What if every bid misses it? Check proposals against the project, not each other

Bid leveling compares bidders, so work every bidder left out looks clean. A worked firestopping example and a 12-point checklist for checking proposals against the project.

Guide5 min read

Published

Steel frame of a building rising on a jobsite

Bring a current or completed project and see how Piper saves review time, surfaces scope gaps, and applies your company's knowledge.

Book a demo
On this page
  1. When the work has no package, every bid agrees
  2. Worked example: four clean bid tabs and one unpriced trade
  3. Twelve boundaries where every bidder can miss the same work
  4. What the specifications actually say
  5. Related guides
  6. Where Piper fits

If every proposal in a package leaves out the same required work, your leveling sheet shows agreement, not a gap. Check the proposals against the drawings, specifications and addenda, not just against each other.

When the work has no package, every bid agrees

A leveling sheet compares bidders. Its rows usually come from what the bidders said or from last job’s template. When every proposal leaves out the same required work, there is no difference to flag, so the tab looks clean.

The only way to catch it is to start from the drawings, specs and addenda that require the work and check each proposal against them. If every bid in a package is silent on a required item, stop comparing bids: the problem is in the documents.

There is no reliable industry statistic for how often this happens. It shows up wherever the documents assign work by cross-reference, which is most projects.

Worked example: four clean bid tabs and one unpriced trade

Hypothetical: an eight-story office building with below-grade parking in New York. A drywall package and three MEP packages, no stand-alone firestopping package. Dollar figures are illustrative.

WhereWhat it saysIf nobody connects it
Spec 07 84 00Single-source firestopping by a qualified firestop contractor, at all penetrations through rated assemblies.No package in the bid invitation is the 07 84 00 package.
Specs 22 05 00, 23 05 00, 26 05 00“Firestopping of penetrations: refer to Section 07 84 00.”Each MEP trade reads this as someone else’s work.
Drawings A-601 and A-611Life safety plans show rated shafts, corridors and slabs, with 22 UL systems scheduled.The quantity of work is on the drawings, but no scope sheet points to them.
Drywall bids A, B, CA: head-of-wall joints only, penetrations by the penetrating trade. B: firestopping by others. C: excludes MEP penetrations.All three treat penetrations alike, so the drywall spread is tight and nothing is flagged. Every MEP tab is just as consistent.
Bid dayAbout 3,000 penetrations at an assumed $45 to $80 each, plus head-of-wall joints if B is carried, is roughly $150,000 to $260,000 unpriced.Before award it is a firestop quote or one clarification to all bidders. After award it is a field fight over every penetration, and inspections can hold up closing the walls.

One gap, four packages, an exclusion in every bid, and not a single flag on the leveling sheets. Comparing the proposals to the project is what finds it.

Want to see this on your own bid? Bring one trade package and its documents. We will check the proposals against your project in the call, including the work every bidder left out. Book a project demo

Twelve boundaries where every bidder can miss the same work

Each one is a boundary, the document to read, and the question to ask before you carry the number.

  1. Firestopping. 07 84 00 against every penetrating trade. Is there a package that carries it, or does each trade point to another?
  2. Final connections to owner-furnished equipment. Division 11 schedules against 22, 23 and 26. Who supplies the disconnect, whip, valve and the last ten feet?
  3. Temporary facilities. 01 50 00 temporary power, lighting, water, heat and protection. Did a trade price it, or is it in your general conditions?
  4. Testing, inspection and retesting. 01 45 00 and each trade’s testing article. Who hires the lab, and who pays when a test fails?
  5. Cutting and patching. Division 01 and demolition 02 41 00. Who opens, who closes, and who matches the finish?
  6. Misc metals and supports for other trades. 05 50 00 and the structural notes. Lintels, embeds and equipment supports: who furnishes and who sets?
  7. Roof blocking, nailers and curbs. 06 10 00, the 07 50 roofing sections and Division 23. Carpenter or roofer, and who furnishes the curb?
  8. Joint sealants at trade transitions. 07 92 00. Window to cladding, cladding to roof, fixtures to walls: whose caulk is it?
  9. Low-voltage pathways. Division 26 against 27 and 28. Sleeves, back boxes, conduit and tray for data, security and AV.
  10. Demolition and protection of existing work. Especially on renovations and occupied buildings.
  11. Layout, hoisting, cleanup and protection of finished work. Every trade assumes another trade or the GC carries it.
  12. Anything the bid invitation never named. If the solicitation was silent, or an addendum moved the work after packages went out, every bidder drew their own boundary, often the same one.

What the specifications actually say

  • The federal firestopping guide spec requires a qualified installer and a single manufacturer and tells the contractor to coordinate with other trades, but it does not name the trade that does the work. That is left to how the GC packages it. Source: UFGS 07 84 00.
  • The VA general requirements have the contractor provide temporary buildings and utilities with its own labor and materials, without expense to the owner, so temporary facilities sit with the prime contractor unless a trade package takes them. Source: VA 01 00 00 General Requirements.
  • Demolition carries patching holes to match adjacent finishes and new supports where removals weaken existing work, which is interface work with the finish and structural trades. Source: UFGS 02 41 00.
  • The contractor performs required tests and retains an approved laboratory, an obligation that sits in Division 01 rather than in any one trade section. Source: UFGS 01 45 00.
  • Errors and omissions in the contract documents, and failing to understand contractual obligations, rank among the leading causes of construction disputes worldwide. Source: Arcadis Global Construction Disputes Report.

Where Piper fits

  • Piper compares each proposal against the trade scope and the project documents, not only against the other proposals.
  • Inclusions, exclusions, qualifications, alternates and addenda acknowledgments come out with the page they came from.
  • Missing, overlapping and unaddressed scope is flagged, including work every bidder may have left out.
  • Each finding links to the drawing, spec section, addendum or quote line it came from.
  • Your leveling format, your team’s decision on what to carry. Piper does not pick the number.

See how the bid leveling workflow works, or book a project demo and bring the documents from a bid you are working on now.

ShareLinkedInX

Related reading

Piper removes manual review from the critical path and brings project data, company knowledge, and expert checks into every preconstruction decision and workflow