What changed in this addendum? Find what it changes in your bid, not just on the sheet

The costly parts of an addendum are often not on a clouded sheet. A worked example and a 12-point checklist for turning an addendum into the scopes, quotes and estimate lines it changes.

Guide4 min read

Published

Construction scaffolding interior

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Ask what changed in what you are carrying, not on the sheet
  2. Worked example: Addendum 3, one clouded sheet, five changes
  3. When an addendum arrives
  4. What the bidding rules say about addenda
  5. Related guides
  6. Where Piper fits

The revised sheet is the easy part of an addendum. The narrative, the questions and answers, the replaced spec sections and the bid form often change more of your number than the clouded drawing does.

Ask what changed in what you are carrying, not on the sheet

A clouded sheet tells you what is different on that sheet. On bid week you need to know which scopes, sub quotes, estimate lines and bid-form entries are now wrong, which subs have to reprice by when, and what you must acknowledge for the bid to stay responsive.

The most expensive parts of an addendum are often not on a revised sheet: a Q&A answer that moves work between trades, a spec section replaced in its entirety, a schedule that was not reissued, or a new line on the bid form.

Worked example: Addendum 3, one clouded sheet, five changes

Hypothetical: a four-story NYC public library renovation bid through PASSPort. Addendum 3 is issued Thursday and the bid is due Tuesday at 2:00 pm. Only sheet A-501 is clouded.

WhereWhat it saysIf nobody connects it
Spec 08 71 00, replaced in its entiretyThe new section is read for what it adds, such as power supplies now furnished by the hardware supplier.The old section made permanent cores owner-furnished. The new one is silent, so cores and keying fall back to the contractor. Nobody reads what is no longer there.
Questions and answers, item 14“Firestopping of penetrations is by the trade making the penetration.”The drywall quote you carry includes it and every MEP quote says “by others”. When the MEP subs reprice to include it, the drywall line double counts. If they do not, they carry an exclusion the addendum just made theirs. No drawing changed.
Bid formNew unit price line UP-4: additional 2-hour rated partition, per square foot.A blank new line, or an acknowledgment entry that stops at Addendum 2, can make a correct number non-responsive.
Revised sub quotesThe hardware quote now acknowledges “Addenda 1 to 3”.It still excludes power supplies and cores. Acknowledged is not priced.
A-501 Rev 2, wall typesPartition P3 at the stair enclosures goes from 1-hour to 2-hour, with an added layer of Type X board each side.Stair doors in a 2-hour enclosure generally need 90-minute doors and frames, but the door schedule was not reissued and still shows 60-minute.

Most of the money in this addendum is in items with no cloud. Map every item to the packages and estimate lines it touches, then check the revised quotes against the change, not just the acknowledgment line.

Bring a bid package and its latest addendum. In the demo we read the addendum against your scopes, quotes and estimate in Piper and show which ones it touches, with the source for each change. Book a project demo

When an addendum arrives

  1. Log every item and attachment. Confirm you hold all earlier addenda with no gap in the numbering.
  2. Read the narrative and Q&A first. Mark every answer that moves work between trades.
  3. Follow each revised sheet outward. List the schedules, sheets and spec sections it implies a change to, especially ones not reissued.
  4. Compare replaced spec sections both ways. Look for what was deleted, not only what was added.
  5. Check the bid form and instructions. New unit prices, alternates, allowances, breakdowns, required forms and the acknowledgment line.
  6. Check dates and the question deadline. Bid date, time and portal, and whether you can still ask.
  7. Confirm the submission mechanics. On NYC PASSPort, whether the addendum needs an updated response or opens a new round.
  8. Send it to every affected sub with a reprice date. Do not assume they downloaded it from the plan room.
  9. Check revised quotes against the change. Not only the acknowledgment line.
  10. Remove the old carry where scope moved trades. And confirm the receiving trade now covers it.
  11. Tag changed estimate lines with the addendum item. Record any temporary plug with its basis and owner.
  12. Reconcile at final review. Acknowledgment, bid form and estimate against the full addendum list.

What the bidding rules say about addenda

  • Under the standard AIA Instructions to Bidders, addenda are issued no later than four days before bid receipt unless they postpone the bid, and each bidder must make sure it has received all addenda and acknowledge them in the bid. Source: AIA A701-2018, §3.4.
  • DASNY solicitations state that only documents obtained from the designated source make a bidder a plan holder of record, and that documents from other sources may not contain issued addenda. Source: DASNY solicitation.
  • On NYC PASSPort, agencies publish a summary of changes with each addendum, and a vendor may need to submit an updated response or answer a new round. Source: NYC Mayor’s Office of Contract Services.
  • Federal reference point: a missing acknowledgment can be waived only if the amendment has a negligible effect on price, quantity, quality or delivery. State and city agencies set their own rules in the instructions to bidders. Source: FAR 14.405.

Where Piper fits

  • Piper reads drawings, specs and addenda together, revision-aware, and answers with the source page.
  • When an addendum arrives, affected trade scope can be surfaced for review instead of relying on memory.
  • Bid leveling pulls each bidder’s addenda acknowledgment next to their exclusions, so a quote on an old addendum is visible.
  • Final bid review checks the estimate against the latest addenda and flags work that may be stale.
  • Piper does not send addenda to subs or change the estimate. Your team decides what moves.

See how the final bid review workflow works, or book a project demo and bring the documents from a bid you are working on now.

ShareLinkedInX

Related reading

Guide4 min

Construction addenda management for GC estimators

Addenda are official bid-document revisions. Log them, distribute them, retakeoff the deltas, and require subcontractor acknowledgments so your estimate and every bid reflect the final scope.

Tower crane above steel reinforcement

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.