How to write a masonry scope of work subs will price the same way

Write a masonry bid scope that fixes grout extent, lintel ownership, flashing handoffs and access conditions so bidders price the same assembly and sequence.

Guide11 min read

Published

Tower crane above steel reinforcement

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. Build a document basis that survives the wall-type shorthand
  2. Define the masonry assembly before listing accessories
  3. Write reinforcement and grout as separate, connected obligations
  4. Assign handoffs by operation, not by material name
  5. Separate loose lintels from attached structural supports
  6. Define flashing completion, not just flashing installation
  7. Make temporary work follow the support sequence
  8. Test the scope with one wall before issuing the package
  9. Reusable masonry bid-scope outline
  10. General and document basis
  11. Inclusions
  12. Exclusions and work by others
  13. Clarifications and unresolved decisions
  14. Alternates and unit prices
  15. Pre-issue check
  16. Keep each masonry assignment connected to its project source

For a GC estimator issuing a commercial or school masonry package at bid-stage CDs, the scope should fix three things before asking for a lump sum: the wall assembly, the work each trade owns, and the conditions under which that work will be installed. “Complete masonry per plans and specifications” can remain a general obligation, but it is not a useful pricing instruction by itself.

The strongest masonry scope is organized by wall type and location, with separate assignments for reinforcement, grout, lintels, flashing, built-in items and temporary work. It tells bidders what to include without prescribing every means and method.

This guide covers new CMU and brick masonry bid packages and subcontract scope exhibits. It is not a restoration specification, an engineered masonry design or a substitute for the issued contract documents. At DD or an early GMP, record unresolved design as a common pricing basis rather than implying the assembly is complete.

Build a document basis that survives the wall-type shorthand

Start the scope with an attachment register. Identify the drawing set and revisions, specification issue, addenda and written bid clarifications. Reference sheets and details by their actual identifiers, not by invented standard sheet names.

For each masonry wall type, connect:

  • Architectural plans, wall schedules, elevations and sections showing location, finish, thickness, pattern and height.
  • Structural notes and details showing reinforcement, bond beams, lintels, bearing conditions, dowels and grouted areas.
  • Envelope details showing ties, insulation, flashing, weeps and transitions.
  • Opening schedules and relevant MEP details showing frames, sleeves, recesses and built-in work.
  • Applicable Division 01 requirements for submittals, mock-ups, access, protection, quality control and closeout.

The current UFGS 04 20 00, Unit Masonry, dated May 2025 with references aligned to October 2026, illustrates why this cross-reference matters. It addresses reinforcement, grout, flashing, insulation, built-in items, tests, cleaning and protection, not just units and mortar. It is a federal guide specification requiring project editing, not a universal subcontract assignment.

Use the actual project section numbers. Do not assume every project places accessories or mortar and grout in the same sections. Likewise, identify the masonry standard edition incorporated by the project rather than writing “latest edition.” UFGS references TMS 402/602-2022; that does not establish which edition governs another contract.

A useful scope line has five parts:

Location + assembly + included operations + interface assignment + source.

For example, as illustrative drafting language:

Provide exterior brick veneer at the east elevation, including scheduled units, mortar, ties, cavity drainage accessories, through-wall flashing and weeps identified in the attached detail register. Refer to the responsibility schedule for air-barrier transitions and steel supports.

That line is not ready to issue until the actual elevation, products, details and responsibility schedule are attached. For the broader package-building process, use the construction scope generation guide.

Define the masonry assembly before listing accessories

Organize inclusions by wall type, not as one undifferentiated materials list. Use separate paragraphs for reinforced CMU, nonbearing CMU partitions, brick veneer and any distinct architectural masonry.

For each, specify the project-defined thickness, unit type, finish, color, bond pattern, mortar, joint finish, exposed faces, returns, special shapes, sills and copings. Identify parapets, pilasters, shafts and below-grade work by location. State whether cavity insulation is included or assigned elsewhere.

Then describe the associated operations. The UFGS unit masonry guide includes cut-unit drawings, reinforcement details, samples, mock-ups, weather procedures and test reports among its submittals. It also distinguishes masonry lintels from precast concrete and steel lintels. Use those categories as review prompts, not as a requirement to add every possible item to every job.

