PenetrationFlashing or weather seal at the designated moisture-control layerPenetrating trade owns sleeve and fixing; firestopping has a separate rated-system assignment

The schedule should also say who submits the interface detail, who supplies each material, who installs it and who confirms compatibility. A detail review is not the same operation as installing a transition.

For rated penetrations, make the separate assignment explicit and refer to firestopping ownership. Do not assume the weather-seal allocation settles it.

The judgment call: one interface installer or split packages?

Competent precon teams can reasonably choose either approach. A single installer may be preferable where a connection becomes inaccessible early or where the proposed system warranty depends on that installer completing the transition. Split ownership may be preferable where glazing or roofing installation controls access and the adjacent specialist must make the final connection.

Decide using the actual receiving substrate, installation sequence, installer qualifications and proposed warranty documents. Do not decide from the section number alone. If split ownership is retained, assign one interface coordinator and a specific inspection hold point; “coordinate with others” is not a completion criterion.

Define substrate turnover without giving away unlimited repair

Separate application preparation from substrate correction.

Application preparation is the work needed to apply the selected system to an agreed receiving condition: cleaning, priming, masking, specified crack or joint treatment and accessory installation. Substrate correction is work that changes an unacceptable receiving condition: substantial surface repairs, reprofiling, correcting slope or removing incompatible materials beyond the agreed base scope.

The distinction is a commercial allocation, not permission to omit required preparation. UFGS 07 13 53 requires clean, dry, smooth receiving surfaces and correction before installation; its editorial notes also tell the specifier to coordinate removal of wax- or oil-containing curing compounds with the concrete section. UFGS 07 14 00 expressly includes removal of contaminants that could impair membrane bonding. Both show why “prep by others” is too broad. Sheet waterproofing source and fluid-applied source.

Write three connected obligations:

  1. The concrete or masonry package delivers a substrate meeting the identified waterproofing receiving criteria.
  2. The waterproofing package inspects, reports deficiencies and performs the specifically listed application preparation.
  3. A named package corrects rejected conditions before release, with a defined pricing mechanism for genuinely uncertain quantities.

That catches a particular estimating error: concrete prices its normal finish, waterproofing excludes all preparation, and neither number includes removal of an incompatible curing compound. The check is to compare the concrete turnover clause against the membrane preparation clause before issuing either scope.

For existing work, state whether the bid basis includes test patches, removal, disposal and repair. If those quantities cannot be established, use a defined allowance or measured unit price rather than an unlimited instruction to “make substrate suitable.”

Price protection and testing as a sequence

Protection board is not interchangeable with temporary protection. The scope should distinguish permanent system components from barriers, access control, temporary coverings and damage repair while the membrane awaits acceptance.

UFGS 07 14 00 prohibits permanent protection-board installation until the membrane passes the specified flood test, while requiring protection if board is not placed immediately. It includes substrate-moisture testing, film-thickness checks and flood testing, with an optional electronic leak-testing provision. UFGS 07 13 53 requires acceptance before concealment and protective covering before backfill. These requirements apply when selected in the project documents. Fluid-applied testing and sequence and sheet protection sequence.

The combined estimating consequence is a separate exposed-membrane interval. Buying the permanent protection board does not necessarily price protection during curing, testing or delayed acceptance.

Specify who carries:

  • Substrate checks and application quality-control records.
  • Test-agency procurement, separately from installer support.
  • Test preparation, temporary dams or drain isolation where required, water supply and disposal.
  • Access, temporary protection and attendance during testing.
  • Repair and retest of the installer's deficient work.
  • Inspection and release before backfill, topping, pavers or other concealment.
  • Protection after acceptance and responsibility for damage by subsequent trades.

For electronic testing, confirm the test approach and required assembly provisions before bidders finalize pricing. Do not write “flood or electronic test” as though it authorizes an unapproved substitution. Likewise, do not prescribe test loading without the project design and approved procedure.

Illustrative carry: the area stays the same, the package changes

Assume a protected plaza has 8,000 square feet of membrane, 400 linear feet of perimeter transition and 24 penetrations. All quantities, rates and amounts below are illustrative, not market benchmarks or customer results.

An initial quote carries membrane application at $8.00 per square foot: 8,000 × $8.00 = $64,000. It excludes protection, transition accessories and test support. The GC's scope review identifies these additional assignments:

Scope treatmentIllustrative calculationIllustrative amount
Membrane application8,000 SF × $8.00$64,000
Compatible permanent protection8,000 SF × $1.50$12,000
Perimeter transition400 LF × $12.00$4,800
Penetration detailing24 each × $150$3,600
Installer test supportFixed scope amount$2,400
Temporary protection before acceptanceFixed scope amount$1,800
Complete assigned packageSum of listed work$88,600

The assigned package increases by $24,600 without adding one square foot of field membrane. That is not a finding about industry pricing. It demonstrates why a membrane-only quote cannot be used as the complete package carry.

Now assume a separate GC testing line contains $4,000: $1,600 for the agency and $2,400 for installer support. Once support is included in the waterproofing package, retain only the $1,600 agency cost outside it. The reconciled commitment is $88,600 + $1,600 = $90,200, not $92,600.

