How to write a wood framing scope subs will price the same way
Define truss supply, erection, hardware, sheathing, blocking and return visits in a wood framing scope that gives every bidder the same pricing basis.
Author
Ido Gedanken, CEOPublished

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.
Book a demo- Type
- Guide
- Read
- 11 min
- Published
On this page
- Establish the document basis before writing inclusions
- Divide each assembly into supply, installation and release
- Write the structural inclusions by system, not by floor area
- Separate truss design from erection, then check the bracing basis
- Define sheathing completion without promising dry-in
- Make blocking a scheduled obligation with a return rule
- Test the scope with an illustrative pricing exercise
- Reusable wood framing scope outline
- General and document basis
- Inclusions
- Exclusions and work by others
- Clarifications and unresolved design
- Alternates
- Unit prices
- Completion and bid response
- Keep the framing assignments connected as the project changes
On a wood-frame multifamily project approaching a GMP, the rough carpentry package should define a completed framing operation, not simply a lumber list. Give every bidder the same answers to four questions: who buys the components, who installs them, who provides the design information, and what condition releases the work to the next trade.
That means naming truss supply and erection separately, assigning connectors through their attachment to the foundation, distinguishing structural sheathing from the weather-resistive barrier, and defining blocking and return visits by a documented basis. An exclusion is not resolved until another package accepts the corresponding work.
This guide is for GC estimators and preconstruction managers preparing bid scopes or subcontract exhibits for conventional light wood framing. It is not a structural design specification, a mass-timber package, or permission to resolve conflicting engineering requirements through scope language. For the wider package-development process, use the construction scope generation guide.
Establish the document basis before writing inclusions
Start with an attachment listing the issued drawings, specifications, addenda and prebid clarifications. Identify sheet numbers, revision dates and affected areas. Do not make a bidder infer whether the architectural roof plan or the revised structural roof plan is the pricing basis.
The federal UFGS 06 10 00 Rough Carpentry guide, August 2016 with Change 3 dated May 2025, covers framing, grounds, nailers, blocking and sheathing. It also includes preassembled components, rough hardware and an air infiltration barrier. Its breadth is useful evidence that a section title alone does not define the subcontract boundary. UFGS is an editable federal guide, not a requirement automatically applicable to a private project.
For the actual package, collect:
- Structural framing plans, sections, member schedules, shear-wall and diaphragm schedules, connection details and foundation anchorage details.
- Architectural plans, wall types, exterior elevations, roof details, stair sections and opening schedules.
- Issued rough carpentry and wood-truss specification sections, plus engineered-wood and treatment requirements wherever specified.
- Envelope details covering sheathing, WRB, flashing and window transitions.
- Backing requirements in casework, accessories, equipment and MEP documents.
- Applicable Division 01 requirements for submittals, access, hoisting, storage, protection, inspections and phased turnover.
Use the project's actual section numbers. Do not add a standard section that was never issued.
Keep technical requirements and commercial allocation separate. The documents establish what must be built; the scope exhibit establishes which package carries each operation. Where the design is incomplete, publish a specific pricing assumption and request resolution rather than writing a framer's interpretation into the design. The distinction is developed in pricing design intent on incomplete drawings.
Divide each assembly into supply, installation and release
A useful scope sentence names an action, a physical limit, a source and a completion condition. “Include all framing hardware” names only a category.
For example, a project-specific clause might read:
“Furnish and install the wood-to-wood and wood-to-concrete connectors identified in the attached connection schedule, including their specified fasteners. Concrete package installs cast-in anchor rods using the coordinated layout. Framing package verifies exposed rod locations before wall erection and reports discrepancies. Post-installed anchors are included only at the locations identified in the attachment.”
That clause still needs the actual schedule and agreement from the concrete package. Its value is the split between purchasing hardware, placing embedded work, checking the interface and correcting a discrepancy. Do not turn “verify” into an undefined obligation to repair another package's work.