Write reinforcement and grout as separate, connected obligations

Avoid “reinforcing by others” unless the exhibit identifies which reinforcement and which operations are excluded. A proposed allocation might put concrete footing dowels with the concrete package and CMU vertical bars, joint reinforcement, bond-beam bars, positioners and masonry grout with the mason. That is a GC packaging decision, not a universal trade rule.

State grout extent by reference to the structural details and wall schedule. Include localized conditions at jambs, bond beams, lintels, pilasters and bearings rather than relying on one typical vertical spacing note.

CMHA TEK 03-02A, Grouting Concrete Masonry Walls, explains the assembly relationship: grout bonds reinforcement and masonry, requires continuous unobstructed grout spaces and can fill selected cores or the whole wall. It also describes horizontal grout confinement. This is legacy guidance referencing 2005 standards; use it to understand the operations, not to import its numerical lift limits into a current scope.

The combined check: trace the vertical grout pattern, horizontal bond beams and local bearing fill separately, then reconcile their intersections. An area-based “partially grouted” assumption is not enough to define all three.

Do not prescribe solid grouting merely to remove uncertainty. Ask for a common base conforming to the issued design. A bidder's proposed alternative method should be separately identified, with approval requirements preserved.

Assign handoffs by operation, not by material name

A steel item can be furnished by one package and set during another package's work. A membrane can be installed by the mason while its transition to the air barrier belongs to the envelope contractor. Write those handoffs explicitly.

The following is a proposed responsibility schedule, not a standard allocation. Replace it with the actual procurement plan and obtain matching acknowledgment from the affected bidders.

InterfaceMasonry package assignment to defineMatching assignment outside masonry
CMU reinforcementFurnish and place listed wall bars, joint reinforcement and accessoriesConcrete package provides specifically identified footing dowels
Steel lintelsReceive and set identified loose lintels, if assignedSteel package details, furnishes and delivers marked pieces; attached supports separately assigned
Bearing plates and embedsSet scheduled built-in pieces and provide identified local masonry fillFurnishing trade supplies pieces and approved locations before wall construction
Through-wall flashingFurnish and install listed flashing, end dams, corners and weepsEnvelope package completes identified barrier transitions before concealment
Scaffolding and bracingProvide defined masonry access and temporary wall supportGC coordinates exclusion zones and permanent-support handoff
PenetrationsForm or build around coordinated openings and restore assigned masonryMEP supplies sleeves; designated firestop package completes specified penetration systems

Separate loose lintels from attached structural supports

“Steel lintels by others” leaves too much undecided. List the lintel marks or opening groups. Assign shop drawings, fabrication, coating, delivery, unloading, setting, anchorage and coating repair where applicable.

BIA Technical Note 28B, April 2025, distinguishes loose lintels, which are not attached to the structure, from shelf angles. UFGS separately addresses masonry lintels, precast and steel lintels, and bearing plates.

Read together, these sources support a practical packaging distinction: do not assign a loose opening lintel and an attached shelf-angle assembly solely because both are steel. Their installation handoffs are different. The estimator should verify the actual detail before allocating them.

Define flashing completion, not just flashing installation

For brick veneer over cold-formed steel framing, BIA Technical Note 28B describes a drainage path through the cavity to flashing and weeps. It also discusses connections between flashing and the water-resistive barrier. Its technical basis is TMS 402/602-2016 despite its 2025 publication date, so do not copy its prescriptive dimensions without checking the project basis.

The bid-scope consequence is more useful than a generic “include flashing” reminder. If the mason owns through-wall flashing and the envelope contractor owns the barrier, define who completes the connection, who checks it and when the mason may conceal it. Otherwise both packages can price their named material while neither prices completion of the drainage path.

Include flashings, end dams, corners, laps, terminations, drip edges and weeps to the extent required by the issued details. Do not allow an unqualified flashing exclusion to remove associated masonry work silently.

For a deeper diagnostic review rather than scope drafting, see the masonry scope gaps guide.