The useful check is two-sided: add uncovered obligations, then remove duplicate treatment elsewhere. Requiring “all testing” in the subcontract without checking the GC line can increase apparent completeness while double carrying cost.

Require the actual warranty, not just a duration

Ask bidders to identify the proposed system, installer eligibility and warranty form with their price. Record material coverage, workmanship coverage, covered accessories, beneficiary, commencement event, exclusions and any required inspection or testing.

The two waterproofing guides illustrate materially different promises. UFGS 07 14 00 specifies a manufacturer no-dollar-limit system materials and installation-workmanship warranty; UFGS 07 13 53 separates a contractor installation guarantee from a manufacturer material warranty. Neither is a default warranty for every commercial project. Fluid-applied warranty and sheet-system warranty.

Therefore, “same warranty years” is not a sufficient leveling criterion. Read the proposed coverage alongside the boundary schedule. If accessories necessary for the required system warranty are excluded from the installer package, resolve who performs them and whether the proposed warranty still meets the contract.

Reusable waterproofing and sealants scope outline

Use this as the scope sheet's structure. Complete the fields and remove inapplicable items before issuing it.

General and basis of bid

  • Project, package identifier, locations and assembly schedule.
  • Issued specifications, drawings, details, addenda and written clarifications.
  • Required submittals, coordination details, mockups and approvals.
  • Access, work phases, mobilization basis and environmental-control assignments.
  • Substrate turnover criteria and rejection procedure.
  • System and warranty basis; approval process for proposed alternatives.

Inclusions

List each membrane assembly separately. Include its specified primers, adhesives, reinforcement, corners, joint and crack treatment, terminations, drains, penetrations and transitions. Name protection board, drainage components and insulation where assigned. Separate installation inspection, temporary protection, permanent protection and testing support.

For sealants, attach a location schedule identifying joint designation, substrate pair, interior or exterior face, joint size, specified material classification, color basis and access. Assign cleaning, primer, backing, bond breaker, tooling, mockups and required adhesion checks. UFGS 07 92 00 explicitly addresses substrate compatibility, mockups, adhesion, primers, backing and bond breakers; use the project's selected requirements rather than assuming a single sealant fits every location. Joint-sealant requirements.

Exclusions and by-others assignments

For every exclusion, provide the receiving package and retained interface obligation. Address structural repair, slope correction, dewatering, wearing courses, glazing assembly seals, roof-system seals, firestopping and expansion-joint covers as applicable.

Do not issue “protection board excluded” without assigning the compatible board and installation sequence elsewhere. Do not issue “all sealants by others” when this package still needs termination sealant or membrane-associated joint treatment.

Clarifications and unresolved conditions

State the base receiving condition, access basis, quantities subject to verification and treatment of unknown repair. Record unresolved design questions with an owner and required decision date. Obtain a common written bid basis rather than allowing each bidder to invent one.

Alternates and unit prices

Keep alternates separate from the base. A proposed system alternate should identify changes to preparation, transitions, protection, testing and warranty, not just the membrane deduction.

Define unit prices by operation and measurement: square feet of a named repair, linear feet of a joint within a stated width and depth range, or each penetration within a defined size range. State included access, preparation, materials, disposal and mobilization, plus who authorizes and verifies quantities. Do not use one sealant rate for unspecified joint dimensions.

Final scope reconciliation

Require the bidder to return an explicit inclusion, exclusion or clarification against each assembly and boundary row. Transfer accepted clarifications into the subcontract exhibit; do not leave the agreed allocation only in an email.

For a separate diagnostic pass, use waterproofing scope gaps; for a wording review, use waterproofing scope-writing mistakes.

Keep the assembly, boundary and revision connected

The durable record is the assembly identifier connected to its drawing detail, receiving condition, adjacent package, test release and warranty treatment. When one changes, the team needs to know which scope commitments deserve another look.

Piper's Scope Generation workflow organizes drawings, specifications, addenda and company requirements into trade-specific scopes with source references. It can surface uncertain boundaries and affected scope for review as project information changes. That supports the same assembly-and-handoff discipline described here; the estimator still decides the allocation, resolves unclear requirements and approves the scope before solicitation.

FAQ

Should waterproofing and general sealants be one subcontract?

They can be, but price them as separate location-based schedules within the package. Decide the contract grouping from installer capability, access, sequence and warranty requirements. A combined subcontract does not remove the need to assign glazing seals, roofing seals and concealed enclosure transitions explicitly.

Who should carry substrate preparation?

Assign application preparation to a named package and substrate correction to a named package, even if the same sub performs both. Define the receiving condition, inspection process and included operations. For uncertain repair, establish a measured unit price or allowance instead of leaving an unlimited preparation obligation.

Can protection board and testing be excluded from the waterproofing bid?

Yes, if the GC assigns the required work elsewhere and reconciles the installation sequence. The exclusion must identify who supplies and installs compatible protection, who procures testing and who supports it. Temporary protection pending acceptance needs its own treatment rather than disappearing inside the permanent-board line.

What makes two waterproofing bids comparable?

The same assembly limits, specified system, preparation basis, accessories, transitions, testing support and warranty obligations make the comparison meaningful. Matching membrane area alone is insufficient. Reconcile each bidder's departures against that common scope, then check the GC estimate for both uncovered work and duplicate carries.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.