Use one responsibility schedule for the bid package and the companion scopes. The following is an illustrative allocation, not a recommended allocation for every project.
| Assembly or operation | Framing package carries | Named companion package carries |
|---|---|---|
| Roof trusses | Receive, unload, erect, connect and install assigned restraint and bracing | Truss supplier provides components and assigned design submittals |
| Foundation connection | Furnish scheduled hold-down bodies and install exposed connections | Concrete package places scheduled cast-in rods |
| Exterior wall assembly | Install specified structural sheathing and assigned edge blocking | Envelope package installs WRB, flashings and opening transitions |
| Backing | Install structural blocking and backing in the issued location schedule | Equipment and finish trades provide attachment requirements by the stated deadline |
| Roof perimeter | Install scheduled wood nailers, blocking and framed curbs | Roofing package carries membrane, flashings and assigned manufactured accessories |
Require each bidder to acknowledge this allocation. A proposal qualification that changes it should identify the affected row and price effect, not sit beneath a general “hardware by others” exclusion.
The companion wood framing scope gaps guide addresses missing interfaces; this guide focuses on writing the issued package so those interfaces have an owner.
Write the structural inclusions by system, not by floor area
Organize the inclusion section around foundations, walls, floors, roofs and miscellaneous framing. Within each system, identify materials, installation and connections together.
Foundations and walls: list sill plates and specified treatment, sill interface materials where assigned, studs, plates, posts, headers, built-up members, opening framing, shear-wall sheathing, edge blocking, hold-downs, straps and fasteners. Reference the schedules that distinguish ordinary walls from shear-wall work.
Floors: list joists, engineered members, rim members, hangers, bridging or blocking, subfloor panels, specified adhesive, fastening and depressed-floor details. State whether stair openings, shafts, equipment openings and framed supports are included. Tie opening sizes to the issued details and coordination process.
Roofs: list rafters or truss erection, roof decking or sheathing, assigned restraint and bracing, gable framing, overhang framing, roof-edge blocking, nailers, crickets and curbs where wood-framed. Distinguish a field-built wood curb from a manufactured equipment curb.
Miscellaneous work: identify rough stairs and landings, bucks, sleepers, grounds, backing and temporary closures only where they belong in this package. The UFGS guide's product and execution lists separately address these items, structural panels, treatment, rough hardware, storage and erection tolerances. Use that as a review prompt, not text to incorporate wholesale.
Two important pricing instructions belong beside these inclusions:
- Identify the grade, species or engineered product basis and specified preservative or fire-retardant treatment. An estimator should not choose a cheaper substitution through a scope assumption.
- Assign receipt, storage protection, material handling and damaged-material treatment. A supply-only purchase is not evidence that these operations are covered elsewhere.
Separate truss design from erection, then check the bracing basis
“Trusses by others” is inadequate because it does not say whether the framer has excluded only manufacturing or the entire roof operation. Write distinct assignments for component design submittals, supply, delivery, unloading, hoisting, setting, connections, temporary restraint and permanent restraint or bracing. Identify the responsible design party for project-specific bracing information without shifting licensed design approval to the estimator.
There is a consequential version issue here. The current public UFGS rough carpentry guide still directs truss handling, erection and bracing to TPI HIB, which its reference list identifies as a 1991 publication. Separately, SBCA's current BCSI page identifies BCSI-2025 as its newest guide for truss installation and restraint/bracing recommendations.
SBCA's explanation of the 2025 changes states that permanent web diagonal brace spacing now depends on the force shown on the truss design drawing, rather than the previous recommendation of every ten truss spaces. It also describes changes to web reinforcement and piggyback-truss bracing.
The estimating consequence is not “use the newest guide regardless of the contract.” It is this: a stock bracing allowance may not represent the intended installation basis, even when the scope says bracing is included. Read the issued specification, truss submittal requirements and proposed erection basis together. If they differ, seek a designer clarification and issue a common pricing basis to bidders.