Make temporary work follow the support sequence

For bid-stage commercial masonry, “scaffolding included” should be accompanied by the access basis: elevations, work fronts, remobilizations, laydown, hoisting assumptions and any shared use. Decide whether the mason supplies its own access or uses a defined GC-provided system. Do not leave both possibilities in the base.

Keep wall bracing distinct from scaffolding. Under federal OSHA 29 CFR 1926.706, a limited access zone must be established before wall construction on the unscaffolded side, extending the wall height plus four feet along its entire length. Walls over eight feet must be adequately braced unless otherwise adequately supported, and bracing remains until permanent supporting elements are in place.

Illustrative coordination check: a 16-foot-high wall requires a 20-foot-wide limited access zone under that provision. If the proposed adjacent work corridor is only 12 feet wide, the pricing issue is not simply eight feet of missing space. The planned simultaneous work is incompatible with that access-zone layout. The GC and safety team must resolve the sequence or an appropriate compliant arrangement before bidders price concurrent work.

Combine that requirement with the project's permanent-support details. If masonry finishes before the roof or floor support is installed, the scope must address the intervening bracing period, inspection, maintenance and eventual removal. “Remove bracing when masonry is complete” is the wrong release condition.

Apply the same discipline to winter protection. State the planned installation window and assign enclosures, heating, fuel, monitoring and protection of completed work as required by the project. UFGS treats weather procedures and protection as part of the masonry specification. Do not let “winter protection excluded” coexist with a base schedule that assumes winter masonry unless a separate priced provision covers it.

Test the scope with one wall before issuing the package

A sample wall review exposes whether the scope defines a complete price basis. It is not a substitute for the subcontractor's takeoff.

Consider this illustrative reinforced CMU wall:

  • Length 120 feet, height 12 feet, no openings.
  • Thirty-one vertical grouted cells, with an assumed clear grout area of 0.20 square feet each.
  • Two horizontal bond beams, each with an assumed clear grout cross-section of 0.12 square feet.
  • Thirty-one intersections per beam, each overlapping the vertical-cell calculation over a height of 8 inches.

The assumptions are synthetic, not standard unit properties or design recommendations.

Vertical grout volume is `31 × 12 × 0.20 = 74.4 cubic feet`.

Horizontal grout volume is `2 × 120 × 0.12 = 28.8 cubic feet`.

Overlap is `31 × 2 × 0.20 × (8 ÷ 12) = 8.27 cubic feet`.

The reconciled geometric volume is `(74.4 + 28.8 − 8.27) ÷ 27 = 3.52 cubic yards`, before waste or procurement allowances. A bidder carrying vertical cells alone has 2.76 cubic yards. The scope-basis difference is 0.76 cubic yard.

At an illustrative marginal material-and-placement rate of $700 per cubic yard, that difference is about $532. If the missing bond beams also require a separately assumed $900 placement setup, the illustrative adjustment becomes approximately $1,432, not $532. Do not add that setup if it is already carried elsewhere.

The useful result is not the arithmetic alone. CMHA's description of horizontal grout confinement and UFGS's separate bond-beam and grout requirements show why a quantity correction may also change operations. A scope should include the required bond-beam units or preparation, confinement, reinforcement and placement, not merely authorize “additional grout.”

Competent estimators may disagree about whether to request a grout-method breakout. On a complete hard-bid design, favor a compliant lump-sum assembly with bidder means and methods. On an early GMP with unresolved grout extent, obtain a common design allowance and defined adjustment basis. Use the design-intent estimating guide when the documents have not reached that decision.

Reusable masonry bid-scope outline

Use this as a drafting structure. Replace placeholders with actual documents and responsibilities before solicitation.

General and document basis

  • Identify areas, wall types and excluded project zones.
  • Attach drawing, specification, addendum and clarification registers.
  • State required dates, work fronts, access conditions and submittal milestones.
  • Require bidders to identify deviations from the issued scope separately.

Inclusions

  • Scheduled CMU, brick and other specified units, mortar, finishes, patterns and special shapes.
  • Reinforcement, grout and bond beams according to the attached structural basis.
  • Masonry lintels and specifically assigned precast or steel lintel operations.
  • Ties, anchors, control and expansion joint components, and assigned joint sealants.
  • Flashing, drainage accessories, weeps and expressly assigned envelope transitions.
  • Built-in items, frame interfaces, bearing fill and coordinated openings.
  • Assigned insulation, sills, copings, cutting, fitting, pointing and cleaning.
  • Submittals, samples, mock-ups, temporary support, access and weather protection.

These categories follow the scope of the UFGS unit masonry guide; only project-required items belong in the final exhibit.

Exclusions and work by others

Pair every accepted exclusion with a named receiving package and an affirmative assignment. Separate furnishing from installation. Specifically resolve scaffolding, steel lintels, cleaning, winter protection, flashing, testing and grout if any bidder excludes them.

For testing, distinguish the independent agency's services from the mason's specimen preparation, access, notice, cooperation and contractor quality-control obligations. Resolve payment for each under the actual contract, not a blanket “testing by owner.”

For penetrations, identify opening formation and masonry restoration separately from firestopping. Do not substitute ordinary masonry grout for a specified penetration system through scope wording.

Clarifications and unresolved decisions

Give each open item a source, question, common bid treatment and responsible decision-maker. Do not turn a scope clarification into an unauthorized design change or override contractual precedence. Track material unresolved items using the process in how to spot scope gaps before carry.

Alternates and unit prices

Keep alternates outside the base unless the solicitation says otherwise. Define the whole change: units, mortar, ties, supports, reinforcement, grout, flashing, labor and access affected by the alternate.

Define unit prices with measurement and inclusions. An additional square foot of an identified reinforced CMU assembly is not the same adjustment as a cubic yard of additional grout. State whether rates include labor, equipment, waste, setup and markup, and whether additions and deductions use different rates. No unit price should authorize a design change by itself.

Pre-issue check

Read one typical wall, one opening and one support transition across the attached documents. Confirm that each operation has one intended cost owner, matching counterpart language and a release condition where work will be concealed or temporary support removed. Then carry the accepted scope and reconciled qualifications into the subcontract exhibit.

For wording errors beyond this outline, use the masonry scope writing mistakes guide.

Keep each masonry assignment connected to its project source

The repeatable unit is not a generic “masonry complete” paragraph. It is an assignment tied to a wall type, source detail and trade handoff. That lets the team revisit a lintel, grout or flashing decision when the underlying detail changes.

Piper Scope Generation builds trade-specific scopes from drawings, specifications, addenda and company knowledge. It keeps scope items linked to their sources and surfaces uncertain ownership, potential gaps and overlaps for review. Teams can use their existing scope structure, and affected scope can be surfaced when upstream information changes.

The estimator still decides the package boundaries, accepts or rejects qualifications and approves the scope for issue. A structured draft is useful only when the team has resolved what bidders are actually being asked to carry.

FAQ

Should masonry reinforcement and grout be included in the masonry subcontract?

Assign them explicitly rather than assuming trade custom. A practical package may include CMU wall bars, joint reinforcement, bond-beam reinforcement and masonry grout while the concrete package carries specified footing dowels. Match both exhibits to the structural details and separate masonry grout from bearing bedding materials.

Who should furnish and install steel lintels?

Decide by lintel type and installation sequence. Identify loose lintels separately from attached supports, then assign detailing, furnishing, delivery and setting. A steel-package furnishing obligation does not answer who places the piece as masonry rises. Use matching responsibility language in both packages.

Can scaffolding and winter protection be excluded?

Yes, if another priced assignment covers the required work and the common bid schedule supports that arrangement. State access and weather-protection conditions rather than leaving them open. Wall bracing has its own support-based release condition and should not be treated as interchangeable with scaffolding.

What should a masonry unit price include?

It should include a defined change to a defined assembly, measured on an agreed basis. State the unit, wall type, reinforcement and grout treatment, affected operations, setup, equipment and markup. Keep addition and deduction rates clear, and do not let a quantity-adjustment rate substitute for approval of changed design.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow