Empire State Plaza chillers: separate Phase 1 conversion from the later thermal network
Separate the Plaza's Phase 1 chiller and receiving-building recommendations from later network work and identify the design evidence needed to price them.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 4 min
- Published
On this page
A GC estimating Empire State Plaza Phase 1 should distinguish the electric chiller conversion from the building changes needed to use recovered heat. The 2024 master plan recommends both, but it also describes later laboratory relocation and a broader thermal network. Do not carry those later phases as an issued Phase 1 package without current design documents.
The May 20, 2024 Energy Infrastructure Master Plan is a dated recommendation, not a construction contract. The June 25, 2025 OGS announcement is a later funding and design statement; it does not establish that the recommendations were adopted unchanged. Sources were checked November 17, 2026. Obtain current documents and procurement status before committing a price.
What Phase 1 connects
The master plan says Chiller 4, the first electric chiller, was installed in 2022 and first used in 2023. It recommends two additional electric chillers and notes that steam-driven chillers could remain for resilience. That is a conversion recommendation, not evidence that existing steam equipment has been removed.
The report also recommends a heat recovery chiller and a targeted building renovation to use its low-temperature hot water. The receiving-building work is necessary to make use of that heat; simply replacing a steam-driven cooling machine with an electric chiller does not define the building conversion. The checked report passages do not name the demonstration building. The report describes it as a proof of concept before broader Phase 3 work, not a commitment to convert every Plaza building in Phase 1.
OGS later described initial $100 million Environmental Bond Act funding for electric chillers and a heat recovery chiller, and an additional $136 million appropriation over five years for building modifications to accommodate the heat recovery chiller, then in design. OGS projected an approximately 20% emissions reduction. That is a projection, not a measured result. These funding amounts are not a single awarded contract price.
Separate the scope by phase and evidence
The following matrix is an estimating interpretation of the cited documents. The missing items are requests for current evidence, not assertions about how contracts have been divided.
| Scope and source basis | Interface implication | Missing evidence before a carry |
|---|---|---|
| Phase 1: 2024 report recommends two additional electric chillers | Cooling plant equipment and electrical demand must be understood together | Current equipment schedules, electrical design, procurement boundaries and utility coordination study |
| Phase 1: 2024 report recommends a heat recovery chiller and targeted demonstration-building renovation; 2025 OGS update funds modifications and describes the chiller in design | Recovered heat needs a receiving building able to use lower-temperature water; plant and building connection cannot be assumed from equipment supply alone | Named receiving building, current heat loads, tie-in limits, controls, drawings and commissioning responsibilities |
| Phase 2: 2024 report assumes laboratory relocation and a resulting load reduction; future building use was uncertain | Later load and reuse assumptions affect the longer-term system basis, not automatically the Phase 1 carry | Current relocation plan, occupancy and confirmed future use and loads |
| Phase 3: 2024 report recommends Plaza tunnel low-temperature hot-water distribution and building exchanger replacements | Later distribution and plant boundaries must be identified separately from a Phase 1 building connection | Current network design, heat-source decision, construction package limits and tie-in details |
| Phase 3: 2024 report recommends phased building mechanical and ventilation renovation with large areas vacated during work | Later occupancy and access assumptions affect sequencing and cost, but are not a current shutdown schedule | Current occupancy plan, access constraints, approved sequencing and supporting rehabilitation scope |
For the later network, the report describes retaining steam between the Sheridan Avenue Steam Plant and the Central Air Conditioning Plant, with a steam-to-hot-water transfer station at the latter. It recommends replacing building steam-to-hot-water exchangers with water-to-water plate-and-frame exchangers. These are later study recommendations, not evidence of a selected heat source or issued Phase 1 scope. The report's Phase 3 building recommendation also anticipates roughly 140°F water at design conditions; current design must establish the actual temperature and receiving equipment.
The report estimated Phase 3 mechanical ventilation renovation at $800 million to $1 billion in study-period dollars, excluding additional supporting and code-related renovation costs it did not estimate. This is a later planning estimate, not a Phase 1 bid or a current award. The report also assumed an office-type reuse for the relocated laboratory building because its eventual use was not known. Neither that assumption nor the projected load reduction confirms the present occupancy plan.
Check the electrical arithmetic, then obtain the study
The 2024 report uses approximately 18,500 tons of peak cooling and 0.56 kW per ton for new centrifugal chillers. Multiplication gives 10,360 kW, or 10.36 MW, rounded to the report's 10.4 MW modeled increase. Adding 10.4 MW to its 17.8 MW baseline yields 28.2 MW. These are the report's inputs and modeled result, not a measurement of present demand or proof that the utility can serve it.
The report says a local utility coordination study of the effect on transmission lines was outside its scope and required before advancing. Ask for that study and its current disposition, along with the design demand, service arrangements and any utility requirements. The master plan alone does not establish utility approval.
Price only a documented boundary
Request a common current revision of the plant and receiving-building drawings, equipment and controls schedules, scope assignments, utility study, occupancy and access constraints, and commissioning and acceptance requirements. Record who owns the unresolved plant-to-building connection and which price revision includes it. Do not prescribe a live cutover from this planning report; obtain the actual operational constraints and approved sequence.
For example, if a hypothetical plant quote includes a heat recovery chiller but a separate building quote starts at a local connection, neither description necessarily prices the intervening work. Mark the two quoted limits on the same current drawing and request clarification before carrying a gap or deleting an apparent overlap. This example does not assert that Plaza contracts are split that way.
Once proposals exist, review bid scope and responsibility gaps against the issued design. To decide whether any Albany project has reached that point, compare project stages and evidence.
Related reading
12 Scope Gaps and Double-Ups to Look for When Leveling HVAC Bids
Twelve HVAC scope gaps and double-ups GC estimators should hunt for when leveling mechanical bids, with what each looks like on drawings and in trade quotes.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow
See Piper on your project
Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.