Before solicitation, record the referenced edition, available truss-design information, assigned bracing operations and treatment of unresolved requirements. At GMP stage, an identified provisional carry may be necessary. On a hard bid, use the permitted prebid clarification process rather than assuming a qualification will be acceptable.
Define sheathing completion without promising dry-in
APA's current Panel Wall Sheathing detail, DT-EWG-5, depicts structural panel sheathing with a separate weather-resistive barrier and siding. That distinction should survive into the scope exhibit. Installing the structural layer does not, by itself, establish who completes the envelope.
Write the sheathing clause with the specified panel designation, thickness, orientation, edge support and fastening basis. Then write a separate boundary for WRB, seam treatment, flashings and rough-opening transitions. If the specified system combines functions, allocate each required operation for that system rather than applying a generic “WRB excluded” sentence.
Set an agreed handoff condition: which area is released, which checks must precede concealment, which openings remain, and who protects unfinished work until the envelope package takes over.
There is also a separate protection handoff. Under current federal OSHA 1926.501, employers must assess walking/working-surface strength and provide the applicable fall protection; the regulation addresses holes and hoist areas separately. Residential construction at six feet or more above lower levels is subject to its stated protection requirement and limited exception.
Read those duties alongside the assembly detail. A floor may have sheathing installed while openings still require protection, and a wall may be structurally complete while envelope work remains. Therefore, avoid one vague “framing complete” milestone. Define structural release, temporary-protection transfer and weather-protection transfer separately. Contract cost allocation does not remove an employer's regulatory duties.
Make blocking a scheduled obligation with a return rule
Write three separate lines: structural blocking, backing for attachments, and fireblocking or draftstopping. They need different source references and completion checks.
Structural blocking belongs with the framing details and panel edge-support requirements. Backing for casework, accessories or equipment needs a location schedule and attachment basis. Fireblocking and draftstopping need their own applicable design details and materials.
The FCIA September 2024 technical presentation, using 2024 IBC and IRC definitions, distinguishes fireblocking in concealed spaces, draftstopping within concealed areas, and firestop systems protecting penetrations in rated construction. Those are educational distinctions here, not a declaration that the 2024 model codes apply to every project.
Do not use “all firestopping by framer” as shorthand for these different operations. Assign each required operation by its actual detail and confirm the adopted project basis.
For attachment backing, establish a submission cutoff and a defined return visit if needed. Competent estimators can reasonably disagree about who should install backing: the framer may be efficient before wall closure, while a later specialty installer may have better attachment information. Decide using information availability, access and closure timing, not the material being wood.
Test the scope with an illustrative pricing exercise
Consider a hypothetical multifamily package in which the GC buys roof trusses directly. All amounts below are illustrative, not market rates or customer results.
The draft framing price is $410,000. It includes walls, floors and roof sheathing but excludes truss erection, connector supply and backing for other trades. The GC's estimate also carries a $96,000 truss supply purchase. Calling the combined $506,000 a complete framing commitment would leave the excluded operations unresolved.
The GC issues a common scope attachment requiring:
- Truss unloading, erection and assigned bracing, priced at an illustrative $24,000.
- Scheduled connector supply and installation, priced at an illustrative $18,000.
- 600 linear feet of identified attachment backing at an illustrative $6 per linear foot, or $3,600.
- One coordinated backing return visit at an illustrative $1,400.
The revised framing bid is $410,000 + $24,000 + $18,000 + $3,600 + $1,400 = $457,000. With direct truss supply, the combined commitment is $553,000.
Now check the estimate's procurement boundary. If it already contains an $18,000 connector purchase allowance for exactly the same scheduled work, remove or transfer that allowance when accepting the revised framing coverage. Adding $47,000 without checking that existing carry would overstate the estimate by $18,000.
The useful check is not the addition. It is matching each scope operation to both a subcontract owner and an estimate location. Run that test before issuing the package. The pre-carry scope review guide covers the wider estimate check.
