Catch what both subs excluded: the shared exclusions bid leveling misses

A shared exclusion has a zero delta, so leveling bids against each other never shows it. A worked controls-wiring example and an 11-point checklist for finding work no bidder carries.

Guide4 min read

Published

Steel frame of a building rising on a jobsite

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Two trades, two clean leveling sheets, one missing scope
  2. Worked example: control wiring that no bidder carried
  3. Eleven checks for exclusions every bidder shares
  4. Why shared exclusions get expensive late
  5. Related guides
  6. Where Piper fits

When every subcontractor excludes the same work, the difference between their bids is zero, so leveling never flags it. The only way to find it is to check each bid against the scope and the specifications, not against the other bids.

Two trades, two clean leveling sheets, one missing scope

Leveling answers “which bid is cheaper for the same work”. It cannot answer “is all the work there”. Bids that are equally incomplete look clean.

It often takes two trades to see. Mechanical excludes the item “by electrical”, electrical excludes it “by Division 23”, and each leveling sheet is consistent on its own. The gap is between the sheets, and only the spec shows who owns it.

Worked example: control wiring that no bidder carried

Hypothetical: a three-story private lab and office building. Two mechanical bids (A at $4.18M, B at $4.32M) and two electrical bids (C at $2.71M, D at $2.65M).

WhereWhat it saysIf nobody connects it
Spec 23 09 23“Control wiring and conduit: furnished and installed by the controls contractor under this section.”The obligation sits with mechanical, through its controls sub.
Spec 26 05 00“Control wiring by Division 23.”Electrical bidders read it, correctly, as not theirs.
Mechanical bids A and BBoth include DDC controllers and sensors. A excludes control wiring “by electrical”. B excludes “line and low voltage wiring by others”.Both exclude it, so the $140,000 spread looks like apples to apples.
Electrical bids C and DC excludes “control wiring by Division 23”. D is silent.C’s exclusion only restates the spec, so leveling adds nothing to either electrical bid. Nobody adds the wiring itself.
Estimate reviewFinding: control wiring per 23 09 23 is in no carried number. Sources: spec 23 09 23, Mech A quote page 1, Elec C quote page 2.Options for your team: carry a GC line, add it to Mech A at their rates, or clarify with both trades before bid day.

Both leveling sheets were right. The work was still missing. Checking each bid against the spec, not against the other bid, is what finds it.

Level one of your packages against the scope. Bring two or three bids for one trade from a current project, or two trades that share a boundary. We will level them against your scope on a call and look for what every bidder left out. Book a project demo

Eleven checks for exclusions every bidder shares

  1. Level against the scope, not only against the bids. Spec sections, drawings and addenda are the rows.
  2. Record a status for every bidder on every item. Included, excluded, qualified or silent.
  3. Sort for rows where every bidder is excluded or silent. Those are absolute gaps, not deltas.
  4. Read exclusions across trade pairs. Mechanical, electrical and controls; plumbing and site utilities; drywall and firestopping; roofing and sheet metal.
  5. Check Division 01 work assigned to “the Contractor”. Temporary heat and winter protection, hoisting, protection, cleaning, permits and testing.
  6. Confirm every bidder priced the same addenda. A bid on an older addendum is a different scope.
  7. Decide who owns each shared exclusion. A GC line, a third package, or a named sub with a clarification. Write it down.
  8. Price the gap before comparing leveled totals. The evaluated low bid can change once the gap lands on one bidder.
  9. Treat “by others” with no named party as an exclusion. Not as coverage.
  10. On public work with sub listing, resolve gaps first. Before the sealed list is final.
  11. Send every open shared exclusion to final review. So it is checked against the estimate before the bid goes out.

Why shared exclusions get expensive late

  • On New York public work where separate specifications are not required, bidders submit a sealed list naming their plumbing, HVAC and electrical subs and the amount for each. Changing an amount after the low bid needs the owner’s approval. Source: NY General Municipal Law §101.
  • Where separate specifications are required, the owner bids plumbing, HVAC and electrical as separate prime contracts, so a controls and power boundary can sit between two primes. Source: NY General Municipal Law §101.
  • On federal sealed bids, a bid is rejected when it imposes conditions that modify the requirements of the invitation, so a GC cannot simply pass a sub’s qualification through to the owner. Source: FAR 14.404-2.

Where Piper fits

  • Piper compares each sub bid against the trade scope and the project documents, not only against the other bids.
  • Base bid, inclusions, exclusions, qualifications, alternates, allowances, unit prices and addenda acknowledgments come out with their page.
  • Missing, overlapping and unaddressed scope is flagged, including where every bidder may be missing the same requirement.
  • It works in your own leveling sheet and exports to Excel.
  • Findings stay in the project for final bid review. Your team decides the carry.

See how the bid leveling workflow works, or book a project demo and bring the documents from a bid you are working on now.

ShareLinkedInX

Related reading

Guide7 min

Public bid leveling: the file is the evidence

Prepare a source-backed leveling file before a sealed public bid. Keep scope coverage, bid compliance and permitted post-opening procedures distinct under the governing rules.

Tower crane against an overcast sky

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow

See Piper on your project

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.