Reusable wood framing scope outline
Use this structure as an editable attachment. Fill the references and assignments before sending it to bidders.
General and document basis
Define buildings, levels and phases; list drawings, specifications, addenda and clarifications; state the bid format and exception-reporting requirements. Identify applicable access, staging, storage, hoisting and turnover assumptions.
Inclusions
Organize foundations, walls, floors, roofs and miscellaneous framing separately. For each, name supply, installation, connections, treatment, submittals, protection and release conditions. Attach the truss responsibility schedule, connector schedule and blocking/backing schedule.
Exclusions and work by others
For every exclusion, name the receiving package and retained framing obligations. “Truss supply by GC; unloading and erection by framer” is actionable. “Trusses excluded” is not. Reconcile crane, engineering, WRB, hardware and backing assignments with the companion scopes.
Clarifications and unresolved design
List the question, provisional pricing basis, responsible party, required response and estimate treatment. Do not hide unknown structural requirements inside “standard framing included.”
Alternates
Describe a complete alternate assembly and its dependent effects. State whether the price is an add or deduct to the base, what changes in procurement and whether a design approval remains outstanding. Avoid accepting a panel or truss substitution without identifying affected connections and installation work.
Unit prices
Use unit prices only for defined variable work. For backing, specify member size, treatment, location/access condition, installation and measurement basis. Separate mobilization from installed length where return visits matter. Do not use one linear-foot rate for structural changes requiring different members or connections.
Completion and bid response
Define inspection coordination, correction of the package's own work, debris removal, phased release and protection transfer. Require bidders to identify exceptions against the numbered scope items and price the requested alternates separately.
Before issue, check that each named companion package contains the matching obligation. For wording that undermines an otherwise complete attachment, see wood framing scope writing mistakes.
Keep the framing assignments connected as the project changes
A revised roof layout can change component supply, erection, bracing and connections without changing the package title. The scope should retain the connection between the source requirement, assigned operation and open decision rather than becoming a detached checklist.
Piper Scope Generation organizes drawings, specifications, addenda and company requirements into trade-specific scopes with source references. It surfaces unclear furnished-by/installed-by boundaries for review, works with company scope formats, and can surface affected scope when upstream information changes. The team still decides the trade allocation and approves the issued package.
For wood framing, that workflow is useful when it keeps truss supply, erection, connectors and blocking in the same project understanding while preserving their separate responsibilities.
FAQ
Should the framer furnish the trusses?
Either allocation can work, but the scope must separate supply from erection. Name who provides component design submittals, delivery, unloading, hoisting, setting, connections and assigned restraint or bracing. A direct GC purchase should appear alongside the framing bid in the estimate so the full operation has coverage.
Does wood sheathing include the WRB?
Only if the issued scope assigns it. Specify structural panels and envelope operations separately, then reconcile the actual system's requirements for seams, flashings and opening transitions. Define the handoff between framing completion and weather protection rather than assuming one automatically delivers the other.
How should blocking for other trades be priced?
Use an issued backing schedule with locations, member requirements and a coordination deadline. Separate that backing from structural blocking and fireblocking. Where attachment information arrives later, define the included return visit and a measurable basis for additional work instead of an unlimited promise to provide all backing.
Can a general engineering exclusion cover truss design?
Not clearly enough. Identify the assigned component-design deliverables and the responsible design party separately from the framer's installation obligations. If project-specific bracing information is unresolved, request clarification and document the pricing treatment. Do not use an exclusion to leave design-dependent installation work unassigned.
Related reading
Construction scope generation: a practical guide for GCs
How general contractors turn drawings, specifications, addenda, and company standards into trade scopes a subcontractor can price, an estimator can trace, and a senior reviewer can challenge.

Design intent is what estimators price when the drawings stop talking
Review implied assemblies and ambiguous interfaces, document the source and decision owner, and keep assumptions visible even when the drawing set appears complete.

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow